Find the order that covers your project
Search the Michigan Public Service Commission’s E-Dockets by the case number or applicant’s legal name. Get the order issuing the certificate and any later orders that affect the project. Record the issue date, applicant, approved location and nameplate capacity. Section 226(9) requires the certificate to identify the facility’s location and capacity. Compare the approved site plan with your property description and the exhibit to your option, lease or purchase agreement.
Section 222 applies the state siting framework to energy storage facilities rated at least 50 megawatts with at least 200 megawatt-hours of discharge capability. Ask whether the project went through the Commission or a local authority, and request the document that applies to the actual site. A project appearing on the Commission’s application list may still be under review. Find the order showing what was decided before using an approval date.

Verify what changed the construction deadline
Start with the issue date in the certificate. Under MCL 460.1226(10), the certificate becomes invalid if construction has not started within five years, subject to the statute’s appeal and extension provisions. The developer can seek a new certificate for the proposed facility. If the developer says work already started, ask for dated records showing the work, its location and how it relates to the approved facility. Ask project counsel which work counts under the certificate.
If the certificate itself was appealed before the Commission or a court with jurisdiction, the five-year period pauses from the filing of the appeal until 60 days after a final decision that can no longer be appealed. Ask for the filing, decision and counsel’s written calculation of the remaining time. If the developer requested extra time for good cause, ask for the Commission order granting it and the revised deadline.
Check which approval you are relying on
A local permit issued through the process in MCL 460.1223(3) has its own commencement rule in subsection (4). Construction must begin within five years after the permit is granted and any challenges to the grant have concluded. The local authority can extend that timeline at the developer’s request. Ask the issuing office for the permit, any extension and the status of challenges. Use the state certificate calculation only when the project actually has that certificate.
Have the developer identify any conditions that still affect the proposed start and show where they appear in the order or permit. A project might have its state siting certificate while still working on access documents or its utility connection. Ask which unfinished step puts the greatest pressure on the requested extension and what dated record would show that it is resolved.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landDecide whether to extend the land commitment
Put the public deadline next to your signed option end date, extension notice and payment deadlines, any closing conditions, and the private definition of construction that starts rent or other payments. Ask counsel whether the extension language refers to an appeal, a construction delay or the developer’s unilateral election. If the company wants more time, ask what evidence of progress it will provide, what you would receive during the extension and when the property or any unused portion would be released.
If you are considering a sale or lease, or you hold an existing project agreement that may be assigned, share the property location, type of agreement and next deadline. Sunland welcomes inquiries from owners and authorized representatives nationwide. Keep signed agreements and detailed site exhibits available to share privately when requested.
Questions landowners ask
Does a siting certificate automatically extend my land option?
Have counsel check the signed option and amendments. The public deadline governs the certificate. Your private documents govern the option period, extension notices and payments.
Does a letter requesting an extension give a developer more time on the state certificate?
Ask for the Commission order granting an extension and the date it establishes. If the company relies on a certificate appeal instead, separately ask for the appeal record and the deadline calculation.
How do I check which parcel a certificate covers?
Request the issued order and approved site plan. Compare the project location and layout with your agreement’s legal description and exhibits, including any separately granted road or cable rights.
Sources & further reading
Sources checked 2026-11-19. Local rules and program details can change. Check the requirements for the actual project.
- Michigan Legislature, MCL 460.1226(9)–(10), certificate location, capacity and construction commencement
- Michigan Legislature, MCL 460.1223(3)–(4), local permit process and commencement
- Michigan Legislature, MCL 460.1222, facility thresholds and scope
- Michigan Public Service Commission, siting process and current application records
- Michigan Public Service Commission, E-Dockets case search instructions