Map the enrolled land and proposed work
Collect each recorded PA 116 agreement, amendments, legal descriptions, tax parcel records and any title information. Compare those boundaries with a current site plan showing panels, access roads, substations and other project improvements. Tax parcel lines and the acreage in a recorded agreement are not necessarily the same. Ask the developer to show temporary work areas and any off-site facilities as well, and ask MDARD which agreement acreage is affected.
MDARD’s process starts with the developer sending the proposed development plan and parcel list to the department. MDARD can provide a searchable list of active agreements and their legal descriptions for comparison with title information. Verify the actual recorded instruments; a developer’s map or an active-agreement list alone should not settle a boundary question.

Plan for an agreement split if needed
If the solar facility occupies less than all land in an agreement, MDARD’s solar process calls for additional split information and two split request forms: one for the solar property and one for the property remaining in the program. Provide legal descriptions for each and ask MDARD how the proposed layout will be handled. An agreement split is a program action; check separately with local officials about any land division or parcel changes that the project requires.
MDARD’s general split guidance sets minimum acreage and agricultural-use requirements for resulting parcels. Do not assume a proposed remainder qualifies: discuss the exact acreage and use with MDARD before finalizing boundaries. If a sale is contemplated, MDARD says the agreement split should be approved, signed and recorded before transfer.
Apply and complete the amendment before construction
The landowner submits the solar amendment application to the local governing body with the agreement, site plan, legal description, developer information and the required commercial agreement information and assurances. MDARD’s process addresses a compatible local ordinance under Public Act 233 of 2023 or an MPSC certificate, and says MPSC siting approval may be required when local approval is denied or no action is taken. Ask the local body, MDARD and, where applicable, MPSC which route applies to this project; an amendment is separate from other siting and construction approvals.
At least 90 days before construction, the owner contacts MDARD and supplies the required materials, including a licensed engineer’s decommissioning plan and cost estimate, financial assurance, assessor-signed taxable value information for the solar split parcel for the past seven years, and anticipated construction and decommissioning dates. MDARD prepares the amendment for signature. Construction may begin only after both the owner and state execute it and it is recorded with the county register of deeds. Build time for review, any corrections and recording into the schedule.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landUnderstand tax credits and the remaining term
The amended solar land remains enrolled, but MDARD’s process says the owner agrees not to claim Farmland Preservation tax credits on the subject property beginning in the construction year until the facility is removed and the land restored to agricultural use. Land remaining under an unamended agreement may still qualify for credits; confirm eligibility with a tax adviser. The solar deferment extends the original agreement term by the deferment period, rather than consuming the remaining agricultural term.
Ask the assessor how solar use will affect classification, taxable value and any qualified agricultural land exemption. MDARD’s March 2026 FAQ says the effect on that designation is unclear and directs owners to the local assessor. If formerly enrolled land has a PA 116 lien, the FAQ says it must be paid in full before solar construction. Early release is a separate application with its own conditions and potential repayment of credits; ask MDARD for the calculation before relying on it.
Fund removal and protect the farm
The amendment places obligations on the owner for removal, restoration to agricultural use, drainage, ground cover and financial assurance. MDARD requires a bond or irrevocable letter of credit payable to the state, maintained during the deferment period and reviewed and adjusted as needed every three years using a licensed engineer’s assessment. Its FAQ says estimated salvage or resale value cannot reduce the decommissioning estimate. The owner is responsible for removal and restoration costs not reimbursed by the surety.
Negotiate enforceable lease provisions allocating those costs and duties to the developer, including drainage repairs, monitoring, security updates and default. The required cover must meet NRCS Cover Standard 327 or the specified Michigan pollinator scorecard threshold. MDARD says grading or moving soil requires specific local and MDARD approval. After removal, MDARD says it issues an agreement without the solar provisions for the remaining original term, subject to any permitted extension. Keep copies of the recorded documents and confirm the closeout steps with MDARD.
Compare the offer with the land commitment
Ask the developer for a schedule, responsible contacts, itemized costs and a map that matches the proposed legal descriptions. Have Michigan counsel and tax advisers review the lease alongside the amendment, any farm tenancy and the agreement’s remaining term. The solar rent should be evaluated together with lost credits, taxes, construction impacts and the long-term restoration obligations.
Sunland welcomes Michigan solar land sale, lease and existing project inquiries. Share the approximate location, acreage and whether a PA 116 agreement covers the proposed area; retain sensitive agreements and financial records for secure review.
Questions landowners ask
Does solar automatically remove land from PA 116?
No. MDARD describes an amended agreement that keeps the solar land enrolled while deferring the agreement during the solar use. The amendment must be executed and recorded before construction.
Can the rest of the farm still claim PA 116 credits?
MDARD says enrolled land not converted to the solar amendment may still be used to claim credits. A split is needed to separate the solar land from land continuing in agricultural production; confirm the facts and tax eligibility.
Who pays for decommissioning?
The amended agreement makes the owner responsible for removal and restoration, including costs not covered by the required financial assurance. The owner can negotiate for the developer to assume obligations in the lease.
Sources & further reading
Sources checked 2026-11-16. Local rules and program details can change. Check the requirements for the actual project.