Map the whole earth change
Ask the developer for a plan showing the panel area, access road, equipment pads, grading, trenches, staging areas and drainage features. Mark parcel lines, slopes, lakes and streams, and work outside the fence or on neighboring land. Separate existing features from proposed work and identify uncertain locations. The fenced area alone may not describe all soil disturbance.
Take the drawing and the estimated disturbed acreage to the applicable county or municipal enforcing agency. Ask how it evaluates the full earth change, the distance to water, and whether a permit or other review is required. EGLE describes the acreage and distance tests as general rules; do not assume either that every solar layout is exempt or that a screening map decides the permit.

Identify the applicant and plan
EGLE explains that county enforcing agencies review soil erosion plans and issue permits, while approved municipal enforcing agencies administer Part 91 independently within their jurisdictions. Use EGLE’s agency directory to find the proper contact for the site and confirm which office handles the work.
EGLE’s training manual describes a landowner or designated agent submitting a soil erosion and sedimentation control plan with an application, and a designated agent applying with written landowner authorization to secure a permit in the landowner’s name. Ask the agency for its current forms, required plan details and signature requirements. Read the actual authorization and application before signing; clarify what authority is being granted.
Agree on responsibilities before access
Ask the developer who will prepare the plan, pay application and compliance costs, install and maintain controls, arrange inspections, correct problems and stabilize disturbed ground. Request copies of the submitted plan, permit and any changes, and ask how you will be notified of agency communications or violations.
Have your attorney review the sale, option or lease provisions for site access, insurance, restoration, deadlines and allocation of responsibilities, including what happens if the permit is delayed or the project ends. Private contract terms do not replace obligations imposed by the permit or law.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landCheck other requirements separately
An erosion permit is not a blanket approval for the project. Ask the agency and the project team whether construction stormwater coverage or other approvals are also needed for the specific work. EGLE says construction disturbing one or more acres generally needs stormwater coverage when stormwater discharges through a point source to state waters. Ask the project team which coverage applies.
Sunland welcomes land sale, lease and existing project inquiries from owners and authorized representatives nationwide. Share the location, approximate acreage, your relationship to the property and any known grading or water features; provide plans privately if requested.
Questions landowners ask
Is an erosion permit always required for solar?
EGLE says a permit is generally required for an earth change disturbing one or more acres or within 500 feet of a lake or stream. Ask the applicable enforcing agency about the actual project.
Can the developer apply for the owner?
EGLE’s training manual describes a designated agent applying with written authorization from the landowner. Confirm current agency requirements and review the authorization before signing.
Should I include the access road?
Show proposed road work and other disturbance outside the array on the plan and ask the enforcing agency how the complete earth change is reviewed.
Sources & further reading
Sources checked 2026-11-16. Local rules and program details can change. Check the requirements for the actual project.
- Michigan EGLE: Soil erosion and sedimentation control program, applicability and agencies
- Michigan EGLE: Part 91 enforcing agencies
- Michigan EGLE: SESC training manual, Unit 6, applications and plans
- Michigan EGLE: Construction stormwater overview
- Michigan administrative rules: Part 91 soil erosion and sedimentation control, R 323.1701