What should a landlord check when a data center tenant brings in another occupant?

A data center tenant may bring in a subtenant or grant a customer a colocation license. The signed Milam County Building 1 lease in Texas addresses both arrangements and sets specific document and notice requirements for subletting.

Could my land work?

Get the signed head lease and the proposed third-party agreement. Ask counsel which provision applies, what the tenant must deliver and who remains responsible. Check for any separate written agreement giving the third party rights against the landlord.

Check the sublease paperwork and both deadlines

Section 9(a) of the Milam lease permits qualifying subleases without the landlord’s consent. On or before the sublease takes effect, the tenant must provide an acknowledgment and affirmation from the subtenant or a copy of the sublease in a form and substance reasonably acceptable to the landlord. The document must address the subtenant’s agreement to follow the head lease for its space and the original tenant’s continuing liability.

The lease separately requires a notice after each sublease within an interval redacted in the public filing. Check the full signed lease for that deadline. Section 34(d) gives written notice procedures. Keep the signed document, notice and proof of delivery together.

Illustration of a landowner reviewing property plans

Check what rights a colocation license gives

Section 9(b) allows the tenant to grant the specified colocation licenses without prior written landlord consent. The licenses and the licensees’ use remain subject and subordinate to the head lease. The parties agreed that these licenses convey no leasehold, subleasehold or other real property interest in the premises.

Review the rights the actual agreement gives the third party. Ask counsel how that document fits the signed lease and which provisions apply to its use. If the property is being sold or the lease assigned, identify any third-party agreements and supporting documents for the closing team.

Confirm who stays responsible under the head lease

In the Milam lease, a qualifying sublease must be expressly subordinate to the head lease and future amendments. The original tenant remains fully responsible, and the sublease cannot impose new duties on the landlord.

If an event of default by the tenant occurs, Section 9(a) generally gives the landlord no duty to recognize or agree not to disturb a subtenant or other occupant. The landlord can agree to those protections in a separate written instrument. Ask for a signed copy of any such agreement and check whom it covers.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Discuss your data center property or existing agreement

Sunland accepts data center property sale, lease and existing agreement assignment inquiries from owners and authorized representatives across the United States. Share the general location, proposed transaction and next decision date. Keep leases, third-party agreements and notices for private follow-up.

Questions landowners ask

Does the Milam tenant need consent to sublet?

Section 9(a) permits a qualifying sublease without landlord consent and requires both supporting documentation and notice. Check the full signed lease for conditions and timing.

When is the sublease paperwork due?

The acknowledgment and affirmation or a copy of the sublease is due on or before the sublease takes effect. The agreement separately sets a post-sublease notice interval, which is redacted in the filed copy.

Does a sublease release the original tenant?

The Milam lease keeps the original tenant fully liable for its obligations. Ask counsel to check the particular agreement and any later amendment or written recognition.

Sources & further reading

Sources checked November 21, 2026. The public lease redacts the post-sublease notice interval. The reviewed records leave any actual sublease, colocation license, third-party occupancy, notice, default or written recognition unverified. Local rules and program details can change. Check the requirements for the actual project.

Want to ask about your land?

Send the location and what you know about the property. You don’t need a project plan, and you are not committing to a lease or sale.

Tell us about your land
Have land in Texas?Tell us about your land