Compare the right with both fields
Find the relevant right or rights through DNRC’s Water Right Query System and obtain current abstracts and available maps, permits, decrees or change authorizations. DNRC advises searching for rights appurtenant to the property as well as by listed owner. Note the right number, owner, source, purpose, place and period of use, point of diversion, flow rate, volume and any conditions. Ask the regional office about records you cannot locate or reconcile.
On a map, show the solar footprint, historically irrigated acreage, the recorded or mapped place of use and the field proposed for irrigation. Show ditches, pumps, pivots, access and any proposed changes to delivery or diversion. Label approximate boundaries and discrepancies. A map or abstract is a starting point for review, not by itself proof that a proposed new use is authorized.

Ask DNRC before moving the water
DNRC says a change in place of use, point of diversion, purpose or place of storage may be authorized if applicable criteria are met, and that a change application is not required in every scenario. Explain precisely where and how irrigation would move, including acreage and any changes to the system. Ask whether the proposal requires a change authorization, which right or rights are involved, and what process applies before using water in the new arrangement.
DNRC recommends contacting the regional office to schedule a scoping meeting before requesting a preapplication meeting or submitting an application. If a change authorization is required, obtain it before making the change. Approval is not automatic: DNRC may approve a proposal in whole, in part or with conditions, or deny it.
Document historical use and delivery
Bring irrigation maps, crop and acreage records, photographs, diversion and pumping records, and information about the equipment and delivery system. DNRC says an applicant for a change must establish historical use to show that the proposed use will not require or consume more water than historically used. The relevant historical period depends on the type of right. Ask DNRC which evidence and technical analysis are needed for your situation.
If water is delivered by an irrigation district, ditch company or water users’ association, discuss the proposed shift with that entity as well. DNRC notes that a customer of such a system may not hold an individual water right for the use. Contracts, delivery arrangements and permissions may also matter; do not assume an individual abstract tells the whole story.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landCoordinate the solar agreement with the water plan
Review the option or lease with a Montana water-rights attorney. Address the existing irrigation facilities, access for operation and repairs, allocation of costs, timing and responsibility for any application, and what happens if an authorization is delayed, conditioned or denied. Coordinate with the farm operator and developer before accepting a footprint that depends on moving irrigation.
A solar project does not itself transfer, expand or cancel a water right, and this guide does not determine its status or the effect of a particular agreement. Sunland welcomes land and existing project inquiries nationwide. Share the location, approximate acreage and your relationship to the property, along with the irrigation question; provide records privately if requested.
Questions landowners ask
Can I irrigate another field with the same water right?
It depends on the right, its place of use and the proposed operation. Compare the records and maps with both fields and ask DNRC whether a change authorization is required before making the shift.
Does leasing land for solar automatically change my water right?
No. A solar proposal or lease does not itself authorize a change in the place or purpose of water use. Have counsel review the agreement and discuss your actual plans with DNRC.
What should I bring to DNRC?
Bring right numbers and abstracts, available maps and authorizations, records of historic irrigation, and a drawing of the existing and proposed fields and delivery system. The regional office can explain what further evidence is needed.
Sources & further reading
Sources checked 2026-11-15. Local rules and program details can change. Check the requirements for the actual project.