Check which easement crosses the site
Compare the recorded grant, title information and a survey of the existing drive with both layouts. Identify the property served and who holds the right. Nebraska’s court process excludes public utility, conservation and negative easements, as well as easements or rights-of-way held by specified irrigation and public power entities or canal companies. A proposed location can also be ineligible if it encroaches on conservation easement land or interferes with specified other easements.
Ask counsel whether a negotiated relocation is possible and what should be signed and recorded if the parties agree. If they cannot agree, a court can approve a move only if the owner of the land burdened by the easement establishes eligibility and meets the statutory conditions. Nebraska also provides that an agreement cannot waive that statutory right, even if the original easement fixes the location or calls for the holder’s consent before an amendment.

Compare what the neighbor would have at the replacement route
For example, moving a private drive to the edge of the battery parcel may free the equipment area while giving the neighbor a longer trip or changing how deliveries reach its property. Compare the current and proposed route with the neighbor’s actual uses, along with access during the move. Ask counsel to check the statutory tests, including utility, burden, safety, the purpose of the easement, disruption and effects on affected property and recorded interests.
Nebraska assigns reasonable expenses of a move under the Act to the owner of the land crossed. The list includes required improvements, mitigation of access disruption, applicable permits, title and recording work and any increase in maintenance costs. If the developer offers to cover the move, have counsel review whether the reimbursement covers those continuing costs as well as the new drive. Compare those figures with keeping the current drive and adjusting the battery layout.
Match possession to the effective relocation
The statutory process requires a civil action. Ask counsel to identify who must be served, including the easement holder, recorded security interest holders on either property, recorded lessees of the property served by the easement, and holders of certain recorded interests the new route would encroach on. Counsel can check which exceptions apply before you set a closing date.
A certified copy of an order approving relocation must be recorded before the owner proceeds with the relocation. When the order requires no new improvement, recording the order constitutes relocation. If the order requires a replacement drive or other improvement, the owner records a relocation affidavit and sends a copy by certified mail to the holder and parties to the case after the work is substantially complete and the replacement is usable.
In that second case, the holder can use the old route until the affidavit is recorded and sent, subject to the court’s order. Ask counsel and the title company what proves that the old route is available for the battery footprint. Make the sale or lease describe the affected area, what approvals and documents are needed and what happens if the developer must wait or redesign.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landDiscuss your battery storage proposal
Sunland welcomes inquiries nationwide from owners and authorized representatives about selling or leasing battery storage land or assigning an existing agreement. Share the general property location and whether an existing private drive affects the proposed layout. Keep surveys, title records and signed agreements for private review.
Questions landowners ask
Can an easement holder’s refusal end the relocation discussion?
Ask Nebraska counsel about the statutory court process. Only eligible easements qualify, and the landowner must establish that the proposed relocation meets the statutory conditions.
Does the court order alone free the old driveway for construction?
When the order requires a replacement improvement, check substantial completion, usable access, the recorded affidavit and certified mailing, along with the terms of the court order. When the order requires no improvement, recording the order constitutes the relocation.
Sources & further reading
Nebraska’s current statutes were checked November 20, 2026. The driveway and battery layout are hypothetical. Eligibility, the effective move and the terms of any order depend on the actual property, easement and relocation proposal. Local rules and program details can change. Check the requirements for the actual project.
- Nebraska Legislature, Neb. Rev. Stat. § 76-2,129, scope and exclusions
- Nebraska Legislature, Neb. Rev. Stat. § 76-2,130, conditions for relocation
- Nebraska Legislature, Neb. Rev. Stat. § 76-2,131, civil action
- Nebraska Legislature, Neb. Rev. Stat. § 76-2,132, court findings and recorded order
- Nebraska Legislature, Neb. Rev. Stat. § 76-2,133, relocation expenses
- Nebraska Legislature, Neb. Rev. Stat. § 76-2,135, relocation affidavit and prior access
- Nebraska Legislature, Neb. Rev. Stat. § 76-2,137, nonwaiver