Locate the claim and the entire project
Use NJDEP’s NJ-GeoWeb claim line as a screening tool, and obtain the adopted claim map and relevant conveyance records. Gather the current deed, title commitment and exceptions, survey, historic descriptions, prior riparian grants and their plans, and any tidelands licenses or correspondence. A land deed alone does not establish that the State conveyed its tidelands interest; compare the actual state instrument and its description with the land being offered.
Have a surveyor plot the parcel and the claim and grant boundaries against the proposed battery pad, cable trench, equipment, access, staging, grading and restoration areas. Check each parcel and crossing, including land controlled by others. Mapping is a starting point: an apparent overlap or absence on a screen should be reconciled with the adopted maps, instruments and site-specific evidence before assigning acreage or value.

Distinguish a license from a grant
NJDEP describes tidelands as lands now or formerly flowed by the mean high tide of a natural waterway. Filling formerly flowed land does not itself remove the state claim. NJDEP describes a riparian grant as a deed selling the State’s interest in formerly flowed tidelands; its current policy is to issue grants only for filled tidelands. A grant is not mandatory, but may be sought to clear title to a claim. Confirm the area and terms of any existing grant rather than assuming it covers the entire parcel.
A tidelands license is a short-term rental for use and occupation of state-owned tidelands. NJDEP says licenses can also apply to formerly flowed land and lists utility-related structures, including cable lines crossing over or under state-owned tidelands, among uses requiring a license. Give NJDEP the actual pad, cable and construction plans and ask what authorization applies. An existing license should be checked for its area, use, term and conditions; it is not a deed conveying the State’s interest.
When a Statement of No Interest may fit
NJDEP describes a Statement of No Interest as its official confirmation that a particular area is free of state tidelands claims, with the burden on the applicant to prove this beyond all doubt. It considers applications in specified circumstances, including when a claim is close to the property or the adopted map shows a claim whose validity is questioned. An undefended shoreline augmented by natural accretion is another listed circumstance.
NJDEP says it will not consider a Statement of No Interest where a valid existing conveyance, such as a riparian grant, has eradicated the mapped claim; if the conveyance’s validity is in doubt, NJDEP directs applicants to submit a grant application. Ask counsel and NJDEP which path fits the evidence. A Statement of No Interest is not a substitute for buying or renting an unresolved state interest.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landResolve the affected area before committing
Ask the developer to identify the minimum usable area and alternative pad or cable alignments. Obtain a title and survey review and NJDEP input on unresolved areas before fixing the price, acreage, site-control boundary or an unconditional promise to deliver a route. A change in layout may affect interconnection, access and other property rights as well as tidelands review.
Have counsel address who pays for surveys, title work, applications and any state consideration, who obtains the necessary instruments, and what happens if an acceptable boundary, authorization or closing cannot be achieved on schedule. Check separate land-use, environmental and construction permits; tidelands property rights and regulatory approvals are different questions.
An owner or authorized representative can ask Sunland to screen a battery storage sale or lease, or submit an existing project for review. Share the location, approximate acreage and known claim or route issue; provide title and survey documents privately when requested.
Questions landowners ask
Does a filled industrial parcel avoid a tidelands claim?
Not necessarily. A claim can cover land formerly flowed by the tide even after it has been filled. Compare the claim and any prior state grant with the actual parcel and project footprint.
Does a tidelands license clear title?
No. NJDEP describes a license as a short-term rental for use and occupation of state-owned tidelands. Review its terms and area for the proposed use.
Can I request a Statement of No Interest because a prior grant cleared the claim?
NJDEP says it will not consider one when a valid existing grant has eradicated the claim. If the grant’s validity is in doubt, NJDEP directs applicants to submit a grant application.
Sources & further reading
Sources checked 2026-11-16. Local rules and program details can change. Check the requirements for the actual project.