Get the letter and map the whole proposal
Gather the issued LOI, every referenced plan or map, NJDEP file and activity numbers, any extensions or later correspondence, and available permit and waiver decisions with their approved plans and conditions. Ask the prior applicant or consultant for the complete file if the owner has only a cover letter. Confirm the property and tax lots shown and whether the determination remains valid; do not assume an old letter or an application receipt is a current decision.
Overlay the latest surveyed project plan on the LOI plan at the same scale and coordinate basis. Include the battery equipment and pad, fence, grading and drainage, access road and turning areas, cable trench to the interconnection point, temporary workspace, staging and restoration. Check routes on neighboring land as well as the offered parcel. A road or cable outside the area addressed by the LOI remains an open question even if the pad fits inside it.

Read the type and limits of the determination
A presence/absence LOI says whether wetlands, State open waters or transition areas are present in the area determined; it does not locate their boundaries. NJDEP also offers a footprint-of-disturbance presence/absence LOI for a defined part of a site of no more than one acre. Its answer applies to that footprint, not the rest of the property. NJDEP allows multiple portions subject to separate fees and a limit of three such LOIs for one site. Compare the actual road and cable work, including temporary disturbance, with the defined footprint.
A line delineation identifies boundaries on an eligible site or tax lot of one acre or less; NJDEP delineates the lines. For line verification, an applicant supplies a proposed delineation that NJDEP confirms or modifies; it can cover a site of any size. A partial line verification is restricted to particular publicly owned sites. Read the issued decision and plan to identify its actual area, verified lines and resource value rather than treating every LOI as a whole-parcel clearance.
Separate the determination from permission to build
An LOI is a jurisdictional determination, not a construction permit. Wetlands, State open waters and transition areas can restrict work even when a project avoids the wetland edge. NJDEP says regulated impacts require appropriate authorization before disturbance. Ask the consultant to identify potential impacts and which permit, transition area waiver or other authorization applies to each portion of the proposed road and the rest of the design.
If an earlier project has a permit or waiver, compare its authorized activities, footprint, term and conditions with the battery proposal. A determination that covers the area does not itself authorize a road or trench, and an earlier permit should not be assumed to authorize a different layout or use. Have the consultant and counsel consult NJDEP about the proper application or modification before work starts, including clearing, grading or temporary access.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landSet the next decision around the missing area
If the proposed work extends beyond the LOI or the letter is expired, unclear or inconsistent with site conditions, ask the consultant and NJDEP what new determination or extension is appropriate. NJDEP describes its mapping as an approximation, not a regulatory determination. Its permit-process guidance says decisions are generally valid for five years and some may be extended; verify this specific decision, any extension and applicable current rules rather than assuming a date.
Ask the developer for alternate pad and route layouts and a schedule for survey, agency review and potential permits. In the sale or lease, have counsel address access for investigation, who pays for applications, responsibility for obtaining approvals, deadlines and what happens if the route or needed authorizations cannot be obtained. Avoid committing to a fixed buildable area until the remaining questions are resolved.
An owner or authorized representative can ask Sunland to screen a battery storage sale or lease, or submit an existing project for review. Share the location, approximate acreage and known LOI or route issue; provide the letter and plans privately when requested.
Questions landowners ask
Does a presence/absence LOI show the wetland boundary?
No. It identifies whether regulated features are present in the area determined, but does not locate their boundaries. A line delineation or verification provides boundary information within its scope.
Can the battery pad be covered while the access road is not?
Yes. A footprint-of-disturbance LOI addresses a defined portion of a site. Compare the pad, road, cable route and temporary work areas with its actual plan.
Does an LOI allow construction?
No. An LOI is a jurisdictional determination. Regulated work may need a separate permit or waiver before disturbance, even when an LOI has been issued.