Map the temporary work and identify who controls the land
Ask the engineer and contractor to mark the property line, proposed battery pad, excavation, cable route, equipment swing and any area needed beyond the boundary. A survey of existing conditions, vibration or crack monitoring, protective covering, scaffolding, shoring or limited staging can require separate access. Confirm which activities are actually necessary, their duration and whether a workable design on the project parcel would avoid entry.
Check title, surveys, leases and occupancy to identify the adjoining owner and affected tenants. A developer’s option or lease for the battery site does not itself authorize access to a neighbor’s parcel. Do not enter, place equipment or project into adjoining airspace on the strength of a preliminary discussion.

Try a written construction license first
Provide the neighbor with a site plan, scope, proposed dates and contact for questions. Counsel can document a voluntary license identifying who may enter, the exact area and permitted activities, notice and working hours, protection of operations, insurance, compensation, responsibility for damage and restoration, equipment removal, and a definite end date or extension process. Record baseline conditions together and agree how claims and disputes will be handled.
Allow time for the neighbor and its advisers to review plans and coordinate tenant access. Do not assume a verbal agreement, a permit to build on the project parcel or an offer to pay grants entry. A negotiated license can address the actual construction sequence and minimize interruptions to the neighbor.
Understand the court route if access is refused
Under RPAPL 881, an owner or lessee seeking improvements or repairs may bring a special proceeding if the work cannot be done in a commercially reasonable manner without entering adjoining property and permission has been refused. The petition and any affidavits must state the facts making entry necessary and the proposed dates. The statute also treats more than one written notice served by certified mail on the owner without response within 60 days as a refusal. Have New York counsel evaluate the facts, parties, notices and timing; the court grants a license in an appropriate case on terms justice requires.
The law lists possible purposes including surveys, monitoring, scaffolding and protective measures. A court license under the section is unavailable where the adjoining property is owned, leased or otherwise occupied by a New York state entity as defined in the statute. A refusal or silence does not authorize self-help entry while a proceeding is pending.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landBudget for conditions and separate permanent rights
Section 881 requires conditions including reasonable prior notice subject to the statute’s emergency exception, a duration based on a good-faith projection, relevant work documents, specified commercial general liability insurance documentation and reasonable compensation for loss of use and enjoyment including diminution in value. The licensee is liable for actual damages resulting from entry. The court may also order reimbursement of reasonable document-review fees and impose other appropriate terms. Ask counsel and the project team to budget for protections, review, compensation, restoration and possible schedule extensions.
Temporary construction access is different from a lasting cable easement, permanent equipment or continuing operational access across a neighbor’s land. Identify any ongoing rights separately and negotiate the needed instrument and approvals with counsel; do not assume a temporary court license supplies them. Sunland reviews battery storage land opportunities nationwide. Share the New York location, acreage and known access constraints, and provide sensitive plans privately if requested.
Questions landowners ask
Can the developer enter if a neighbor refuses access?
Not without permission or another legal basis. Section 881 allows an eligible owner or lessee to ask a court for a license in an appropriate case; it does not itself authorize immediate entry.
Can the court license cover monitoring or scaffolding?
The statute lists monitoring devices, protective structures and scaffolding among possible purposes, subject to the statute and the court’s terms.
Does temporary access create a permanent cable easement?
Do not assume it does. Identify and separately negotiate any permanent rights needed for the project.
Sources & further reading
New York Real Property Actions and Proceedings Law section 881, including its February 2026 revision, checked November 16, 2026. Local rules and program details can change. Check the requirements for the actual project.