New York landowner guide

Can I carve out a battery storage pad from property in an IDA leaseback?

A New York business may have room for a battery energy storage system (BESS) beside its operating facility, but an industrial development agency (IDA) may hold a recorded interest covering that ground. In one structure the company leases the property to the IDA, which leases it back to the company. The proposed pad must be examined within that chain even if the business continues operating on the rest of the site.

Could my land work?

Start with a title review and survey of the proposed pad and its access and utility routes. With New York counsel and the IDA, determine whether a surveyed partial release or reconveyance can remove the pad from the agency’s interest, whether an arrangement within the existing project documents is possible, or whether to select another location or wait. Separately resolve the continuing project, payment in lieu of taxes (PILOT) and potential benefit-recovery consequences. A tax-lot split or lender release alone does not remove an IDA leasehold.

Trace the property interest before offering the pad

Draw a simple chain showing who holds fee title, who granted the company-to-IDA lease and who holds the IDA-to-company leaseback. The owner may be both the original lessor and the leaseback tenant. Some projects instead involve agency-held fee title. Obtain a current title report, deed, recorded leases or memoranda, amendments, purchase or reconveyance provisions, easements and legal descriptions; do not infer the structure from the PILOT bill alone.

Map the proposed fenced pad, construction and maintenance access, cables, utility corridor and temporary work areas against each recorded description. Confirm the entity authorized to act for the operating business and contact the IDA and its counsel. New York law permits agencies to acquire and dispose of property interests and enter leases, but that authority does not promise a release for a particular project.

Illustration of a land parcel and surrounding landscape

Compare a partial release with an arrangement inside the project

For a sale or independent lease outside the existing arrangement, ask whether the IDA will release its interest over the identified land and what instruments are necessary on both sides of the leaseback. The company, agency, proposed buyer or developer and any lender may each hold different rights. A partial release must describe precisely what remains and what is removed; it does not automatically amend every other agreement.

Alternatively, ask whether the proposed use or sublease can be accommodated under the existing documents and what approvals or amendments that structure would require. That choice may leave the pad inside the IDA project and its obligations. Actual documents and agency decisions govern; there is no single statewide consent form or guaranteed timetable for every private transaction.

Make the surveyed release and title work a closing deliverable

Have a surveyor prepare the proposed carveout and retained area, with legal descriptions and any needed access, utility and drainage easements. Have title counsel compare those descriptions with the company-to-IDA lease and leaseback, identify all instruments to amend or release, and arrange execution and recording as appropriate. A subdivision, separate tax lot or lender’s partial mortgage release does not itself remove a recorded agency leasehold.

A May 2024 Tompkins County IDA agenda packet illustrates the distinction: an unsigned proposed partial release described a 1.39-acre area to be removed from a company-to-agency lease while the remaining leasehold continued. It is an example of a proposed instrument, not proof that the release was executed or a procedure required statewide.

If the agency holds fee title, a lease release alone may not convey that title. Counsel should establish the required deed or other reconveyance route and any purchase-option conditions. Obtain the executed instruments and updated title evidence; an agenda item or resolution alone does not establish that the pad has been released.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Protect the operating project and its financing

Compare the carveout with the original project’s approved use and operating needs. The retained facility may need truck circulation, parking, fire access, setbacks, drainage, utilities and expansion space. Identify shared infrastructure and grant workable rights over both parcels where needed. Confirm any changes to project plans or permitted uses with the relevant parties.

Review mortgages, financing agreements, guarantees and other recorded interests separately. A lender may require its own consent, partial collateral release or payment. Coordinate the sequence of IDA instruments, lender documents, subdivision approvals and recording with the title company so that the buyer receives the agreed interest and the remaining business retains the rights it needs.

Resolve PILOT and benefit consequences separately

Collect the executed PILOT, project and financial assistance agreements, agency resolutions, reporting records, notices and the IDA’s applicable policies. Ask the IDA for its assessment of the retained project, any required amendment, future PILOT calculation, outstanding obligations and potential recovery of benefits. General Municipal Law section 874 addresses agency policies for modifying assistance and recovering benefits; the actual facts and documents matter. A pad sale is not automatically a recapture event.

Keep property-tax and contractual consequences distinct from state sales and use tax recovery under section 875, which addresses specified unauthorized or excessive exemptions and material misuse. Paying an agreed amount does not itself clear the IDA’s recorded real-property interest. Conversely, recording a release does not by itself settle every surviving PILOT or project obligation.

Allocate application, survey, legal, recording and any agreed benefit costs between seller and buyer, and provide for unresolved amounts and a denied request. Private allocations bind their parties as agreed; they do not alter the agency’s rights. Do not assume the end of a PILOT term automatically clears title or every surviving commitment.

Choose a practical path for the BESS proposal

The existing business’s IDA benefits do not automatically cover a new battery developer. New York’s tax guidance ties sales-tax exemption authority to the appointed agent and authorized project purchases. Ask the agency and tax advisers about any separate appointment or assistance request; neither an existing appointment nor the location alone establishes an exemption for the developer.

Set diligence and closing conditions that allow time for the agency decision, required instruments, lender action, subdivision and title review. If the proposed release is unavailable or too costly, compare a site outside the agency interest, a permissible arrangement within it, a smaller footprint or waiting. Investigate zoning, fire access, permits and interconnection separately; neither an IDA property release nor existing benefits approve a battery project.

Sunland considers land for sale or lease and existing agreements nationwide. It may contract for an opportunity and then assign it to a specialist, subject to the agreement’s terms. An owner or authorized representative can share the location, acreage, operating use and known IDA structure, and provide project documents privately when requested.

Questions landowners ask

Does creating a separate tax lot release the pad from the IDA lease?

No. A tax-lot split does not itself remove a recorded leasehold. Have counsel identify, execute and record the necessary property instruments and verify title.

Will a pad sale automatically require repayment of IDA benefits?

No. Consequences depend on the applicable law, agency policies, project documents and facts. Ask the agency and advisers to assess the proposed change and continuing project.

Can the battery developer use the existing business’s sales-tax exemption?

Do not assume so. Exemption authority depends on the appointed agent and authorized project purchases. The agency and tax advisers should evaluate the developer’s proposed purchases and any separate appointment.

Sources & further reading

Sources checked 2026-11-18. Local rules and program details can change. Check the requirements for the actual project.