Find the terms for the existing battery
Confirm which utility serves the project and whether the New York State Standardized Interconnection Requirements apply. The requirements cover eligible systems of 5 megawatts or less connected in parallel with the utility distribution system. Section I.E addresses existing stand-alone storage and storage paired with generation.
Get the signed agreement, Attachment I and any later changes. Identify the utility’s interconnection customer and ask the buyer to describe which operating terms its proposed purchase depends on. For example, if the buyer plans to charge from the grid at times the signed attachment limits, ask the utility and project advisers to compare the current and proposed terms before pricing that change.

Ask what the utility must review
Section I.E calls for a completed Appendix K to start utility review of proposed changes to the operating characteristics of an existing interconnected system. The utility addresses the proposed terms in its technical review and determines whether a further protection and control review is required. Ask who will handle the filing and what the utility expects for review costs, timing and any utility construction.
For proposed changes to the characteristics listed in Appendix K, Section I.E also calls for an amendment to incorporate revised Attachment I and payment of applicable utility construction costs. The applicable standard contract requires amendments in writing signed by the utility and customer. Request the signed amendment, its revised attachment and confirmation of any outstanding conditions before relying on the new terms.
Decide what must be ready at closing
Ask whether the buyer would still close if the system could continue only on its existing terms. If the change is part of the buyer’s valuation, agree what utility outcome is acceptable, who pays review and utility costs, and what happens if a decision or amendment is delayed. Identify the party who can submit the request and sign before or after the transaction.
Have counsel check the interconnection agreement and land documents for a change in the utility customer or leaseholder. If a deal includes an assignment, establish which records show that change and which show approval of new operating terms. Compare any pending utility requirements with the dates for possession, payment and the first planned operation under the new terms.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landDiscuss your battery project or land agreement
Sunland welcomes inquiries nationwide from owners and authorized representatives about selling or leasing battery storage land or assigning an existing agreement. Share the general property location, the proposed transaction and whether it depends on a utility change. Keep signed agreements, utility attachments and project records for private review.
Questions landowners ask
Can the utility require review if the equipment stays the same?
Section I.E addresses changes to operating characteristics of an existing battery. Ask the utility to compare the actual proposed use with the signed agreement and determine the applicable review.
Does submitting Appendix K settle the new operating terms?
Appendix K starts the review. Check for the signed interconnection amendment, revised Attachment I and any conditions the utility still needs the parties to meet.