Check what the existing guaranty covers
Compare the exact legal names of the tenant, the current guarantor and the proposed guarantor. Identify who can enforce the guaranty and which obligations it covers, such as rent, damages or performance of restoration work. Review any caps, exceptions, notice requirements and expiry terms. Keep the guaranty alongside any bond or letter of credit and check which protection applies to each obligation.
Read the proposed assignment or ownership change alongside the lease’s provisions on assumption and guaranty replacement. Section 23 of the signed Cassel battery ground lease in Brookhaven requires a defined qualifying successor using that provision to agree in writing to assume the lease obligations, including providing a parent guarantee. Review the actual transfer structure before applying that requirement.

Identify the event that ends the old guaranty
Section 51.02 of the Cassel lease allows a replacement with a legal entity that has at least $50 million in assets under management. The tenant must deliver written notice to the Town of Brookhaven together with an executed guaranty substantially in the form attached to the ground lease. Under that clause, delivery of a qualifying replacement package is the point at which the old guaranty is deemed to end automatically.
Ask what records show that the replacement entity itself meets the metric in your lease and when those records were prepared. Assets under management are the measure in the Cassel clause. Review the proposed guarantor’s assets, liabilities and what resources it could use to pay or perform separately. Compare the proposed guaranty line by line with the required form and current signed guaranty.
Document the handoff before acknowledging it
Confirm who must sign and receive each document, how the replacement becomes effective and which notice provision applies. Ask counsel whether your acknowledgment confirms receipt or also agrees to a release or changes the lease. If the lease lets the tenant replace the guaranty by delivering specified documents, have counsel check whether the package meets those terms.
Check how both guaranties and any proposed release address amounts already due, unresolved defaults and duties that survive the transfer. If the parties are negotiating the timing, specify what must be delivered before the old protection ends and what happens if the package is incomplete at closing. Keep both signed guaranties, the dated notice, proof of delivery and any separate release in the closing file.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landDiscuss the ground lease or transfer
Sunland reviews battery storage land sale, lease and existing project agreement inquiries across the United States, including potential assignments. Share the site’s location, approximate acreage, your role and the proposed guaranty or transfer deadline. Keep signed agreements and private financial records available for follow-up.
Questions landowners ask
Does a buyer taking over the lease replace the parent guaranty?
Check the transfer and guaranty provisions for the specific agreement. In the Cassel example, the replacement clause calls for written notice and delivery of a qualifying executed guaranty.
Does the Cassel lease require a guarantor with $50 million in cash?
The contract metric is at least $50 million in assets under management. Ask what financial records establish the proposed entity’s eligibility and review its ability to honor the guaranty separately.
Will the old guarantor still cover an earlier problem?
Have counsel compare the current and replacement guaranties and any release. Resolve how unpaid amounts, existing claims and surviving obligations are treated before acknowledging the change.
Sources & further reading
Sources checked November 20, 2026. The Cassel example describes the terms of the signed ground lease. The attached guaranty exhibit bears Agilitas Energy’s signature and leaves its date fields blank. Verify delivery, the effective date and any replacement in the signed transaction file. Local rules and program details can change. Check the requirements for the actual project.