New York landowner guide

Can you use land over a New York gas storage reservoir for battery storage?

A landowner may own the surface above an existing underground gas storage reservoir while another party holds rights in the formation. A battery energy storage system (BESS) may be possible, but the reservoir boundary alone does not identify what can be built or where the gas operator may enter.

Could my land work?

Collect the deed, storage lease or easement and related recorded instruments, and have New York counsel and the project team map the actual rights against a proposed battery layout. Separate subsurface storage rights from rights to wells, pipelines, roads and surface access. Coordinate proposed construction and continuing access with the operator, and resolve any needed consents or changes before committing the site.

Separate ownership of the land, formation and stored gas

Start with a title search and the full chain of deeds, reservations, leases, easements, assignments and any court or other instruments affecting the parcel. Identify who owns the surface, who holds the relevant subsurface interest and which entity currently holds the storage rights. A production lease, a storage grant and a surface easement may be different documents held by different parties; a tax map or a field boundary is not a substitute for their terms.

New York Environmental Conservation Law section 23-1307 states that previously possessed gas lawfully injected into an underground storage reservoir belongs to the injector and its successors or assigns, subject to the statute’s treatment of native reserves. It does not itself give an operator storage rights. The section also says a production lease does not include oil or gas storage rights unless it grants them, while expressly preserving the applicable rules for leases made before October 1, 1963. Have counsel evaluate the actual instruments and their dates.

Illustration of a land parcel and surrounding landscape

Map operator rights and the proposed battery footprint

Ask the operator for its current contact, available field and facility information, and the locations of known injection, withdrawal and observation wells, buried lines, access roads and other equipment. Have a surveyor and engineer compare those features and the recorded rights with the proposed fenced area, foundations, trenches, cable route, drainage, construction staging and emergency access. Confirm underground locations through the appropriate utility-location process before ground disturbance; records and markings may not tell the whole story.

Read the actual grants for the location and scope of entry, road use, maintenance, additional facilities, restrictions and any consent or notice requirements. A reservoir can extend under many parcels without a surface facility on each one, and FERC notes that some storage-field parcels may involve only subsurface rights. Do not assume either that the whole surface is unavailable or that an empty field means there are no access rights. Keep the operator’s existing rights usable and ask how proposed foundations, heavy loads, excavation and access changes would affect operations.

Resolve compatibility before signing away flexibility

Discuss the preliminary plan with the operator and the battery developer early. Ask for written identification of conflicts, required setbacks or operating clearances, crossings, emergency access and any consent or amendment needed under the applicable documents. The project engineer, operator and relevant authorities should determine requirements for this site; there is no universal clearance supplied by the reservoir boundary alone. Move the pad, fence or cable route if needed, and document agreed access, protection, maintenance and responsibility for damage.

Determine which agencies regulate the particular gas facility and battery project. FERC describes its role for interstate natural gas facilities and storage fields; not every storage facility is under FERC jurisdiction. Where applicable, its eLibrary and project docket may provide useful records, while state and local records and permits may also matter. A regulatory filing or approval does not replace a review of the property rights and site-specific agreements.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Choose a land transaction that matches the rights you can convey

Compare a fee sale with an option or lease for the battery footprint and any required access and cable rights. In each case the buyer or developer needs a clear picture of the interests it will receive and the existing gas rights that remain. Review title exceptions, permitted uses, operator coordination, consent conditions, responsibility for securing approvals and what happens if a workable layout cannot be agreed. Do not promise an unencumbered site without confirming title.

If an existing option or lease will be assigned to a specialist, have counsel check its assignment clause, required consents and any continuing obligations; an assignment does not automatically release the original party. Sunland reviews battery storage land opportunities nationwide, including in all 50 states, for potential sale or lease. Sunland also reviews existing battery storage options, leases or projects for possible assignment to a specialist. Share the location, acreage, known gas operator and available title documents privately for an initial discussion.

Questions landowners ask

Does a gas storage reservoir make the entire surface unusable?

Not necessarily. The recorded rights, facilities, access needs and applicable requirements must be compared with the proposed battery layout. Some parcels in a field may involve only subsurface rights.

Does an old gas production lease automatically grant storage rights?

Section 23-1307 says a production lease does not include oil or gas storage rights unless it grants them. The statute preserves applicable rules for leases made before October 1, 1963, so counsel should review the instrument and its date.

Does FERC regulate every underground gas storage facility?

No. FERC’s landowner guidance concerns interstate natural gas facilities; determine the authority and records relevant to the particular facility.

Sources & further reading

New York Environmental Conservation Law section 23-1307 and FERC landowner guidance checked November 16, 2026. Local rules and program details can change. Check the requirements for the actual project.