Verify the use and what the battery lease would change
Collect zoning and approved use records, including the building’s Certificate of Occupancy if it has one, and any applicable approvals and plans. For an eligible older building without a certificate, the Department of Buildings says a Letter of No Objection may establish its legal use. Ask your adviser to confirm whether the existing use lawfully continues under the current Zoning Resolution. Record which part of the property it uses and when substantial operations last took place.
Section 52-31 treats a move to another listed use as a change of use. Changing the owner or occupant alone does not change the use. The Zoning Resolution separately describes principal-use energy infrastructure equipment, including batteries, and energy storage equipment accessory to a principal use. Ask how the actual proposal is classified if the business would leave, stay on part of the site or keep operating with a battery added for its own use.

Check when the existing use stopped
Under § 52-61, when a non-conforming use of land with minor improvements is discontinued for two continuous years, the land thereafter can be used only for a conforming use. The rule also applies where active operation of substantially all non-conforming uses in a building or other structure stops for that period. An intention to reopen does not change the rule. Ask counsel to check any applicable exceptions and the evidence of when operations stopped.
For example, the tenant of a lawfully non-conforming outdoor storage yard moves out when the battery developer begins its review. If that use stays discontinued for two continuous years and § 52-61 applies, a later cancellation can leave the owner unable to resume the old use. Ask your adviser to assess an actual change of use separately from a discontinuance. Two years is the discontinuance test described here, not a guarantee that every shorter interruption or conversion preserves the prior use.
Decide how early to give possession
Put three dates side by side. When must the existing occupant stop operating, when would the developer get exclusive possession, and when do the agreement’s approval conditions expire? Ask whether limited investigation access can work while the lawful prior use continues, and identify which areas and activities the existing business would need to retain.
If the developer needs the whole property vacant sooner, consider what losing the option to resume the old use would mean for re-letting the site and for the proposed payment and timing. Have counsel align the move-out and possession terms with the project’s remaining approvals and agreed deadlines. Ask what happens if the approval period is extended, the developer walks away or the prior use cannot resume.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landDiscuss your property or existing battery agreement
Sunland welcomes inquiries nationwide from owners and authorized representatives about selling or leasing battery storage land or assigning an existing agreement. Share the general location, current use and proposed possession date. Keep signed agreements, zoning records and plans for private review.
Questions landowners ask
Does a new owner or tenant automatically end a lawful non-conforming use?
Section 52-31 says a change in ownership or occupancy alone does not change the use. Have your adviser check what is actually changing, including any interruption in operations.
Does an option agreement start the two-year period?
Section 52-61 addresses the discontinuance of the use or active operations. Give your adviser the operating dates and the option and possession documents to determine what happened and when.
Sources & further reading
Official NYC sources checked November 20, 2026. The outdoor storage yard and proposed battery lease are hypothetical. The legal use, interruptions and effect of a proposed change depend on the actual zoning and operating record. Local rules and program details can change. Check the requirements for the actual project.