Confirm the district, funding and responsible parties
Request the certified agricultural district map and district number for every affected parcel, including land crossed by a proposed road or transmission line. Compare the map with the tax parcel boundaries. Being in a district is different from receiving an agricultural assessment; land can have one status without the other. Ask the county and the project team to resolve boundary questions before relying on an initial map.
Ask which entity is advancing funds, what program and project design are proposed, and who will prepare and file the notice of intent (NOI). Section 305(4) covers specified public acquisitions, construction and advances of public funds; it is not a blanket filing requirement for every private lease. NYSERDA identifies district projects applying for NYSERDA incentives as subject to the section. Other public involvement can also matter, so ask the relevant agency or New York counsel about the actual transaction.
For the NY-Sun Commercial/Industrial long form, the developer supplies the package to NYSERDA, which submits the notice to Agriculture and Markets. The statute directs the proposing public agency, corporation or government to file with the Commissioner of Agriculture and Markets and the county Agricultural and Farmland Protection Board. Ask for the filing contact, a copy of the submitted package and updates; do not assume the landowner personally files the agency notice.

Map the whole project against the working farm
Obtain a dated aerial layout and survey or tax map showing each affected owner and parcel, the array, fences, inverters, storage, interconnection equipment, lines, access roads, staging and equipment storage, grading and stormwater features. Overlay the farm fields, crops, drainage, irrigation, gates, livestock movements and farm roads. Mark land you expect to keep farming and the routes and equipment widths needed to reach it. Include the tenant or farm operator and review existing farm leases together.
Ask for the NRCS Web Soil Survey map and the county-specific mineral soil group classification for affected soils. NYSERDA’s form asks for impacted mineral soil groups (MSG) 1–4 within the Facility Area. That defined area includes the operating generation facility, associated interconnection and any energy storage, generally inside the security fence and applicable permanent improvements outside it, such as roads, parking and stormwater controls. Vegetative screening and appropriately buried utilities are exceptions in the form’s definition. Temporary construction areas still belong on the impact map even where not counted in that defined operating area.
Ask whether the proposal is stacked with another project. The long form defines stacked projects as multiple projects greater than 1 MW DC that abut on parcels owned by the same landowner or owners; they undergo aggregated review and affected MSG 1–4 acreage is aggregated to determine mitigation. Separate fences or interconnection points do not by themselves settle this question.
Choose the form and plan the schedule early
The October 2026 NY-Sun long form applies to projects affecting more than 30 acres of MSG 1–4; its instructions direct projects affecting less than 30 acres to the short form. Because those instructions do not specify exactly 30 acres, ask NYSERDA which form applies at that boundary. Have the project team document the acreage calculation, any stacked projects and revisions before submitting.
Section 305(4) calls for filing at least 65 days before the specified acquisition, construction or advance of public funds. Completeness review, possible additional submissions and the commissioner’s review can affect the schedule. The statute also allows an additional delay order in specified circumstances. Sixty-five days is not an automatic approval or a promise that work can start on day 66; ask the filing entity for the actual status and any conditions before authorizing work.
The NY-Sun form treats commencement as the first construction-related activity, which may include creating access roads, trenching, clearing or staging supplies and equipment, as well as installing panels. Identify the earliest planned work and ask the developer and NYSERDA how it fits the notice and other requirements. Keep site investigation permissions and construction permissions clear in the agreement.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landPut farm impacts and alternatives into the record
The notice includes an agricultural impact statement addressing short- and long-term effects, unavoidable adverse effects, alternatives, irreversible commitments and proposed mitigation. Tell the developer where a fence or road would divide fields, block machinery or livestock routes, interrupt drainage, compact soils, or limit future farming. Describe seasonal work and any concerns of directly affected landowners and the operator. Request the draft impact description and check that it accurately reflects those facts.
The long form asks for other parcels considered and why they were not selected, as well as siting constraints such as wetlands, setbacks, grading, interconnection and owner restrictions. It also requests an attached decommissioning plan and a description of returning the site to agricultural use. Ask the developer how it evaluated alternatives and whether a smaller footprint, different road or layout would preserve more workable acreage. Review any restoration commitments against the lease and the farm’s practical needs.
NYSERDA says Commercial/Industrial district projects must meet Agriculture and Markets construction mitigation guidelines. Its guidance also identifies a mitigation fund payment for projects with interconnection applications after November 1, 2020 on more than 30 acres of MSG 1–4. The long form asks, where applicable, for a payment estimate and whether an agricultural co-utilization plan is being pursued. Ask NYSERDA which requirements, payment and potential plan apply to this project; proposed co-use is not itself an accepted plan.
Carry the agreed protections into the land agreement
Have New York counsel review the option, sale or lease and site plan together. Address access for the farm operator, notice before entry, construction timing, drainage and soil repairs, crop losses, temporary work areas, insurance, restoration, decommissioning security, and who pays review and mitigation costs. Specify how changes to the footprint, storage or access are approved and communicated to affected owners and the farm tenant. Coordinate any lender consent and existing rights.
The agricultural district notice is separate from local permits, environmental review and any agricultural assessment or conversion question. Ask the municipality and assessor about those separate processes and obligations. A preliminary layout, an NOI filing or a developer’s estimate does not establish a permit or tax outcome.
Sunland welcomes land sale, lease and existing agreement inquiries nationwide. Share the approximate New York location, acreage, district status if known and current farming arrangement. Sunland may contract for a parcel and then assign its interest to a specialist; discuss the proposed transaction and assignment terms before signing. Keep sensitive records for secure review.
Questions landowners ask
Does every solar lease in an agricultural district require an NOI?
No. Section 305(4) addresses specified public actions, including certain advances of public funds. NYSERDA says projects in state-certified districts applying for its incentives are subject to the section. Confirm the actual funding and public action with the responsible agency.
Does the landowner file the NY-Sun notice?
The public entity files the notice. For the NY-Sun Commercial/Industrial long form, the developer provides information to NYSERDA for its submission. Owners and operators should help verify farm facts and ask for the submitted documents.
Can construction begin 65 days after filing?
The law requires advance filing and provides for completeness and substantive review, including a possible additional delay order. The passage of 65 days alone is not an approval. Confirm status and other required permissions with the responsible authorities.
Which form applies to exactly 30 acres of MSG 1–4?
The long form states more than 30 acres and refers less than 30 acres to the short form. Ask NYSERDA for direction at exactly 30 acres, including how stacked project acreage is calculated.