New York landowner guide

How can a solar project take possession of land with boarded horses?

A New York landowner considering a solar sale or lease may rent the property to a boarding stable whose customers own the horses and tack. A possession date in the solar agreement alone does not move those horses or settle the stable tenant’s and customers’ rights.

Could my land work?

Review the stable lease and boarding arrangements early, identify who can authorize each horse’s move, and agree on a realistic, phased possession plan. Preserve safe care, turnout and trailer access until the horses leave, then document each handoff before construction begins. A claimed boarding lien or ownership dispute needs individual legal review; do not assume that the landowner or developer can release or relocate a customer’s horse.

Identify the people, property and rights

Gather the stable lease and amendments, any renewal or termination notices, maps, and available boarding agreements. Identify the landowner, stable operator and tenant, each horse owner or authorized representative, and any other person claiming rights in a horse or equipment. Inventory horses by reliable identifiers, their locations and contacts, and separately identify customer-owned tack, trailers and other property. Handle the inventory and contact details securely.

Have New York counsel review possession, notice, renewal, removal and access provisions and any disputes. A tenant’s agreement to surrender land does not by itself establish authority to move every customer’s horse or transfer the customers’ property. Confirm directly with the person legally authorized to consent to each relocation, and document that authority and any permissions required under the applicable agreements.

Illustration of a land parcel and surrounding landscape

Keep care and access workable until the move

Map the stalls, turnout areas, water, feed and supply routes, manure handling, gates, parking, trailer loading and the route to the public road. With the stable operator and affected owners, identify veterinary and farrier access, emergency contacts and practical arrangements for daily care. Agree who supplies and pays for these services through the actual move, including a contingency if a destination or transporter falls through.

Phase surveys, fencing and construction so the stable retains agreed safe access and turnout until each area is surrendered. Set notice for entry, traffic controls, gate responsibilities, working hours and an emergency route. Heavy equipment, open gates or a blocked trailer turning area can make a paper access right unworkable. Put any temporary alternative route or turnout arrangement in writing with the parties who can grant it; obtain any needed third-party permissions.

Arrange the relocation and resolve claims

Coordinate the destination, transporter, loading time, horse identification and receiving contact with the owner or authorized representative and the stable operator. Confirm any destination, transport, health or veterinary requirements with the receiving facility, transporter and veterinarian. Assign costs and responsibility for tack and other personal property; obtain appropriate authorizations before it is moved. A developer’s construction schedule does not itself authorize relocation.

New York Lien Law § 183 can give a qualifying boarding stable keeper a lien dependent on possession for sums due under an express or implied agreement with the animal’s owner for covered care or boarding. It also addresses specified vehicles and harness kept or stored in connection with the activity. Whether a particular claim attaches depends on the facts, the agreement, the amount and possession; do not assume every debt or item of tack is covered. Ask counsel to evaluate any asserted lien or competing claim and arrange an agreed, documented resolution with the affected parties. Do not move, retain or dispose of a horse or property to settle a dispute without appropriate legal advice.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Use the court decision carefully

In Jamaica Bay Riding Academy, Inc. v. Metropolitan Equestrian Team, Inc., decided December 14, 2022, the Appellate Division, Second Department affirmed an order vacating two asserted § 183 liens and directing return of the horses and related equipment. The parties had agreed to free boarding in exchange for use of the horses, and the evidence did not establish outstanding sums for covered services. The decision turns on its facts; it does not mean that a boarding stable can never have a valid lien.

For a proposed solar transaction, identify unresolved charges and claims well before the handoff. Counsel can examine the agreements, invoices, payments and possession and help the parties document a resolution. Do not treat a disputed lien as automatically valid or automatically extinguished by a sale, lease or tenant departure.

Make possession measurable

Divide the site into mapped areas with dates and conditions for survey access, limited construction entry and final exclusive possession. Specify the last day for horses, tack and tenant equipment in each area, continued access to areas still occupied, who maintains fencing and utilities, and how delays or incomplete removal affect commencement, payment and construction. Counsel can tailor conditions, extensions and remedies to the actual leases and transaction.

At each handoff, record the date and area, a joint inspection and photographs, horse and property departure confirmations from the appropriate parties, keys and gate controls, remaining exceptions, and signatures or written acknowledgments from those able to surrender the relevant area. Confirm care and access continue for anything remaining. Keep the lease, notices, authorizations, resolutions and handoff records together; an empty stall alone is not proof that every right or claim has been resolved.

Sunland welcomes solar land sale, lease and existing project inquiries nationwide and may contract for a property and assign the agreement to a specialist. Share the county, approximate acreage, stable occupancy, proposed timing and access concerns. An inquiry does not commit you or guarantee a project; share personal and ownership records securely when needed.

Questions landowners ask

Can the landowner move a boarder’s horse when a solar lease starts?

A solar lease alone does not establish authority to move a customer-owned horse. Identify the owner or authorized representative, review the applicable agreements and obtain the required permissions.

Does a boarding bill automatically give the stable a lien on every horse and item?

No. Section 183 is conditional and possession-dependent, and its application depends on the particular agreement, covered sums and property. Have counsel review any claim.

Can construction begin while horses remain?

Only if the relevant parties have agreed to the access and possession arrangements and the work can proceed safely with necessary permissions. Map the retained areas and routes and preserve care, turnout and trailer access until the agreed handoff.

Sources & further reading

Sources checked 2026-11-17. Local rules and program details can change. Check the requirements for the actual project.