Map the working yard and the proposed solar footprint
Identify the beekeeper and the owner of the hives and equipment, the number and seasonal location of colonies, and any written or informal permission to use the land. Review notice and termination terms with counsel rather than assuming that an informal arrangement can be displaced immediately. Map hive stands, water, vehicle turning and loading areas, the lane and gates used to reach them, and any seasonal or nighttime access needs.
Overlay panels, fencing, gates, cables, roads, drainage, staging and construction traffic. Walk the route with the beekeeper and developer, including the vehicle and equipment actually used for loading. Decide whether a working yard and practical loading lane can remain throughout construction and operation or whether the colonies must move. A drawing that leaves the hives in place but blocks the lane may not preserve the operation.

If the bees stay, secure practical access
Specify the yard boundaries, route and vehicle clearance, gate and key arrangements, notice and contact procedures, and access during construction, maintenance and emergencies. Address working hours, temporary closures, alternate routes, safe separation from crews, equipment damage and repair. Agree who maintains the lane and gates, and how future layout changes are approved. Coordinate vegetation management and pesticide plans with the beekeeper.
Have counsel reconcile those rights with the solar agreement’s exclusivity, security and insurance terms and any existing tenancy or easement. Set out who bears loss, damage and interruption costs and how the arrangement changes or ends. Check local requirements and the final design; permission to place hives does not itself authorize the solar project.
If the bees move, link relocation to possession
Choose the destination and timing with the beekeeper, taking weather, colony health, season, suitable vehicle access and permission at the new site into account. Allocate who finds and secures the new yard, arranges and pays for labor, transport, equipment, site preparation and restoration, and bears delay or loss. Document a backup plan if the destination is unavailable or conditions make the agreed move unsafe.
Set a clear handover: identify when hives and equipment must be removed, how completion is confirmed, and when the developer receives exclusive access to the yard and lane. Preserve access needed to complete the move until that milestone, and address extensions, failed relocation and termination. Do not rely on a construction start date alone as proof that the beekeeper has vacated.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landCheck New York registration and movement requirements
New York Agriculture and Markets Law section 173-c requires all beekeepers to provide the commissioner the number of managed colonies, the county of each colony, current contact information for those responsible for their care, and whether they intend to sell nucleus colonies; the information must be updated annually. The beekeeper should confirm how and when to update the registration for the actual move, including a destination in another county. The host or developer should not assume responsibility for the beekeeper’s reporting simply because it controls the land.
The department’s PI-136 and additional-yard PI-136A forms ask whether bees are currently kept in each yard and, if no, offer transferred or inactive. The form does not define those terms. Ask Agriculture and Markets which entry fits the facts and how to report the destination; do not assume moving colonies makes the old yard transferred. Annual reporting and the form’s yard fields are distinct from the rules for moving bees. Section 173-c also addresses certain shipments into New York from another state or country; those entry provisions should not be treated as an automatic requirement for a move wholly within New York. Before moving, ask the department about any applicable disease, quarantine or other movement restrictions for the specific colonies and route.
Keep habitat commitments separate from the yard decision
A proposed wildflower seed mix or other pollinator habitat may have value, but it does not establish a right to keep managed hives, a usable loading lane, or a funded relocation. Ask for the actual planting, management and access commitments in the project documents, including who maintains them and for how long. Evaluate them separately from the beekeeper’s agreement and any applicable project approvals.
Owners and authorized representatives can contact Sunland about New York solar land, sales, leases or existing projects. Share the approximate location, acreage, yard and access status, and whether the proposed footprint overlaps the operation; provide sensitive agreements and records privately when needed.
Questions landowners ask
Can the beekeeper stay after the solar lease is signed?
Possibly, if the parties agree and the design, access and other applicable requirements permit it. Record the yard and loading route rights and reconcile them with the developer’s possession and security terms.
Does moving colonies within New York trigger the interstate shipment provisions?
Section 173-c’s cited shipment provisions concern entry into New York from another state or country. Ask Agriculture and Markets about any other applicable movement restrictions and how to report the specific move.
Does a new pollinator planting replace the existing bee yard?
No. Planting commitments and the beekeeper’s rights, working access and relocation arrangements are separate matters.
Sources & further reading
Section 173-c, the department’s Honey Bee Health page and the October 2025 registration forms were checked November 16, 2026. Confirm current reporting procedures and any movement restrictions with Agriculture and Markets for the specific yard and move. Local rules and program details can change. Check the requirements for the actual project.