New York landowner guide

Can a nursery growing block be released for solar?

A nursery field may look open for a solar project while valuable trees or other live plants are still growing in rows. Releasing it requires more than a date on a map: the owner, grower and developer need to know which plants remain, who may lift them, and how the nursery can continue its work and inspections.

Could my land work?

Inventory the stock and map the field, staging space, irrigation and access with the grower before setting possession dates. Agree which plants stay, which may be lifted, who owns them and what happens if lifting or sale is delayed. Confirm the grower’s registration, inspection and any movement requirements with New York’s Division of Plant Industry, especially before moving stock or operating in a new growing area. Document a phased release in the sale, lease or assignment with New York counsel.

Identify the nursery operation and its rights

Collect the deed, nursery or farm lease, crop and equipment agreements, registration, inspection reports, customer commitments and a current field map. Identify the landowner, actual grower, any tenant or plant owner, and the party authorized to release each area. Overlay the proposed panels, access roads, cable routes, fencing and construction staging on the growing blocks and supporting facilities.

Distinguish live nursery stock grown for planting from a stand grown for cut Christmas tree harvest. A cut-tree harvest schedule may help sequence access, but it does not resolve the registration, inspection and plant movement questions for live nursery stock. If both operations are present, inventory and schedule each separately.

Illustration of a land parcel and surrounding landscape

Check registration and inspection access

New York Agriculture and Markets says anyone selling plants in the state must register with its Division of Plant Industry as a nursery grower or nursery dealer. Under Article 14 of the Agriculture and Markets Law, a grower applies for registration; the department says it inspects the operation before issuing a grower certificate, renews it on a two-year cycle and inspects at least once per cycle. A dealer receives a registration certificate without an initial inspection requirement. Determine which role applies to the actual business rather than assuming that the landowner or developer holds the grower’s registration.

Keep the inspector’s practical access to stock, growing areas and sale or staging locations available through construction. Identify gates, routes, contact people and advance notice arrangements with the grower and regional inspector. Obtain current certificates and reports and address any restrictions or corrective orders; the department can issue quarantine orders restricting movement of plant material. Registration alone is not a blanket clearance to move every plant.

Inventory plants and the work needed to lift them

Make an itemized schedule by block and row, species or variety, size, count and condition. Identify the owner of each lot, customer-reserved stock, the stock to be retained in place, stock the grower may lift, and any stock to be sold or otherwise disposed of. Attach a dated map and provide a process to reconcile counts and changes jointly before handover. Decide who receives proceeds and who bears loss, damage and replacement costs.

Ask the grower for realistic lifting windows, labor and equipment needs, root-ball and handling requirements, temporary storage and watering, truck access and market commitments. Protect irrigation, power, turning space and a staging area until each lot has been removed. Weather, plant condition, inspection findings or a hold can delay lifting; set notice and a practical extension or other agreed consequence rather than assuming all stock can move on a fixed day.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Verify movement and release each area

Before moving stock, identify the species, origin, destination and intended route and ask the Division and destination authority what inspection, certification, quarantine or other conditions apply. The department works with USDA on phytosanitary certificates for shipments meeting other states’ or foreign countries’ import and quarantine requirements. A certificate or restriction depends on the shipment and destination; do not assume every local move needs the same paperwork.

If the grower will use a new field, review its registration and application records: New York’s grower application separately lists additional growing sites by street address, county and production acreage. Confirm with the Division how the new location affects registration and inspection before moving or selling stock from there. Identify who prepares the new area and its water and access, pays moving and establishment costs, and obtains required approvals. Do not treat a proposed replacement field as operational until those arrangements are in place.

Make possession and handoff enforceable

Use a phased plan that specifies the boundaries of each field and staging area, permitted interim activities, protected routes and utilities, notice, and the objective event that releases each area. Agree on a joint inspection and written handoff after the identified stock and equipment are removed or otherwise accounted for, required movement conditions are met, and access needed for remaining operations is preserved. Specify deadlines, extensions, compensation and termination or adjustment rights if a release is delayed.

For a sale, address retained crop and access rights after closing. For a lease, reserve the grower’s blocks and access until their agreed release. For assignment of an existing project agreement, check required consents, transfer of duties and any continuing liability. Have New York counsel coordinate the land transaction with the nursery lease and rights of plant owners; involve the grower, developer and a nursery or plant-health specialist in the field and movement plan.

Sunland considers land sale, lease and existing project assignment opportunities nationwide. For an initial discussion, share the approximate location and acreage, proposed solar footprint, nursery use and timing constraints; provide maps and operating documents privately when appropriate.

Questions landowners ask

Does a nursery dealer need the same initial inspection as a grower?

The department says a nursery grower operation is inspected before its registration certificate is issued; a dealer certificate does not require an initial inspection. Confirm the role and current requirements with the Division.

Can the developer take possession while plants remain?

Possibly, if the parties define retained blocks, access, utilities and safety arrangements and preserve the grower’s rights and inspection access. Put the phased release and handoff conditions in writing.

Can live stock be moved to a new field?

Confirm the new location’s registration and inspection implications with the Division and check applicable movement, certification and quarantine requirements for the actual plants and destination before moving.

What records help review a replacement growing field?

The New York grower application lists additional growing sites by street address, county and production acreage. Compare the proposed site with the current records and confirm registration and inspection steps with the Division.

Sources & further reading

Sources checked 2026-11-17. Local rules and program details can change. Check the requirements for the actual project.