Verify the state record for the project
Ask for the exact permit and case numbers, the permittee’s written filing and the agency’s response. Check the facility and route descriptions, the date of the response and any remaining site work it identifies. A developer’s statement that it submitted a filing gives you a reason to request the actual agency record.
For applications received on or after March 9, 2026 that are governed by the current rules, 16 NYCRR §1100-11.4 calls for a written filing with ORES and the secretary. It identifies the permit or certificate, explains the reason for relinquishment and how the conditions were satisfied, and describes any remaining site actions. ORES checks the conditions, including applicable post-operational and decommissioning requirements, and provides written concurrence or reasons the permit or certificate should stay in effect.

Read what the Flat Creek ruling confirms
In an October 6, 2026 letter, ORES confirmed relinquishment of Flat Creek Solar’s April 3 siting permit under former §1100-11.3. The November 13 ruling records the confirmation and closes the project’s local agency account. Flat Creek applied in September 2024, before the current Part 1100 took effect.
For your own property, use the case file to confirm the public permit status. Ask the developer and your title team for the private documents showing what happened to the land rights.
Check each private right before committing the land again
Collect the signed option, lease and easements, all amendments and assignments, any termination notices, and any recorded memorandum. Match each instrument to the parcels and routes it covers. Ask counsel which event ends each right, whose notice or signature is required, and whether the terms call for a separate release. Have the title company identify any document it needs recorded and request a title update before closing.
If the developer needs to return to the site, check its access and restoration terms, the work area and what will document completion or return of possession. Reconcile payments due under the signed agreements. Use those records to agree on when a buyer or new tenant can take possession and how to handle any work or payment that continues beyond that date.
| Record | What to verify |
|---|---|
| State permit file | Permittee, affected facility, written agency response and any remaining site actions. |
| Signed private agreements and notices | Which rights end, when they end and what obligations or access may continue. |
| Title and closing records | Any required signatures, releases or recording and the agreed possession date. |
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landDescribe the property when you inquire
Sunland welcomes nationwide inquiries from landowners and authorized representatives about land sales, leases and assignments of existing solar agreements. Share the general location, your role and the next decision or closing date. Keep signed agreements, notices and title records for private review.
Questions landowners ask
What should I request if the developer says the permit is gone?
Ask for the permittee’s relinquishment filing and ORES’s written response. Match both to the permit number and check the current case record for any later action.
Does ORES’s confirmation show the recorded solar memorandum has been released?
Ask the title company to check the county records for the memorandum and any recorded termination or release. Have counsel match the recorded documents to the full signed agreement and private notices.
Can I give possession to a new tenant right away?
Review when the prior rights end and what access or restoration obligations apply. Agree on the possession date using the signed documents and verifiable handback records.
Sources & further reading
The current rule, signed Flat Creek confirmation and November ruling were checked November 21, 2026. Verify the private agreements and title records for the particular parcel. Local rules and program details can change. Check the requirements for the actual project.