Identify the permitted site and its closure record
Confirm that the prior use was a regulated transfer station and identify the permitted boundary, legal owner, operator and parcel proposed for the battery equipment, access and utility routes. Obtain the permit and amendments, incorporated closure and leachate management plans, operating record, final waste receipt date, closure correspondence, inspection reports and any monitoring or corrective action records. A former transfer station and a landfill are different facility types; have the specialist check whether other uses or permits also affect the property.
Ask the operator and DEQ Solid Waste Section to reconcile the documents with the site’s current condition. Identify any remaining systems, monitoring locations, easements, access needs and recorded restrictions. The approved plans and permit conditions matter alongside the rule; an old listing or an empty building alone does not establish completion.

Understand the closure milestones
For a transfer station subject to 15A NCAC 13B .0406, the owner or operator must give the Division written closure notification at least 90 days before the proposed date waste acceptance ceases. Closure activities in paragraph (b) must begin no later than 30 days after the final receipt of waste and be completed within 180 days after closure activities begin. These are separate triggers, not a single deadline measured from a transaction. If the station stopped operating in the past, have the responsible professional establish the actual dates and status with DEQ rather than assume a new sale restarts the clock.
The rule requires removal of all waste, closure of any leachate collection system in accordance with the leachate management plan incorporated into the permit, and completion of the closure plan activities incorporated into the permit. Once those requirements are met, the owner or operator must notify the Division in writing how they were met and place the notice in the operating record. The Division conducts a final closure inspection to verify the rule’s closure conditions. Ask for the correspondence and inspection record; do not equate a notice submission with verified closure.
Check continuing obligations and the title record
If the Division requires a corrective action program following closure, or the owner or operator elects to leave a leachate collection system or tank in place for future use, Rule .0406 requires submission to the Division of a notice recorded at the county Register of Deeds. It must be discoverable in a deed title search, meet the cited statutory requirements and inform potential purchasers that the property was used as a solid waste management facility and its use may be restricted. Have counsel examine the actual title record and agency requirements; the rule does not require this particular notice in every closure.
If the Division requires groundwater or surface water monitoring or corrective action, Rule .0406 provides for it to continue during post-closure care until the Division authorizes termination of corrective action under 15A NCAC 02L .0106. After closure an owner or operator may request removal of the rule’s land-use restrictions. The Division approves removal if the specified post-closure activities are complete, it authorizes termination of any corrective action program, and any leachate collection system has been removed. Review written agency decisions and any recorded documentation rather than assume restrictions have ended.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landBuild the closure status into a sale or lease
Compare the proposed project footprint with the permitted site, remaining systems and any investigation or monitoring areas. Ask the environmental professional and DEQ what access, approvals or ongoing work are necessary before construction or occupancy. Review closure and post-closure cost estimates and financial assurance documents with the responsible parties, including whether the Division has accepted any change or release; do not assume a property transfer releases assurance or regulatory duties.
Counsel can describe the delivered condition and records, responsibility for outstanding work and costs, access for inspections and continuing care, restrictions on construction, insurance, schedule and remedies if conditions are not satisfied. In a lease, preserve the access and rights needed throughout the term. A documented possession milestone can tie handover to agreed evidence and site conditions while allowing for agency review.
Start a battery storage inquiry
An owner or authorized representative can share the location, approximate acreage, ownership, present use, road access, nearby electrical infrastructure and interest in a sale or lease. Identify the former transfer station and whether closure or monitoring remains open; share detailed records privately during diligence.
Sunland considers battery storage land opportunities nationwide. Sunland may put a parcel under contract and subsequently assign that contract to a specialist developer. Owners with existing project agreements are welcome to inquire. A discussion can assess site and transaction fit; project feasibility, timing and approvals are not guaranteed. Consult qualified environmental professionals, counsel and DEQ about the specific property.
Questions landowners ask
Does stopping waste acceptance complete closure?
No. The rule identifies closure activities, written notification and a Division final inspection. Review the actual permit and closure record with DEQ.
When do the closure deadlines run?
The written notice is due at least 90 days before proposed cessation of waste acceptance. Closure activities must begin no later than 30 days after final receipt of waste and be completed within 180 days after beginning those activities.
Does every former transfer station require a recorded notice?
Not under Rule .0406 in every case. Its notice provision applies when the Division requires post-closure corrective action or a leachate collection system or tank is elected to remain for future use. Other restrictions may also apply.
Can the land be leased while monitoring continues?
Potentially, depending on the site, permit, restrictions and project design. Review continuing access and construction constraints with DEQ, counsel and qualified professionals before agreeing to possession.