North Carolina landowner guide

What should a landowner check before approving a solar rebuild or expansion?

A solar tenant may ask a North Carolina landowner to approve replacement equipment, a larger project footprint or more generating capacity. The request is a useful point to check who must register the project, whether a statutory rebuild or expansion is proposed, and whether the existing lease still protects the land when the project is removed.

Could my land work?

Ask the project owner for a written description of the proposed work and its DEQ compliance analysis, then compare it with the lease and existing decommissioning security before consenting. For a covered utility-scale project, a qualifying rebuild or expansion triggers registration at least 90 days before commencement; applicable plan and financial assurance requirements must also be satisfied before work starts. The project owner and landowner may be different entities, and state assurance does not automatically replace the lease’s protections.

Identify the project and the responsible owner

Obtain the lease and amendments, site plan, current generating and interconnection information, certificates, DEQ registration and correspondence, and the proposed scope and schedule. Identify the legal entity that owns the solar equipment and the entity requesting consent. DEQ defines project owner as the entity or entities owning the personal property constructed or assembled for the project; that may differ from the landowner. Confirm who will file, fund and maintain assurance and how obligations pass to a successor.

North Carolina’s program covers a ground-mounted solar project capable of generating at least 2 megawatts alternating current (MW AC), directly connected to the local or regional grid and able to deliver power to it. The definition includes associated infrastructure such as battery storage and transmission facilities. Certain customer-owned or leased facilities primarily for the customer’s own use, offset or net metering are excluded. Confirm classification with DEQ for the actual project; lease language calling a project a solar farm does not settle the statutory test.

Illustration of a land parcel and surrounding landscape

Compare the work with the statutory triggers

A statutory rebuild requires both replacement of more than 50% of the original photovoltaic modules with a different type of module or other fuel source and the project being deemed new for income tax purposes. A statutory expansion means adding at least 2 MW AC of directly connected generating capacity able to deliver power to the grid or increasing the project’s ability to deliver power to the grid by 35%, whichever is larger. Ask for the original and proposed module inventory, tax treatment, and existing and proposed AC generating and grid-delivery capacities. Confirm the calculation and classification with DEQ; ordinary replacement, a larger fenced area, or a project label alone does not establish a statutory trigger.

DEQ explains that the plan and assurance requirements apply to projects with certificates of public convenience and necessity applications pending or submitted on or after June 26, 2023, and to projects generating solar energy or interconnected to a transmission facility on that date that are rebuilt or expanded after it. Check the project’s history and the proposed work against these dates and definitions. Other lease or local requirements may apply even if the work does not meet the statutory rebuild or expansion definition.

Verify registration, plan and financial assurance

For a covered utility-scale solar project, DEQ says the project owner must register and pay the fee at least 90 days before a rebuild or expansion begins. A project subject to the plan and financial assurance requirements must submit its decommissioning plan and establish financial assurance before commencement. Ask the project owner for the proposed submission, DEQ correspondence and evidence of the executed assurance mechanism and its acceptance or status; confirm the project-specific steps and timing with DEQ. Do not assume a consent deadline changes a statutory deadline.

The statute calls for a plan prepared, signed and sealed by a North Carolina licensed professional engineer and financial assurance in an amount acceptable to DEQ. Registration must be updated every five years, with documentation of applicable assurance. Ask how the revised equipment, infrastructure, removal, recycling, site restoration and cost estimate are reflected, and how the mechanism will be maintained through decommissioning and restoration. Obtain the current plan and assurance documents as well as proposed updates; a promise to arrange a bond later is not evidence that assurance is in place.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Preserve the landowner’s existing protection

Review the existing lease, amendments and local approvals for consent rights, removal and restoration standards, security amount and form, beneficiary, renewal and replacement obligations, notice of cancellation, access and enforcement rights. DEQ says existing projects must submit copies of existing decommissioning plans and financial assurance required by local ordinance or landowner agreement. Ask for the actual instrument, proof it remains effective and the calculation behind it. A DEQ filing or state assurance should not be assumed to satisfy or release a separate lease obligation.

With counsel, compare the old and proposed footprints and restoration baseline, and decide whether the lease security needs to change before consent. Address new equipment and buried infrastructure, cost increases, who bears shortfalls, timing and any successor or assignment. State law does not preempt more stringent applicable landowner or local requirements. Confirm any local approvals and coordinate the amendment, DEQ process and construction schedule before authorizing work.

Prepare for a practical review

Request a marked-up site plan, a description of equipment and capacity changes, proposed start date, DEQ registration and plan status, financial assurance documentation and the specific lease amendment requested. Have counsel and an independent engineer review the scope, estimate and instruments as appropriate. Sunland welcomes solar land and existing project inquiries; share the location, acreage and general proposal, and provide agreements or sensitive records privately when needed.

Questions landowners ask

Does replacing more than half the panels automatically count as a rebuild?

No. The statute also requires replacement with a different type of photovoltaic module or other fuel source and that the project be deemed new for income tax purposes. Confirm the facts and classification with DEQ.

Is the landowner always responsible for the DEQ filing?

The program places registration and applicable plan and assurance obligations on the project owner, which may be a different legal entity from the landowner. Identify the actual entity and review the lease and any separate obligations.

Does state financial assurance replace a lease bond?

Not automatically. Review the lease, local requirements and actual instruments with counsel. More stringent applicable landowner or local requirements can continue to apply.

Sources & further reading

NC DEQ program guidance, G.S. 130A-309.240 and Session Law 2023-58 were checked November 16, 2026. Confirm project classification, deadlines and submission status with DEQ for the specific work. Local rules and program details can change. Check the requirements for the actual project.