Map the rights before negotiating
Collect the declaration, recorded plats and plans, amendments, bylaws, rules, deeds, easements and any existing leases, mortgages or association agreements. Overlay a surveyed battery plan showing the fenced pad, transformers, access roads, underground cables, drainage and construction staging. Identify every unit and common or limited common element affected, not just the footprint of the batteries.
A unit is separately owned property as defined by the declaration and plans. Common elements are generally the parts of the condominium other than the units; limited common elements are common elements allocated for the exclusive use of fewer than all units. Exclusive use of a loading yard does not necessarily make it part of a unit or give its user authority to sell or lease it. A unit owner can negotiate only the rights that owner actually holds, subject to the governing documents and other restrictions.

Check the condominium’s governing law
Ask counsel when and under which law the condominium was created and whether older documents were amended to adopt the Pennsylvania Uniform Condominium Act. Section 3102 applies selected provisions to older condominiums for later events without invalidating existing governing provisions; it does not simply apply every current provision to every older condominium. The earlier Unit Property Act and recorded documents may also matter.
Do not assume residential rules or a single vote apply to an industrial property. Confirm whether every unit is restricted exclusively to nonresidential use, whether an applicable provision permits variation, and what the declaration actually says. A master association, declarant rights, lenders or other recorded interests may add parties or approvals.
Distinguish a lease from a conveyance
Where section 3302(a)(9) applies, and subject to the declaration, the association may grant leases, easements, licenses and concessions through or over common elements. If the grant is not for the benefit of all or substantially all unit owners, the same owner approval required for an amendment to the declaration is required. If it materially impairs a unit owner’s common-element right or benefit, that owner’s prior written approval is required. Counsel should evaluate both tests and any additional document requirements for the particular proposal.
A sale or other conveyance of common elements is different. Where sections 3302(a)(8) and 3318 govern, the association acts for the unit owners under section 3318, not a single owner acting alone. Section 3318 generally requires at least 80% of association votes, including 80% of votes allocated to units not owned by a declarant, or a larger percentage in the declaration. All owners of units to which a limited common element is allocated must agree to its conveyance or encumbrance. The declaration may specify a smaller percentage only when all units are restricted exclusively to nonresidential uses. Have counsel determine the applicable threshold and any other consents.
Section 3318 also excludes land, buildings or facilities containing or comprising a unit or necessary for use or operation of a unit from its conveyance or encumbrance authority. A conveyance under it cannot deprive a unit of access or support. These limitations require a site-specific review; a vote does not resolve every title or access issue.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landProtect operations and document approvals
Talk with the association and affected occupants early. Map truck turning and loading, emergency access, utilities, drainage, parking and maintenance routes during construction and operation. Identify any right or benefit materially impaired by a proposed lease or easement and obtain the prior written approvals the applicable law requires. Check the declaration and bylaws for meeting, notice, voting, execution and amendment procedures; give affected owners the proposal and enough detail to evaluate it.
For a section 3318 conveyance or encumbrance, the required agreement or ratifications must be executed in the manner of a deed, specify a date after which it is void unless recorded, and be recorded in every county containing part of the condominium; the agreement is effective only on recording. The association’s contract is not enforceable against it until the statutory approvals are completed. Have counsel and the title company check the transaction instruments, recording, existing liens and any required lender releases. Lease recording and notice requirements depend on the actual documents and circumstances.
Make the battery agreement practical
Include a precise plan, permitted use, construction and restoration obligations, safety and access arrangements, insurance, maintenance, payment allocation and removal at the end of the term. Address routes to the grid and rights for future replacement. Require necessary approvals and title review before the parties become committed, and specify who pays for surveys, legal work and design changes.
If the developer may assign the agreement, review both the condominium documents and the proposed assignment consent, continuing liability and notice terms. An assignment cannot supply property rights or approvals missing from the original grant. Sunland welcomes battery storage inquiries from Pennsylvania owners, associations and authorized representatives; share the site location, acreage and available condominium plans privately.
Questions landowners ask
Can the owner who uses the yard lease it?
Not necessarily. The yard may be a common or limited common element even if one unit has exclusive use. Check the recorded documents, association authority and required approvals.
Does every common-yard lease require an 80% vote?
No universal percentage applies. Where section 3302(a)(9) applies, its tests for benefit and material impairment, the declaration and other applicable rules determine the required approvals. Section 3318 separately addresses conveyances and encumbrances.
Can the association sell a yard needed for truck access?
Section 3318 excludes facilities necessary for the use or operation of a unit from its conveyance authority and preserves unit access and support. Counsel should evaluate the actual layout, documents and applicable law.