Start with the permit and the people
Collect the issued Chapter 102 NPDES permit or coverage documents, amendments, approved erosion and sediment control and post-construction stormwater management (PCSM) plans, inspection reports, agency correspondence and any notice of termination. Confirm the permit number, current permittee, listed co-permittees and status with DEP or the county conservation district (CCD). A purchase agreement or deed alone does not establish what has happened to permit coverage.
Describe who owns the land, who holds the permit now and who will control or conduct construction after the transaction. A change in company name, a transfer to another permittee and a change in construction operators are different situations. Pennsylvania requires operators who are not the permittee to be co-permittees; ask the reviewing office how that applies to the actual roles.

Ask the reviewing office about the handoff
Contact the DEP or CCD office that approved the coverage before setting the handoff date. Ask whether the change calls for a permit transfer, a co-permittee addition or removal, a name change or other action, and which forms, signatures, timing and supporting documents apply. DEP’s FAQ says that when site or project ownership will transfer, the permittee must submit a transfer application to DEP for an individual NPDES permit or the CCD for general permit coverage. It identifies separate transfer and permittee name-change applications when the permittee changes or remains the same with a new name, respectively.
DEP’s Chapter 102 Permit Amendments FAQ says to use the NPDES or WQM Permit Transfer application to add a co-permittee, with applicable sections completed by the current and proposed parties. Its note distinguishes operator co-permittees: it says their addition or removal should be documented on the Chapter 102 Visual Site Inspection Report. Give the agency the actual permit and proposed roles and ask it to reconcile the current guidance with that permit’s conditions before work changes hands.
Read the project’s conditions
Terms and procedures depend on the coverage. As one example, the issued Aspen Solar individual permit PAD280019 says a permittee seeking transfer before submitting a notice of termination must submit a transfer application at least 30 days before the proposed transfer. It describes conditions for automatic transfer and an alternative modification process. That permit also contains specific acknowledgement and release requirements for operator co-permittees. These are Aspen’s permit terms, not a substitute for checking your own permit and current DEP instructions.
Ask DEP or the CCD what must be submitted and when, whether proposed work or site boundaries require a separate amendment, and when the incoming party may assume its role. Keep copies of submissions, agency responses and any effective transfer or other documentation.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landPlan for construction and long-term care
Until coverage is properly terminated, arrange a continuous handoff of inspections, maintenance and repairs to erosion controls, stormwater measures and stabilization work. Agree who will correct outstanding deficiencies and pay for remaining work. Have counsel review the transaction documents alongside the permit; private allocation of costs does not by itself change regulatory responsibilities.
Ask the reviewing office about the remaining requirements for a notice of termination and the long-term operation and maintenance of PCSM best management practices. Pennsylvania’s rules tie termination to permanent stabilization and installation of required practices, and address continuing PCSM responsibilities. A project sale is not itself a notice of termination.
Prepare an inquiry
Sunland welcomes nationwide land and existing project inquiries. Share the Pennsylvania project location, your role, the proposed change and its timing, and whether construction stormwater coverage remains active. Provide the permit and transaction documents privately if requested.
Questions landowners ask
Does selling a solar project automatically transfer its construction stormwater permit?
Do not assume it does. Review the specific permit and consult DEP or the CCD about the applicable transfer process and effective date before the handoff.
Does a new construction operator need to be a co-permittee?
Pennsylvania requires operators who are not the permittee to be co-permittees. Ask DEP or the CCD how to document the change under the current guidance and the project’s permit.
Does a sale end responsibility for stormwater controls?
A sale alone does not terminate permit coverage. Arrange ongoing construction controls and ask DEP or the CCD about termination and long-term PCSM obligations.
Sources & further reading
Sources checked 2026-11-16. Local rules and program details can change. Check the requirements for the actual project.