Find out what the stalls support
Collect the deed, title report, recorded parking instruments, leases, site plans, permits and conditions of approval for the parking parcel and the use it serves. Identify the owner, operator, tenant and benefited parcel, and ask which stalls count toward each approved use. A recorded right, a private lease obligation and a city parking condition are different commitments; each may require its own resolution.
Put the existing stalls, accessible spaces and routes, drive aisles, entrances and pedestrian connections on a plan alongside the proposed battery equipment, fencing, construction staging and cable routes. Check whether temporary construction closures would interrupt parking before the permanent footprint is built.

Separate the city review from the recorded instrument
The city code text at section 18.75.030(C)(5) describes required parking for two or more uses, structures or parcels being satisfied jointly to the extent owners or operators show their parking needs do not materially overlap. This provision may have governed an existing approved plan. The right of joint use must also be evidenced by a recorded deed, lease, contract or similar written instrument. The instrument establishes the right; it does not by itself demonstrate that the city has accepted a particular parking calculation or a proposed change.
Ask city planning staff to identify the existing approval and the review, evidence and any amended decision needed before stalls are removed or reassigned. Ask which current rules, later ordinances, overlays and state parking reforms apply to changes at this site; do not assume the requirements underlying an older approval still apply unchanged. Do not treat the code’s general allowance as approval of this specific battery project.
Test peak demand and replacement parking
With each affected operator, document business hours, busiest days and seasonal or event peaks, employee shifts and expected parking demand. Compare the actual overlapping periods and available stalls, including the construction period. A daytime and nighttime schedule can support a shared-parking analysis, but a calendar alone does not prove that demand will not materially overlap. Ask the city what evidence it requires and how the proposed battery use is classified.
If replacement stalls are proposed, map their number, location, access, dimensions, accessible route and timing, and confirm they meet the applicable standards before the original stalls are displaced. The code text at section 18.75.030(C)(3) describes a 500-foot limit for qualifying nonresidential off-site parking, measured from the nearest stall to a building entrance along a sidewalk or other pedestrian route, and a recorded instrument evidencing the right. That provision may have governed the existing approval. Confirm with the city whether that provision applies and whether the replacement plan and recorded rights are acceptable. An off-site right and a shared-use right may both need attention.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landPut the transition into the transaction
Negotiate any amendment, release or substitute parking arrangement with the parties holding rights, and obtain required consents. Specify who designs, pays for, builds and maintains replacement parking; who obtains city review and records the instrument; and when existing stalls can be fenced or removed. Set a deadline, an inspection or evidence of completion, and a remedy if the replacement or approval is delayed. Preserve usable parking and access until the agreed and approved transition occurs.
In a sale, disclose continuing rights and allocate responsibility for completion and post-closing access. In a lease, show excluded or reserved areas and condition possession of affected stalls on the agreed transition. For an assignment, review consent, successor obligations and whether the assignor remains liable. A developer agreement alone cannot release another party’s parking rights or change a city condition.
Prepare a useful site package
Bring the current title materials, parking documents, approved plan, proposed battery layout, peak-hour comparison and a proposed replacement plan to the city and Oregon counsel. Confirm the applicable review and the form and recording of any revised instrument before committing to a delivery date.
Sunland welcomes battery storage land sale, lease and existing agreement inquiries. Share the property location, acreage, existing parking commitments and the area and timing that might be available.
Questions landowners ask
Does a recorded shared parking agreement authorize the battery project?
No. It evidences the joint-use right; ask Philomath what review and approval the proposed battery layout and parking changes require.
Can another lot replace the committed spaces?
Possibly, if the affected parties establish the necessary rights and the city accepts the applicable plan. Ask the city which current requirements apply. The code text describes a 500-foot pedestrian-route measurement and a recorded right for qualifying nonresidential off-site parking, which may have governed the existing plan.
Can the owner fence the stalls during construction?
First confirm the existing rights and approval conditions. Agree on and complete any approved transition before access to required parking is interrupted.
Does selling or assigning the property end the parking obligation?
Do not assume so. Review the recorded instrument, private contracts, approval conditions, consent requirements and successor obligations with Oregon counsel.
Sources & further reading
Sources checked 2026-11-16. Local rules and program details can change. Check the requirements for the actual project.