Ohio landowner guide

Can a data center tenant’s lender request a new lease after early termination?

Before you promise the space to another tenant after ending a data center lease early, check whether the outgoing tenant’s lender can request a new lease. The signed Pike County Building 1 lease in Ohio gives a qualifying leasehold lender a short request period and sets conditions the lender must meet.

Could my land work?

Get the signed lease, mortgage and lender notices. Ask counsel to confirm the termination date, whether the lender consented, and whether a written request and any required cure or payment meet the agreement. Check these records before committing to give someone else possession.

Identify the lender and its rights under the lease

Section 9(c) of the Pike County lease addresses a lender with security over the tenant’s interest. It calls for the tenant to give the landlord written notice, a copy of the mortgage and the lender’s notice information. The lease also requires a mortgage acknowledgment addressing how any remedies that affect the leasehold are subject to the lease.

Ask counsel to identify which lender or representative qualifies under the full signed lease. Check who received copies of any default and termination notices and whether the lender exercised its separate cure rights.

Illustration of a landowner reviewing property plans

Measure the request period from actual early termination

Under Section 9(d), a qualifying lender has ten business days after the lease terminates before its stated term without the lender’s consent to request a new lease in writing. The clause excludes a termination for tenant default that the lender did not timely cure under Section 9(c)(1). The filed copy redacts an additional condition that must be satisfied at signing and immediately afterward. If all conditions are met, the landlord must enter into the new lease with the lender that made the timely request.

Put the effective termination date and any lender consent, cure records and written request on one timeline. Have counsel check the delivery methods and receipt evidence under the signed lease before relying on that timeline.

Check the cure, cost and priority terms

Section 9(d) requires the lender to cure all monetary defaults, begin curing all reasonably curable nonmonetary defaults, and reimburse the landlord’s reasonable costs and expenses of entering into the new lease.

The new lease must have the same terms and priority as the original, including any options to extend the term or acquire the land. The public filing separately redacts a condition on tenant transfers under the new lease. Have counsel and the title company confirm which signed documents and title records establish the new lease and its priority. Keep those records with the request, cure documentation and expense records.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Discuss a property with an existing lease

Sunland accepts data center property sale, lease and existing agreement assignment inquiries from owners and authorized representatives across the United States. Share the general location, the interest you may transfer and your next decision date. Keep leases, lender notices and title documents for private follow-up.

Questions landowners ask

When does the Pike County lender’s request period start?

Section 9(d) measures ten business days after the qualifying early termination. Confirm the effective termination date, written request and delivery under the lease.

Does a timely request settle whether the landlord must sign a new lease?

The signed lease has additional conditions, including cure and reasonable expense reimbursement. The public filing redacts one condition at signing and immediately afterward.

Does the clause cover a tenant default the lender never cured?

Section 9(d) excludes early termination for a tenant default the lender failed to cure on time under Section 9(c)(1). Have counsel review the default and cure records for the specific lease.

Sources & further reading

Sources checked November 21, 2026. The signed lease redacts part of the lender and new-lease conditions. The records reviewed leave any actual leasehold mortgage, early termination, cure, lender request or new lease unverified. Local rules and program details can change. Check the requirements for the actual project.