Find the overall start date and each phase’s delivery date
The Building 1 lease starts on the later of the first phase’s target commencement date and its delivery date. The delivery date turns on when the phase meets the conditions in the lease’s work letter. Rent begins at lease commencement, and Section 4(a) abates rent for each phase until its own delivery date.
Put the current target date and the documented delivery date in separate columns for each phase. Check whether the lease or an amendment extended the target. Even if the first phase is delivered early, the lease start still uses the later of the two dates. Section 3(c) also gives the tenant an early access period for each phase without rent for that period.

Ask for a signed date confirmation for each phase
Section 3(a) calls for the landlord and tenant to sign a separate commencement date agreement after the readiness conditions for each phase are satisfied. Ask for both signatures, the phase covered and any agreement that changes the date, accepts part of a phase or adds a condition.
Before sharing a rent schedule with a buyer, flag any phase whose date is still projected, disputed or missing support. For a new lease, agree on who confirms delivery and how the parties will document any delay or credit.
Reconcile the first invoice and the payment
Under the Building 1 lease, the landlord invoices the first base rent and first operating expenses for each phase using the agreed delivery method. The tenant has 30 days after receiving those invoices to pay. The lease prorates rent by day when overall commencement or a later phase’s delivery falls midmonth.
For each phase, compare the period billed, the date the tenant received the invoice, any credits or disputes, and the amount and date of cash received. Bring the signed date confirmations and the rent ledger together before agreeing which figures belong in a sale or assignment package.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landDiscuss a property with phased rent
Sunland accepts data center property sale, lease and existing agreement assignment inquiries from owners and authorized representatives across the United States. Share the general location, the transaction you’re considering and your next decision date. Keep signed leases, date confirmations and invoices for private follow-up.
Questions landowners ask
Does early access start rent under the Building 1 lease?
The lease gives each phase an early access period without rent for that period. Check the overall commencement date and the phase’s delivery date to determine when billing begins.
Can you use the lease signing date for every phase?
The Building 1 lease uses the later of first-phase delivery and the first-phase target date to start the lease. For each phase, check its own delivery date and the signed confirmation.
When must the tenant pay the first rent invoice for a phase?
The tenant has 30 days after receipt to pay the first base rent invoice for each phase. Keep proof of receipt with the invoice and reconcile payment to the period billed.
Sources & further reading
Sources checked November 20, 2026. The public lease redacts the work letter, the commencement date agreement form and terms for partial or conditional acceptance. The filings reviewed leave actual phase delivery dates, invoices and payments unverified. Local rules and program details can change. Check the requirements for the actual project.