Locate the crossing and review title
Show the proposed driveway, public road, property boundaries and corridor edges on a survey. Gather your deed, title commitment and exceptions, recorded easements, old crossing agreements and any available railroad maps. Ask the surveyor to relate the proposed crossing to the railroad milepost or other description in the docket, and have counsel compare the records for that precise segment. An old farm crossing may have limits on location, vehicles, beneficiaries or use that do not cover solar construction traffic.
Determine who owns the corridor and what interests the railroad, trail sponsor, adjoining owners or others hold. Ownership and crossing rights depend on the instruments and applicable law. Neither a trail on the ground nor removed tracks proves the railroad abandoned its interest or that the adjoining owner can grant a new crossing.

Check the railbanking status for this segment
Search Surface Transportation Board (STB) docket records for the line and compare the mileposts and maps with your proposed crossing. Obtain the notice or certificate of interim trail use or abandonment (NITU or CITU), amendments or replacements, the notice that an interim trail use agreement was reached, and any later decisions. Ask the parties for the actual agreement and subsequent transfers or changes. The docket and title records answer different questions; review both.
Under 49 CFR 1152.29, a NITU in an exemption proceeding or CITU in an application proceeding can allow negotiation of a trail use agreement. Issuance alone does not establish that the agreement was reached. The rule requires a joint notice when an agreement is reached, including a map and description with mileposts; an agreement may cover less than the original notice or certificate. Interim trail use is subject to possible future restoration of rail service. If no agreement is reached or a segment is removed, check the subsequent orders and any notice of consummation of abandonment rather than assuming the outcome. Counsel should assess what that status means for the particular property interests.
Resolve crossing rights and practical design
Identify the present trail sponsor, day-to-day operator and corridor owner, and ask each who must approve a crossing and what documentation is required. The STB explains that it does not supervise or manage trail use; a railbanking notice is not itself permission for your driveway. A local attorney can assess whether an existing right covers the proposed use and which parties must grant any new rights or approvals.
Give those parties a plan showing crossing location and width, construction and emergency vehicles, delivery frequency, drainage, sight lines, trail-user protection and any gates or signs. Ask about design standards, permits, insurance, maintenance, restoration, fees and responsibility if rail service returns. Also check the public road entrance with the road authority and any utility crossings. Put necessary rights, conditions, duration and responsibilities in enforceable documents reviewed by counsel before relying on the route.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landKeep access commitments conditional
Map and price other potentially workable routes while the crossing is investigated, including access over other land where rights would need to be obtained. Compare road frontage, grading, environmental constraints and utility conflicts with the project team. An alternative on a map is not secured access until the necessary rights and approvals are in place.
Before signing an option, lease or sale agreement, ask your attorney to align access representations, investigation time, costs, termination rights and responsibility for obtaining approvals with what you actually know. Avoid guaranteeing a driveway across land or interests you do not control. Sunland welcomes solar land sale, lease and existing project or agreement inquiries from owners and authorized representatives nationwide. Share the location and acreage if known; provide title or agreement documents privately if requested.
Questions landowners ask
Does a trail mean the railway has been abandoned?
Not necessarily. A corridor may be in interim trail use under a railbanking agreement, or it may have a different status. Check the docket, exact segment and title records with counsel.
Does a NITU give me permission to cross the trail?
No. A NITU permits the railroad and prospective sponsor to negotiate interim trail use; it does not itself grant a landowner a solar driveway. Review existing crossing rights and obtain any necessary permissions.
Can I use an existing farm crossing for solar construction?
That depends on the crossing instrument, its beneficiaries and scope, applicable law and any required approvals. Have counsel review the documents and proposed traffic before relying on it.
Sources & further reading
Sources checked 2026-11-16. Local rules and program details can change. Check the requirements for the actual project.