Map the crossing and collect the records
Obtain the recorded WRE deed, legal description and exhibits, amendments, title report and documents for any road, utility or other third-party rights. Ask NRCS for the wetland reserve plan of operations and applicable authorizations and restoration records. Older Wetlands Reserve Program deeds and individual easements may differ; identify the actual instrument, its date and administering office.
On a survey or scaled map, show the easement boundary alongside the array, road width, turning areas, cable trench or bore, poles, staging, drainage changes and temporary work areas. Include construction traffic, routine maintenance and eventual replacement and removal. Identify wetland features, restoration structures and seasonal access constraints. A route outside the panel fence can still affect the easement.

Examine existing and reserved rights
Have a real estate attorney and title professional determine whether a recorded third-party easement predates the WRE, its priority and precise scope, and who can exercise it. A right held by a utility or neighbor is not automatically the landowner’s right to grant to a solar developer. Compare permitted purpose, beneficiaries, location, width, vehicles, installation and maintenance with the proposed project. Obtain the right holder’s position where relevant.
Also check rights expressly reserved in the WRE deed and any prior written authorizations. Private access or historical use of a farm track does not necessarily include heavy construction, widening, commercial traffic or an underground cable. Do not infer a new right from a map line or from the fact that an existing road remains visible.
Discuss the proposal with NRCS
Contact the local NRCS office with the deed, survey, title documents and a detailed description of each proposed activity and alternative. Ask what the recorded deed allows, what review or written authorization applies, and whether the proposed use is even eligible for consideration. Do not clear, grade, trench, bore or begin construction while relying on an informal conversation.
Under 7 CFR 1468.38, NRCS may in its discretion authorize compatible uses on an easement subject to the governing requirements and limitations. NRCS evaluates consistency with long-term protection and enhancement of wetland and other natural values and specifies the activity’s conditions. Compatible use authorizations are time-limited and may be modified or rescinded by NRCS. The applicable deed and NRCS guidance also explain that such authorizations do not vest rights. NRCS guidance cautions that roads within an easement are not guaranteed to remain passable and should not be represented as permanent vehicle access.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landSeparate temporary work from permanent infrastructure
Describe separately a temporary survey or work request, recurring vehicle access, road construction or improvement, and a permanent buried cable and its maintenance. A temporary authorization for one activity does not grant a perpetual corridor or authorize another activity. NRCS state guidance describes permanent structures as prohibited on WRE areas; review the actual deed and ask NRCS and counsel about the proposed work, rather than assuming an authorization or amendment will be available.
For an ACEP easement, 7 CFR 1468.6 provides that after recording, subordination, modification, exchange or termination of an interest requires NRCS approval and must meet applicable criteria. If a developer suggests changing the easement, ask NRCS to identify any legally available process and decision authority for this specific deed and proposal. Do not treat payment, mitigation or a restoration promise as automatic permission. Separate wetland, water, local land-use and utility approvals may also be needed; none substitutes for the rights and authorizations governing the easement.
Build a workable alternative into the agreement
Map routes around the easement, including another public-road connection or a separately negotiated neighboring corridor. Evaluate title, physical feasibility, costs and permits for each. Ask the developer to fund survey and legal review and document who seeks approvals, pays costs and bears the risk of denial. Set milestones for confirming durable access and utility rights before construction or an irrevocable commitment.
Address termination or redesign if the necessary rights cannot be secured, and restoration and liability for unauthorized work. The owner remains responsible for understanding obligations under the recorded easement. Sunland welcomes solar land and project inquiries; share approximate acreage, location and the existence of a USDA wetland easement, and provide sensitive records privately when needed.
Questions landowners ask
Does an array outside the WRE avoid easement review?
Not if access, cable work or other project activity crosses or affects the easement area. Map the complete footprint and consult NRCS.
Can an existing farm track serve construction traffic?
Possibly, but the deed and any prior rights determine the scope. A visible track or private access alone does not establish a commercial construction right.
Does a compatible use authorization create permanent access?
No. It is a discretionary authorization with conditions, does not vest rights and may be revoked. Evaluate a durable project route separately.
Sources & further reading
Sources checked 2026-11-16. Local rules and program details can change. Check the requirements for the actual project.