Landowner guide

Should you waive a BLM grazing cancellation notice for a solar project?

If a proposed solar right-of-way overlaps public land where you hold a Bureau of Land Management grazing permit or lease, you may be asked to waive advance notice of cancellation. Before signing, find out which grazing use could end, what time you would give up and what happens to your interest in authorized range improvements.

The short answer

Give the BLM field office the grazing permit or lease, the notice and a map of the proposed solar work. Ask which areas and grazing use would be affected, when a cancellation could take effect and what would remain. Review the exact waiver and document your interest in affected permanent improvements before signing a waiver or a separate agreement with the developer.

Confirm what the notice covers

Compare the proposed solar footprint, roads and utility routes with the allotment map and your grazing permit or lease. Mark the affected pastures, gates, water and routes your livestock need. Ask the BLM field office whether it is considering cancellation for all or part of the permit or lease and how the remaining grazing use would be handled.

Under 43 U.S.C. §1752(g), a qualifying cancellation to devote covered public land to another public purpose generally requires two years’ prior notification, with an emergency exception. Ask the field office to confirm the date and scope of any formal notice and whether a separate grazing decision has been issued. Keep the notice and evidence of receipt with the proposed transaction documents.

Illustration of a land parcel and surrounding landscape

Read the waiver before committing to a date

The BLM grazing rule allows the permittee or lessee to waive the two years’ prior notification unconditionally. The rule preserves the right to qualifying improvement compensation under the regulation. Ask counsel to review the actual wording and any separate agreement for what each signature covers. Check whether a developer’s document also addresses payments, access, a release of claims or another commitment.

Before deciding whether to waive notice, ask BLM how a waiver could affect the earliest cancellation date and what the field office expects to happen to use of the remaining allotment. Compare that timing with the grazing season, access to water and any alternative forage available to you. Confirm which agency decisions still have to be made.

Document your interest in permanent improvements

List each affected fence, well, pipeline or other improvement and gather its authorization, maps, construction records and any cooperative agreement. Check which work you or a prior operator contributed and what interest the BLM records show. The agency’s rules distinguish titles, contributions and interests. Ask the field office which records it needs for each improvement.

If a permit or lease is canceled in whole or in part to devote covered public land to another public purpose, the federal compensation provision covers the permittee’s or lessee’s adjusted interest in qualifying authorized permanent improvements they placed or constructed. The federal government pays reasonable compensation capped at the fair market value of the terminated portion of that interest. Ask the authorized officer how that value would be determined. For an improvement authorized under a range improvement permit, ask whether salvage and rehabilitation are available and what approval is required.

RecordQuestion to resolve
BLM notice and grazing decisionWhat land and grazing use are affected, and on which date?
Proposed waiver or settlementWhat would each signature change?
Improvement authorization and cost recordsWhich interest qualifies, and how would BLM value it?
Solar transaction and route planWhich approvals, access rights and dates must the agreement address?

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Match the solar agreement to the federal decision

If a sale or lease of your deeded land relies on a proposed federal route, tell the buyer or solar tenant which grazing and right-of-way decisions are still pending. Have counsel address the required authorizations, any retained ranch access and what happens if the approved route or effective date differs from the proposal. Ask BLM to confirm any remaining grazing authorization before making commitments about the allotment.

Sunland welcomes nationwide inquiries from landowners and authorized representatives about solar land sales, leases and existing solar agreements or assignments. Share the approximate location, the proposed transaction and whether there is a connected BLM grazing notice or right-of-way. Keep signed permits, notices and improvement valuation records for private review.

Questions landowners ask

What does waiving the two-year notice change?

The BLM rule allows an unconditional waiver of the notice period. Check the proposed form and ask BLM when the grazing decision could take effect. Review any separate agreement for additional commitments.

Can I still receive compensation for improvements if I waive notice?

The BLM rule preserves the qualifying compensation right. Ask the authorized officer to verify the improvement’s authorization, your interest in it and the portion affected by cancellation.

Does a solar right-of-way application cancel my grazing authorization?

Ask the field office for the applicable notice and grazing decision. Verify which use would end or remain and when that change would take effect.

Sources & further reading

Federal statute and BLM rulemaking checked November 20, 2026. BLM identifies the cited 2005 provisions as operative while the 2006 rule remains enjoined. The May 2026 revision was proposed. Confirm your actual notice, permit and decision with the handling field office. Local rules and program details can change. Check the requirements for the actual project.