Pause nearby work and document the proposal
Do not approach, touch or attempt to inspect the nest, and do not clear or grade nearby while the developer obtains advice. Record the observation from a safe distance without trying to provoke or follow birds. Share the location only with people who need it for protection, planning and agency review; do not post it publicly.
Ask for a preliminary map showing panels, access roads, cable routes, clearing, grading, staging and construction activity, plus the expected schedule. Identify what is known and unknown about the nest without guessing whether it is active or abandoned. A qualified wildlife professional can help assess the observation without unnecessary disturbance.

Discuss disturbance risk with FWS
The Bald and Golden Eagle Protection Act prohibits take of eagles, including certain disturbance. FWS describes disturbance as activity that causes or is likely to cause injury, reduced productivity or nest abandonment through substantial interference with normal breeding, feeding or sheltering. FWS notes that habitat removal as well as noise and visible activity can cause disturbance.
Provide FWS with the proposed work and schedule and ask which local guidance, surveys and protective measures apply. Distance, activity, timing, existing conditions and the nest’s status can matter. Ask whether alternatives such as shifting the footprint, retaining vegetation, changing the work sequence or moving construction outside sensitive periods would avoid or reduce impacts. Do not apply a single nationwide setback as a guarantee.
Understand the permit question
Ask FWS whether the proposal may cause disturbance take and whether a permit is appropriate. FWS offers general permits for eligible bald eagle disturbance activities under prescribed conditions, and specific permits for other qualifying situations. General permit eligibility and conditions depend on the activity and circumstances; a proposed solar project is not automatically covered.
An eagle disturbance permit and an eagle nest take permit address different activities. Do not remove or alter a nest or its supporting tree based on a disturbance permit alone. Ask FWS about any separate authorization, state requirements and local rules before work affecting a nest. Follow the terms of any permit actually issued or obtained.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landResolve the footprint and responsibilities
Ask the developer to document the revised plan, agency consultation, anticipated schedule and who is responsible for surveys, permit applications, protective measures and contractor instructions. Have your attorney review the option or lease for how changes, delays or an unavailable permit affect the agreement. Keep location information limited to those who need it, while ensuring workers who could affect the nest receive appropriate instructions.
Sunland welcomes land and existing project inquiries nationwide. Share the general property location, approximate acreage and your relationship to the property. Provide sensitive nest and survey information privately to the appropriate professionals or agency when requested.
Questions landowners ask
Does a nearby nest automatically stop a solar project?
Not necessarily. The impact depends on the nest, the proposed work and its timing. Consult FWS and a qualified wildlife professional about avoidance, minimization and any permit needs.
Is there one setback that guarantees a permit is unnecessary?
No single distance guarantees that every activity avoids disturbance. Ask FWS to review the activity, timing and site conditions against applicable guidance.
Can a nest be removed under a disturbance permit?
Do not assume so. Nest take and disturbance are different matters; ask FWS about the required authorization before disturbing, altering or removing a nest.
Sources & further reading
Sources checked 2026-11-15. Local rules and program details can change. Check the requirements for the actual project.