Identify the station and its needs
Confirm with the observer and local NWS office that the equipment is part of the Cooperative Observer Program (COOP), what instruments and observations are involved, and who owns and maintains the equipment. COOP stations can have different instruments and arrangements; equipment may be owned by NWS, the observer or another entity. Locate each gauge, temperature sensor, snow measurement area, cables and any other equipment, and identify the observer and backup.
Collect any site agreement, access arrangement and station contact information. Ask how often the observer must visit and how NWS reaches the equipment for inspections or maintenance. The presence of a station alone does not establish a legal ban on solar development; the actual agreement, property rights and other applicable requirements need review.

Compare the entire solar layout
On a site plan show the instruments and their surroundings, then overlay panels at their proposed heights and orientation, inverters, fences, roads, foundations, cable routes, drainage work, staging and temporary construction access. Include vegetation changes and the route used by the observer and NWS staff. Compare alternatives with the developer before fixing an option area or promising exclusive possession.
Exposure is more than leaving a small clear patch around a gauge. NWS guidance considers airflow and nearby obstructions for temperature sensors and precipitation gauges, as well as nearby paved surfaces for temperature measurements. Panels, fences, grading or changes in vegetation could alter the local exposure; ask NWS to assess the actual design and instrument combination. Published siting guidance is not a universal solar setback or a substitute for a station-specific evaluation.
Ask NWS to assess continuity and any move
Contact the local Weather Forecast Office early, provide the proposed layout and construction sequence, and request a site discussion with its cooperative program representative. Ask whether the existing site can remain suitable, what access and exposure it needs during construction and operation, and whether NWS would assess an alternative site. Keep the instruments in place until the responsible NWS representative has coordinated any change.
NWS station-management guidance distinguishes a move from a relocation using the distance from the primary observing gauge and calls for a climate-data compatibility evaluation for relocation. Distance and elevation are among the factors considered, but a nearby site does not automatically preserve continuity or the same station identifier. Ask NWS how it would evaluate the historical record, document changes and handle any transition or parallel observations where appropriate. Do not promise that a station will remain in service at a new location until NWS has assessed it.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landCarry the agreed solution into the land documents
If the existing site remains workable, have counsel describe the station area, necessary surroundings and access on a plan and address gates, keys, routine and emergency entry, equipment protection, vegetation management and notice of nearby work. Agree who coordinates with the observer and NWS, and how layout changes or construction damage will be handled. Preserve practical access throughout construction as well as operation.
If relocation is being considered, identify who arranges and pays for site preparation and access, who coordinates with NWS, the schedule and what happens if the alternative is unsuitable or delayed. Make any relevant option or lease commitments consistent with the station agreement and the outcome of NWS review. Local land-use and solar approvals should be checked separately.
Prepare the first conversation
Share the station location, instrument list, photographs, existing access and proposed solar drawing with the local NWS office and developer. Record outstanding questions and confirm the agreed next steps before construction or any equipment change.
An owner or authorized representative can ask Sunland to screen land for a solar sale or lease. Share the location, approximate acreage and known station constraints; provide agreements and detailed plans privately as needed.
Questions landowners ask
Does a cooperative weather station prohibit a solar farm?
Its presence alone does not establish a legal prohibition. Review the station agreement and property rights, and ask NWS to assess the proposed layout and station needs.
Can the station simply be moved to a nearby field?
Do not assume so. NWS should evaluate the alternative site, exposure, access and climate-data continuity and coordinate any move.
Is leaving a small space around the instruments enough?
Not necessarily. Nearby structures, surfaces, vegetation and access can affect observations or operation. Ask NWS to evaluate the complete proposed layout.
Sources & further reading
NWS program guidance and directives checked November 16, 2026 Pacific. The local NWS office should assess the specific station and proposed changes. Local rules and program details can change. Check the requirements for the actual project.