Find the actual easement and the land it covers
Start with the deed, title commitment and all listed exceptions. Obtain complete recorded copies of the avigation or airport hazards easement, exhibits, legal descriptions, amendments, assignments, releases and any related agreements. Ask the title company and attorney to identify the present holder and any other beneficiaries or parties whose rights matter. The airport manager may help locate records, but an airport map or a title exception summary is not a substitute for the signed instrument.
Have a surveyor plot the easement description against the current parcel boundaries and the intended project area. A partial easement may affect the most useful access or equipment location even if much of the acreage lies outside it. Check discrepancies in old descriptions, survey datums, elevations and any referenced drawings with the surveyor and counsel. An avigation easement can remain attached to the land after a sale; a new buyer or tenant must account for the rights that still apply.

Compare the rights with the proposed solar layout
Read the instrument as a whole. It may grant aircraft overflight and address noise or other effects, limit structures or trees, prohibit future obstructions, and give the holder entry and removal rights. Some restrictions use an elevation or sloping surface; others may prohibit above-ground objects altogether. Check exceptions for existing structures, duration, notice and consent language, and whether the terms reach temporary construction equipment as well as permanent facilities. The FAA’s Central Region sample is an example, not the recorded agreement for your parcel.
Give the surveyor and project team the panel layout and maximum elevations, including tracker positions, grading, inverters, transformers, fencing, poles, lines and any proposed buildings. Include temporary cranes and construction staging where relevant. Compare each item with the actual easement surface or restriction using consistent horizontal and vertical references. A panel that is short above its own ground level can still conflict with a sloped elevation limit, and a height-compliant object may face a separate use restriction.
Check vegetation provisions as well. Screening, trees and habitat plantings may conflict with clearing or future growth rights, and the airport may have access to remove obstructions. Plan gates, maintenance access, worker safety and responsibility for damage around the rights actually granted. If the instrument addresses glare, lights, electrical interference or fuel storage, have the project team evaluate those terms against the particular equipment and use. Glare questions depend on the instrument and project circumstances; proximity alone does not make every off-airport solar project subject to the FAA’s on-airport solar policy.
Separate airport rights from FAA notice and local approvals
Ask the airport or other current holder, through counsel as appropriate, whether the proposed layout fits the easement and what documentation it would require for any consent, modification or release. Identify the party authorized to sign, any other necessary participants, and whether federal obligations or FAA review or approval apply. A modification or release is not assured. If terms are agreed, have counsel address recording, project boundaries, ongoing access and enforceability before relying on them.
FAA construction notice is a separate question. Under 14 CFR 77.9, notice can be required for certain construction or alterations based on height, proximity and other specified criteria; the project team should evaluate each applicable proposal, including temporary equipment, and use FAA Form 7460-1 when required. An FAA aeronautical study or no-hazard determination does not itself amend or extinguish a private easement or replace the holder’s consent. Conversely, a holder’s consent does not eliminate applicable FAA notice or local permitting requirements. Check airport zoning, land-use permits and utility requirements independently.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landUse the findings in the sale or lease
If the preliminary layout conflicts with the easement, compare moving equipment outside the burdened area, reducing height or revising vegetation and access plans. Ask the developer to test the consequences for usable acreage, electrical collection, construction cost and interconnection. An alternative layout is only a candidate until the relevant rights and approvals are confirmed.
Before signing, have your attorney review disclosures, title and survey review periods, access for studies, payment, extension and termination rights, and which party pays for applications or seeks consent. Avoid representing that the site is unrestricted or that approval is guaranteed. Existing options or leases may already allocate these obligations, so review them before negotiating another agreement.
Sunland welcomes nationwide inquiries from landowners and authorized representatives about solar land sales, leases and existing project agreements. Share the parcel location and acreage if known, and provide easement, survey or agreement documents privately if requested. Sunland may contract for a property and later assign the opportunity to a specialist; an inquiry does not guarantee a transaction or project approval.
Questions landowners ask
Does an avigation easement mean solar is prohibited?
Not automatically. The recorded terms, affected area, proposed equipment and applicable approvals determine whether a particular layout can proceed. Some instruments restrict all above-ground structures; others use different limits.
Does an FAA no-hazard determination override the easement?
No. An FAA study addresses aeronautical effects under its process; it does not itself change the recorded property rights. Resolve any required consent or change with the holder and counsel.
Can the airport enter the solar site?
That depends on the recorded rights. An easement may grant ingress and egress and removal rights. Review their scope and coordinate project access and safety with the holder.
Sources & further reading
Sources checked 2026-11-17. Local rules and program details can change. Check the requirements for the actual project.
- FAA Central Region: Land acquisition and avigation easement resources
- FAA Central Region AIP Sponsor Guide, section 561: Avigation easements
- FAA: Suggested surface and overhead avigation easement
- FAA AC 150/5190-4B, section 5.3.3: Purchase of avigation easements
- 14 CFR 77.9: Construction or alteration requiring notice
- FAA: Obstruction evaluation and airspace analysis