Map the whole proposal against the correct boundary
Ask the developer for a drawing showing the panels, inverters, battery equipment if proposed, fencing, access road, drainage work, construction staging and cable or utility routes. Include temporary work areas and the access needed for maintenance and eventual removal. Compare those features with a survey, deed and the current CBRS mapping. A project may occupy only part of a parcel, and a road or line outside the array fence can be important to the review.
The CBRS is a set of designated coastal areas shown on official maps maintained by FWS. Its boundary is a different question from the flood hazard zones shown on a Flood Insurance Rate Map. Check both where relevant: being outside a mapped CBRS unit does not establish that land is free from flooding, and a flood-zone determination does not settle CBRS location. If the boundary crosses the property, identify which proposed features lie on each side rather than treating the entire tax parcel as one location.

Use the FWS location process
Start with the FWS CBRS Mapper and property documentation service. The service offers a self-service validation tool to help document whether a location is in or out of the system. FWS explains that locations within the tool’s approximately 20-foot buffer around a CBRS boundary require an official determination from the Service. Provide the precise location and the supporting survey, deed, property record or other material FWS requests; an approximate pin or an aerial photograph may not resolve a close boundary.
Keep the validation result or determination with the survey and proposed site plan, including the unit name or number and applicable dates. If a project drawing changes, compare the revised roads, lines and work areas again. For a flood insurance question, FWS directs insurance agents to work through the National Flood Insurance Program (NFIP) or the applicable Write Your Own insurer for an official determination when needed. Ask the insurer how the building and coverage will be evaluated.
Identify the type of CBRS area
FWS distinguishes System Units from Otherwise Protected Areas (OPAs). System Units carry the broader CBRA restrictions on most new federal expenditures and financial assistance that may encourage development or modification, subject to exceptions. Examples can include certain federal grants, loans and infrastructure spending. In an OPA, FWS says the CBRA federal funding restriction concerns federal flood insurance. A unit designation does not, by itself, show that a particular project has applied for or would qualify for federal support.
Ask the developer to identify proposed funding, guarantees, insurance and any other federal assistance for the project and related infrastructure. Give the responsible federal program the precise location, unit classification, relevant dates and transaction documents, and ask it to determine whether a restriction or exception applies. Do not assume every loan, private insurance policy or tax benefit is prohibited, or that a developer’s early financing description is a final agency decision.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landReview insurance for the actual structure
FWS says NFIP flood insurance is generally prohibited within the CBRS, with exceptions. Eligibility depends on the location and history of the particular structure and the relevant prohibition date. For example, a structure wholly outside the CBRS is not barred from NFIP coverage merely because an undeveloped portion of the same property lies inside. FWS also distinguishes the substantial improvement or damage treatment for certain existing structures added between 1982 and 2023 from structures added in 2024 or later.
Ask the owner’s insurer, the developer and their advisers which existing or proposed buildings and property require coverage, whether an NFIP policy is available for each, and what private coverage and lender requirements may apply. Do not assume solar panels, outdoor equipment or an entire project automatically qualify for NFIP coverage. Obtain the insurer’s assessment for the actual structure and policy rather than using a parcel-level map as an insurance quote.
Compare usable layouts and transaction terms
If the property straddles a unit boundary, ask for a comparison of a layout outside the mapped area and one that includes it. Include the feasibility and cost of roads, cables, drainage, construction and long-term access, not only the acres under panels. A route around the unit still needs legal access, engineering and any applicable permits. The owner may prefer to retain an affected portion, offer a different boundary or decline a proposal if the financing, insurance or access remains unresolved.
Have counsel review the proposed option, lease or sale description and specify who obtains surveys, location documentation, insurance and funding decisions, and who pays if the layout changes. Allow time for the relevant parties to review the actual proposal and address what happens if an essential condition cannot be met. Before a binding commitment, seek confirmation of the funding and insurance on which the economics depend. An option or private contract cannot itself establish a federal agency exception or an insurer’s coverage.
Check other approvals and start a discussion
CBRA does not itself prohibit development financed by private, state or local funds, and FWS says it does not prohibit federal permits. That does not remove separate requirements for wetlands, coastal resources, local land use, floodplain construction, utility crossings or recorded property restrictions. Ask the developer to identify the agencies and rights involved and to explain the status of each review. An approved permit is also not a substitute for a required funding or insurance determination.
Sunland welcomes solar land sale, lease and existing agreement inquiries nationwide. An owner or authorized representative can share the property location, approximate acreage, proposed transaction and any known CBRS designation. Provide surveys, maps and insurance information privately when requested. Sunland may contract for an opportunity and assign it to a specialist; a project, funding or approval is not guaranteed.
Questions landowners ask
Does CBRS designation prohibit a private solar project?
No. FWS says CBRA does not prohibit development carried out with private, state or local funding or the issuance of federal permits. Other laws, property restrictions and permits can still apply.
Is every part of a property treated the same way?
Not necessarily. Compare the official CBRS boundary with each proposed feature and any structure for which insurance is sought. Ask FWS for a determination when its location process calls for one.
Will the solar array be covered by federal flood insurance?
Do not assume it will be. Ask the insurer about the specific structures, property, policy and dates, including whether NFIP coverage is available. Federal flood insurance is generally restricted within the CBRS, subject to exceptions.
Sources & further reading
FWS Coastal Barrier Resources Act spending, insurance and property documentation guidance checked November 18, 2026. The actual unit, boundary, relevant dates, proposed activity and funding source determine the review; ask the responsible agency and qualified advisers about the specific transaction. Local rules and program details can change. Check the requirements for the actual project.