Landowner guide

Can a solar sale or lease proceed on land enrolled in a wildlife agreement?

A wildlife agreement can coexist with productive land use, but a solar proposal may change who controls the land and what happens on it. An existing Safe Harbor Agreement, Candidate Conservation Agreement with Assurances or Conservation Benefit Agreement deserves review before promising possession or a construction schedule.

The short answer

Obtain the signed agreement, enhancement of survival permit, enrollment certificate if applicable, maps and amendments. Compare the proposed parties, activities and schedule with the covered species, enrolled acreage, baseline and conservation duties. Ask the U.S. Fish and Wildlife Service and any program administrator how a sale or lease would be handled and whether the proposed solar work requires a change or other authorization. A land transaction alone does not transfer a permit or extend its coverage to a new activity.

Start with the actual agreement and permit

This guide concerns non-federal land enrolled in an existing Fish and Wildlife Service wildlife agreement. An enhancement of survival permit can authorize specified take of covered species and provide assurances tied to the agreement. “Take” has a specific meaning under the Endangered Species Act and can include harm to wildlife; an agreement is not a general development approval. Check the actual permit, its conditions and the activities it authorizes.

In 2024 the Service combined Safe Harbor Agreements (SHAs) and Candidate Conservation Agreements with Assurances (CCAAs) into Conservation Benefit Agreements (CBAs). The Service says existing SHAs and CCAAs, and certain drafts published before May 13, 2024, generally are not expected to convert until the associated permit expires or the agreement needs amendment. Do not assume an older agreement has already become a CBA, or that its particular terms match a newer one.

Ask for the complete signed agreement and exhibits, permit and conditions, modifications, baseline documentation, maps, monitoring reports and correspondence. Note the issue and expiration dates and whether the agreement covers the whole property or only a mapped portion. Ask the permit holder about outstanding reports, management work, notices and any compliance concerns; a short summary or a title commitment may not contain the full operating obligations.

Illustration of a land parcel and surrounding landscape

Identify who holds coverage and who would control the land

The landowner, permittee, tenant and solar company may be different parties. A programmatic CBA can have a primary permit holder, such as a state agency or nonprofit, that issues a certificate of inclusion to a participating owner. Obtain both the umbrella documents and the parcel certificate. Check the named participant, enrolled boundary, covered activities and any procedures for a change in ownership or control. An individual permit and a program enrollment are not interchangeable.

For a sale, ask the Service and, where relevant, the program administrator how the buyer becomes a party and what documentation is needed. Under 50 CFR 13.25(c), when property subject to an agreement and permit issued under sections 17.22(c) or 17.32(c) transfers, the Service will transfer the permit to the new owner if the new owner agrees in writing to become a party to the original agreement and permit. Section 13.25(b) also sets out Service determinations for transfers to successors, including qualifications and adequate written funding assurances. Coordinate the applicable process and obtain documentation of the Service action; a deed alone is not proof of permit transfer.

A lease or assignment creates a different question: who has sufficient rights to perform the conservation measures, who remains responsible under the existing documents, and whether the developer or its contractors can carry out the proposed activities under the permit? Do not assume the sale provision automatically resolves a lease or a program certificate. Ask the Service and program administrator to identify the applicable enrollment, permit and consent steps for the actual parties.

Compare the solar footprint with species, baseline and duties

Place the enrolled boundary and habitat areas on the same map as the proposed panels, access roads, fencing, cable trenches, substations, laydown areas and any offsite access or interconnection work. Include early surveys, vegetation clearing and geotechnical work, not just the completed array. Compare timing and methods for mowing, grazing, herbicide use, drainage and maintenance against seasonal restrictions and required management.

List each covered species and its status, the activities for which take is authorized, the conservation measures and the person assigned to perform them. A species seen on the parcel is not necessarily covered. For a non-listed species covered by a CBA, the Service explains that take authorization becomes effective if the species is later listed; the regulations also condition effectiveness on a timely signed permit and proper implementation. Coverage for one species or activity should not be assumed to cover another.

The baseline is the documented starting condition used in the agreement, not simply today’s appearance or a promise that all habitat may be removed. The Service describes a CBA option to return enrolled property to baseline before permit expiration if the agreement included that provision before issuance. Even then, compare the actual permit authorization, timing and notice conditions with the intended work. Return to baseline is not automatic permission to clear for a solar project or to affect an uncovered species. Seek site-specific confirmation before disturbing habitat.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Resolve changes and dates before granting construction access

Ask the Service whether the specific solar design fits the current agreement and permit, whether an amendment or another authorization is needed, and what review and public process could affect the schedule. A proposed amendment is not an approval. The regulations treat permit amendment or renewal as a new agency decision under current relevant law; build time for that decision into the transaction rather than assuming it will be granted.

For permits issued under the current CBA rules in 50 CFR 17.22(c) and 17.32(c), a participating owner must notify the Service at least 30 calendar days before transfer of property subject to the agreement. Those rules also generally require the permittee to give reasonable advance notice of expected take, generally at least 30 calendar days. Check the actual permit, historic agreement and agency instructions for the notices and deadlines applicable to this transaction; these are different notices and one does not replace the other.

Set a timetable working backward from closing, possession and proposed field work. Keep required habitat management and inspection access in place during review. If the solar term extends beyond permit expiration, ask what happens to covered activities and responsibilities at that point; assurances under the current CBA regulations are limited to covered species, proper implementation and the permit term. Surrendering a permit does not necessarily erase outstanding conservation or termination measures.

Put the handoff into the sale or lease

With counsel, make the land documents reflect the actual agreement and the Service’s response. Identify who requests records, sends notices, applies for any transfer or enrollment, pays for monitoring and habitat work, and maintains access for the permittee, administrator and Service. Allocate responsibility for existing deficiencies and future reports without assuming that private allocation changes obligations to the agency.

Separate permission for limited due diligence from possession and construction. Use milestones tied to documented approvals or confirmations, with a process for revised layouts, delays and termination if necessary approvals cannot be obtained. At handover, exchange current maps, the permit and certificate, report history, contacts, deadlines and evidence of completed measures. A title review should also address separate easements, restrictions or other land rights; wildlife permit review does not resolve those rights.

Discuss the property with Sunland

Sunland considers solar land opportunities nationwide, including potential sales and leases. Share the location, acreage, current use and the existence of an agreement, together with the approximate enrolled area and known deadlines. Coordinate with the permit holder before sharing sensitive species locations or other protected records.

Ask how the proposed footprint, entry rights and timeline could accommodate ongoing duties. Sunland may contract for land and assign the opportunity to a specialist. An initial discussion does not itself grant entry, transfer a permit or establish that a project will be approved or built.

Questions landowners ask

Does a sale automatically transfer an enhancement of survival permit?

No. The regulations provide a process for transfer in specified circumstances, including a new owner agreeing in writing to join the original agreement and permit. Coordinate with the Service and obtain documentation of its action.

Does an old Safe Harbor Agreement automatically become a CBA?

No. The Service says existing SHAs and CCAAs generally are not expected to convert until the associated permit expires or the agreement requires amendment. Review the actual documents and ask the Service about the proposed change.

Can the developer clear habitat back to the baseline?

Do not assume so. Check whether return to baseline and associated take are authorized, the applicable conditions and timing, and whether the proposed solar work and species are covered. Seek confirmation before clearing.

Does a solar lease pass the owner’s assurances to the tenant?

A lease alone does not establish that. Review the permit, enrollment and control of the work with the Service and any program administrator, including whether additional steps or authorization are needed.

Sources & further reading

Sources checked 2026-11-17. Local rules and program details can change. Check the requirements for the actual project.