Can land under an FSA-guaranteed land contract be leased or partly sold for solar?

A solar offer can arrive while a farm buyer is still paying the seller under a land contract. If that contract already has an FSA Land Contract Guarantee, a lease or sale of part of the farm may affect the buyer’s operating plan, the seller’s security and the guarantee. Buyer and seller should examine the same proposal before either promises land or proceeds to a developer.

The short answer

Find the land contract, guarantee agreement, current balance and proposed solar map, then discuss the exact transaction with the Farm Service Agency (FSA), the escrow or servicing agent and counsel. Under 7 CFR 763.19(b), a seller and buyer may modify a contract with prior written Agency approval if the specified feasibility requirements are met; leasing, subleasing and partial releases are among the listed modifications. A solar proposal is not automatically approved.

Identify the agreement and who can act

This guide assumes the land contract already has an FSA guarantee. The program provides certain financial guarantees to a private farm seller; it is not the same arrangement as an FSA direct loan secured by a mortgage. Section 763.6(c) says existing land contracts are not eligible for the guarantee program, so an ordinary existing seller-financed contract should not be assumed eligible for a new retroactive guarantee.

Obtain the signed land contract, guarantee agreement, amendments, legal description, payment ledger and any liens or title documents. Identify the buyer, seller and approved escrow or servicing agent. The guarantee period is ten years from its effective date unless terminated earlier; the land contract itself may last longer. Confirm whether the guarantee remains in force and which plan applies rather than inferring coverage from the contract balance.

Illustration of a land parcel and surrounding landscape

Compare a lease with a partial sale

Map the proposed panels, roads, fencing, cables, setbacks and construction areas against the land under contract and the farm’s working fields. A lease may provide recurring rent while leaving the contract in place; a partial sale may release a defined area and produce closing proceeds. Both can change access, acreage, farm income and expenses. Ask the developer for its option, lease or purchase terms, timing, assignment provisions and restrictions on farming.

State law, title and the actual contract determine each party’s property interest and authority to sign or convey. Ask counsel whether the seller, buyer, lienholders or others must join the documents and whether subdivision or survey work is needed. Do not assume that a buyer’s possession alone permits a long solar lease, or that the seller can transfer the site free of the buyer’s interest.

Prepare the modification request

Section 763.19(b) permits the seller and buyer, with prior written Agency approval, to modify the land contract if there is a feasible plan for the upcoming operating cycle and a feasible plan can reasonably be projected throughout the remaining guarantee term. The rule lists leasing or subleasing and partial releases as possible modifications. Contact the FSA farm loan official early and request review of the actual draft and maps; neither a developer’s offer nor an oral conversation is written approval.

Show the acreage and use before and after the proposal, anticipated rent or sale proceeds, construction restrictions, changes to production and expenses, and the buyer’s payment obligations. Provide an updated operating plan and supporting assumptions to FSA as requested. Review the guarantee agreement and any separate lender requirements as well. FSA must evaluate the specific facts; the regulation does not promise approval of a solar lease or sale.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Trace partial-release proceeds and the ledger

The rule states that all proceeds from a partial release must be applied to a prior lien if one exists and, in addition, the same amount must be credited to the land contract principal balance. Ask FSA, the escrow or servicing agent, lienholder and closing attorney to determine the applicable lien, payment instructions and ledger entries for the proposed transaction before agreeing how proceeds will be used. Do not assume the buyer or seller can simply retain the sale price as cash.

For a lease, model the timing of rent against contract installments and the cost of the changed farm operation. For a sale, compare proceeds and the required principal credit with the value and earning capacity of the land retained. Ask a tax adviser to model the actual transaction and obtain a settlement statement and updated balance after closing. Keep financial records private when providing them to the parties who need them.

Check transfer, assumption and assignment

If a proposal transfers the property and assumes the guaranteed debt while the guarantee is to remain in effect, section 763.19(b)(4) requires an eligible buyer and written Agency approval. The rule permits a narrow exception by the Deputy Administrator for Farm Loan Programs when an eligible buyer cannot be found and an exception is in the Government’s best financial interests. A solar developer is not automatically eligible, and an exception is not automatic.

The seller also may not assign the land contract to another party without the Agency’s written consent. Distinguish assignment of the seller’s land contract from a developer’s proposed assignment of its solar agreement, and have counsel and FSA review each relevant document. The rule also lists events that can terminate a guarantee before ten years, including sale of real estate without the guarantee being properly assigned. Confirm the proposed structure and its effect in writing before closing.

Coordinate the documents and project schedule

Ask the escrow or servicing agent to reconcile payments and communicate the approved changes. Set a schedule for FSA review, any title or lienholder consents, survey, document revisions and closing or possession. The solar agreement can address who pays for these steps, maintains access, handles a changed footprint and bears delay if approval is not obtained. Counsel should align the final documents with the Agency’s decision and the parties’ actual interests.

Sunland welcomes land sale, lease and existing project or agreement inquiries nationwide. Share the location, approximate acreage, your relationship to the property and the existence of the land contract. Provide financial and contract records privately if requested. Sunland may contract for the property and subsequently assign the agreement to a specialist developer; an inquiry does not assure a transaction or FSA approval.

Questions landowners ask

Does FSA automatically approve a solar lease under a guaranteed land contract?

No. Leasing or subleasing is a possible modification under 7 CFR 763.19(b), subject to prior written Agency approval and the rule’s feasibility requirements. Ask FSA to review the actual proposal.

Can the parties keep all proceeds from a partial release?

The rule requires all partial-release proceeds to be applied to a prior lien if one exists and the same amount credited to contract principal. Coordinate the actual settlement and ledger with FSA, the agent and counsel.

Can a developer assume the guaranteed contract?

A transfer and assumption with the guarantee remaining in effect requires an eligible buyer and written Agency approval, subject to the rule’s narrow Deputy Administrator exception. Do not presume the developer qualifies.

Sources & further reading

Sources checked 2026-11-18. Local rules and program details can change. Check the requirements for the actual project.