Landowner guide

How should I schedule solar construction around grain pledged under a marketing assistance loan?

A solar construction schedule may require a bin or storage area to be emptied before the developer takes possession. If harvested grain there is pledged under a USDA Marketing Assistance Loan (MAL), the producer should coordinate any movement with the Farm Service Agency (FSA) before the project relies on an empty site.

The short answer

Identify the pledged grain, its storage location, the producer and the loan maturity date. Before moving farm-stored loan collateral, the producer should contact the county FSA office that services the loan and obtain the applicable authorization and instructions. Build the agreed movement or repayment plan into the possession schedule, with an alternative if clearance takes longer. A MAL pledges the harvested commodity; check separately for loans or liens on the bin and real estate.

Identify the collateral and who controls it

Ask the producer or tenant which commodity and quantities are pledged, where they are stored, the loan number and maturity, and who can work with the servicing county FSA office. Compare that information with a site plan showing bins, access roads, truck turning space, utilities and the area the developer needs. The landowner may not be the borrower or owner of the grain, so coordinate directly with the producer and any operator with storage or access rights.

A MAL uses the harvested commodity as collateral. It does not by itself establish that the bin or land is the MAL collateral. A bin may have separate financing, including a Farm Storage Facility Loan, and the property may be subject to mortgages, leases or other interests. Review those documents and obtain any separate consents required before promising removal, demolition or possession.

Illustration of a land parcel and surrounding landscape

Coordinate movement with the county FSA office

Before moving farm-stored pledged grain, the producer should contact the servicing county FSA office, explain the proposed destination and purpose, and obtain the applicable authorization. A transfer to another storage location and delivery to a buyer for sale can require different authorizations and instructions. Confirm the approved quantities, locations, timing, records and repayment requirements with FSA before arranging trucks or construction.

Under 7 CFR 1421.10, written authorization to remove collateral for sale does not itself release CCC’s security interest or the producer’s liability if payment in full has not been received. Moving without prior approval can be an unauthorized removal or disposition; the regulation addresses a limited non-workday notification circumstance. Do not build a planned construction schedule around that exception. Ask FSA about the particular loan and consequences before taking action.

Make an achievable possession plan

Have the producer, landowner and developer agree on the intended movement or repayment steps, responsible parties and dates. Confirm access for trucks, weighing, loading and any FSA inspection, as well as safe separation from construction traffic and equipment. Ask FSA what evidence and follow-up are needed; retain the authorization, delivery and repayment records and confirm completion with the office.

Tie the developer’s possession and notice to proceed to a realistic clearance milestone, rather than assuming a lease signing empties the site. Allocate costs and responsibility for delays, and agree on notice and a revised date if the grain cannot be cleared as expected. Consider phased work outside the storage and access area or a different staging area, if safe and independently authorized. Do not block access or direct anyone to move collateral before the required arrangements are in place.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Document the remaining site obligations

Once grain is cleared, separately address who owns and removes the bin and equipment, disconnection of power, foundations, debris, repairs and restoration. Check any lender, utility, lease and local requirements. The grain authorization is not permission to remove a financed bin or extinguish another party’s property interest.

Have counsel review the solar agreement alongside the farm lease and financing documents, including what happens if possession is delayed or an alternative area is unavailable. Sunland welcomes solar land inquiries nationwide. Identify the location, your relationship to the property and the known storage constraint; share loan or other sensitive documents privately if requested.

Questions landowners ask

Does the marketing assistance loan pledge the bin?

The MAL uses the harvested commodity as collateral. The bin or land can have separate loans or interests, so review their documents and any required consents separately.

Can the grain be moved to another bin before construction?

A move may be possible, but the producer should contact the servicing county FSA office and obtain the applicable authorization and instructions before moving farm-stored collateral.

Does permission to move release the loan?

No. Under 7 CFR 1421.10, written authorization to remove collateral for sale does not itself release CCC’s security interest or the producer’s liability if payment in full has not been received. Confirm repayment and release with FSA.

What if the grain cannot be cleared by the possession date?

Notify the other parties and use the process in their agreements to revise the schedule or pursue an agreed alternative. Any phased work must preserve necessary access and meet its own approvals.

Sources & further reading

USDA program guidance and 7 CFR 1421.10 were checked November 16, 2026. The servicing FSA office should confirm requirements for the specific commodity, loan and proposed movement. Local rules and program details can change. Check the requirements for the actual project.