Landowner guide

What happens if an updated solar lease estoppel changes before closing?

If your land sale includes an existing solar lease interest, the purchase agreement may require a fresh statement about the lease just before closing. A change in that statement can affect whether the buyer takes the solar interest, whether the seller has work to do after closing or whether the sale goes ahead.

The short answer

Compare the original and updated solar estoppels against the signed purchase agreement. Identify the changed certification, determine whether the contract treats it as material and check who can make an election. Put the chosen path, property and assets to be delivered, price and earnest money treatment, and any surviving cure obligations in the closing instructions.

Identify the solar interest and the party certifying it

List the land, any separate solar leasehold, equipment and related easements that the purchase agreement includes. Identify the parties to the solar lease and the party asked to certify its status. If you hold the tenant’s rights under a ground lease, give counsel the documents showing how you hold those rights and what any proposed assignment covers.

In a signed 2021 Shafter, California, farmland sale amendment, the seller and buyer added the selling tenant’s interest under a separate solar ground lease to the property to be conveyed. The amendment required additional title work and two certificates from that lease’s landlord. It required the first certificate by the end of the inspection period and the updated one between 30 and 10 days before closing.

Illustration of a land parcel and surrounding landscape

Compare the updated certificate with the original

Put the certifications side by side and record each change, its effective date and the evidence behind it. Check whether it involves a default, amendment, payment or other fact that matters to the sale. Ask the certifying party to explain unclear wording and have counsel review how the purchase agreement treats each change.

Check which notice or election is due and who can give it. Review the actual ground lease, proposed assignment, consents and title commitment alongside the purchase agreement. A changed certificate may raise a distinct question about the lease or equipment. Give the closing team the supporting records before telling the buyer what can be delivered.

Check which closing choices the contract gives the buyer

In the Shafter amendment, a material change in the solar landlord’s certifications limited the buyer to the remedies listed for that change. It could terminate by written notice and pay the earnest money to the seller, close without a price adjustment while giving up the solar assignment and equipment acquisition rights, or close at the agreed price with the seller’s continuing undertaking to address the change or default.

Each purchase agreement sets its own choices. Before releasing closing documents or earnest money, confirm the buyer’s written election, the closing date and whether the solar interest and equipment will be delivered, excluded or addressed after closing.

Path in the signed exampleClosing item to confirm
TerminateWritten notice, recipient of earnest money and escrow instructions
Close with the solar rights excludedAssets omitted, assignment and equipment documents, and price treatment
Close with a continuing seller undertakingOpen issues, required efforts, proof of resolution and later assignment steps

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Document what happens if you close before a cure

Under the Shafter amendment’s continuing-cure path, the seller would use reasonable best efforts to restore the changed certifications or cure defaults raised by the updated certificate. That obligation would survive closing. If those efforts succeeded, the buyer would accept the solar lease assignment. If they did not succeed, the clause allowed the buyer to accept the updated certificate as submitted.

If your agreement permits this path, identify the work, who is responsible, what will count as proof of a cure and who will prepare the later assignment. Check what happens if the issue remains open and agree which notices and signatures are needed. Have the title and closing teams record what transfers at closing and what is still outstanding.

Discuss an existing solar agreement in a land transaction

Sunland welcomes nationwide inquiries from owners and authorized representatives about land sales, leases and assignments of existing solar agreements. Share the approximate location, which interest you hold and how the updated certificate affects your expected closing. Keep signed agreements, certificates and closing papers for private review.

Questions landowners ask

Does a changed solar estoppel mean the sale must stop?

Check which changes the purchase agreement treats as material and what remedies it gives. The signed Shafter amendment described both termination and possible ways to close.

If we close before a cure, does the solar assignment go through at the same time?

Check the written election, the assigned rights and the closing instructions. If the assignment depends on a later cure, document what will establish it and who will complete the transfer.

Can the seller expect a price adjustment or keep the deposit?

Check how your purchase agreement treats the price and earnest money for the remedy actually elected. The Shafter amendment called for payment of earnest money to the seller under its written termination option and no price adjustment under the two specified closing options.

Sources & further reading

The signed sale agreement and amendments were checked November 20, 2026. The filed estoppel is an unsigned form. The underlying ground lease, signed estoppels and any exercise of a remedy were unavailable for review. Local rules and program details can change. Check the requirements for the actual project.