Identify the land and your interest first
Gather the tract number or legal description, any ownership or probate documents, and any existing leases or maps. Ask the realty office to identify the land status, the current owners and their undivided interests, and whether a pending probate or other title issue affects the record. An undivided interest is a share in the tract; it does not by itself identify a particular field or give one owner authority to lease the entire tract.
A mailing address, reservation boundary or family description alone does not establish whether land is individually owned trust or restricted land, Tribal trust land or fee land. A project may cross more than one tract or status. Have the appropriate office check each affected area, including roads and electrical routes.

Know whose consent counts
For a fractionated tract outside Alaska, 25 CFR 162.012 sets consent thresholds by the number of owners of undivided trust or restricted interests: 90% of those interests for one to five owners, 80% for six to ten, 60% for 11 to 19, and over 50% for 20 or more. These are percentages of interests, not a vote by headcount. In Alaska, the rule requires consent of all Indian landowners in the tract. BIA determines owner counts and interests from its records as of submission for approval.
Under the rule, a lease with the applicable consent can bind non-consenting owners; a non-consenting Tribe is bound only with respect to its fractional interest and is not treated as a party to the lease. A prospective lessee must notify all Indian landowners of a fractionated tract and obtain the applicable consent. Ask the realty office how the rule applies to the actual ownership record rather than calculating from a family list.
Adult Indian landowners and emancipated minors may consent. Section 162.013 also identifies representatives who may consent and limited circumstances in which BIA may consent in writing on an owner’s behalf, including certain unresolved estates or unknown whereabouts. These are not blanket authority for a developer or another family member to sign for you. Ask the office and your lawyer about representation and any applicable exceptions.
Separate consent from lease approval
For a proposed solar resource lease covered by Part 162, Subpart E, the prospective lessee negotiates with landowners, prepares the required information and analyses with them, and submits the lease package to the BIA office with jurisdiction for review and approval. Owner consent is not itself BIA approval. Environmental and cultural resource requirements are part of the review; ask what remains outstanding and who is responsible for each step.
Subpart E covers specified wind and solar resource leases, including generating electricity for resale, a public-serving grid or local community users. If generation solely supports another approved agricultural, residential or business use on the same parcel, a different subpart applies. Ask the realty office to classify the actual proposal and any separate access or right-of-way needs.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landDistinguish Tribal land and fee land
Tribal trust or restricted land has a different ownership and consent context from an individually owned tract. Under the HEARTH Act, a Tribe with approved regulations may approve covered leases of eligible Tribal trust or restricted land under those regulations without further Interior approval. BIA says HEARTH regulations do not apply to individually held trust land, fee land or fractionated interests. A Tribe’s participation or a tract’s location on a reservation does not by itself make a proposed individual-land lease a HEARTH lease.
Fee land follows a different title and leasing analysis. Do not assume that either the Part 162 process or a private fee-land template fits every parcel. Ask the realty office and qualified counsel to identify the governing authority, including any applicable Tribal rules and tract-specific exceptions.
Review the whole proposal before signing
Request the proposed lease, a dated map showing the leased area and access and electrical routes, and an explanation of the schedule. Ask how rent is calculated, allocated and paid to interest owners; what happens during development and construction; and whether the agreement limits other uses or grants rights to another company. A quoted project rent is not necessarily the amount payable to your individual interest.
Review protection of current uses and culturally important places, notice of entry, insurance, performance security, removal and restoration, and what happens if the project does not proceed. Ask how changes, assignment, extensions and release of rights work. A separate access request or option can have consequences before a lease is approved, so have it reviewed too.
You can contact Sunland about a potential solar opportunity with the general location and that the land may be individually owned trust or restricted land. Confirm the title and process with the realty office before sharing sensitive ownership records. An inquiry does not authorize entry or commit any owner to a lease.
Questions landowners ask
Can I lease the tract if I own an undivided interest?
Your interest alone may not provide the required consent for the tract. Ask the realty office to verify the record and applicable threshold; BIA approval is a separate step.
Does every owner have to sign?
Not always. Section 162.012 provides percentage thresholds for fractionated tracts outside Alaska; leases in Alaska require consent of all Indian landowners in the tract. Authorized representatives and specified BIA consent can also matter.
Does HEARTH Act approval replace BIA approval for my individual interest?
BIA states that Tribal HEARTH regulations do not apply to individually held trust land or fractionated interests. Confirm the status and applicable process for each tract.
Sources & further reading
BIA leasing, wind and solar, and HEARTH summaries and the text of 25 CFR 162.010, 162.012, 162.013 and 162.501 were checked November 16, 2026. This is general guidance; land status, title, special authorities, governing law and project approvals require tract-specific review. Local rules and program details can change. Check the requirements for the actual project.