Compare the payment bases
Fixed acreage rent generally multiplies an agreed annual dollar amount per acre by the acres defined in the lease. Confirm whether those are all leased acres, occupied acres or another mapped area, and when the operating payment begins. A production payment instead changes with measured energy over a period. Nameplate capacity, measured in megawatts (MW), describes generating capacity; it is not energy produced over time, measured in megawatt-hours (MWh) or kilowatt-hours (kWh). One MWh equals 1,000 kWh.
Two production formulas are materially different: measured MWh multiplied by an agreed dollar amount per MWh, or a percentage of a defined amount of actual electricity revenue. The first depends on measured energy and the contracted rate; the second also depends on the price received and the definition of revenue and deductions. NYSERDA describes several possible royalty bases and suggests considering a minimum; its discussion is New York guidance, not a nationwide rate schedule. DOE notes that lease payments vary with project size, location and negotiated terms.

Reconcile a sample meter settlement
Suppose a hypothetical lease pays $4 per MWh of net energy delivered at a specified revenue meter. An annual statement shows an opening cumulative reading of 10,000 MWh and a closing reading of 22,500 MWh. The difference is 12,500 MWh, or 12,500,000 kWh. At $4 per MWh, production rent is 12,500 × $4 = $50,000 for that year. If the agreed annual minimum is $45,000 and the lease pays the greater of the minimum or production rent, the payment is $50,000, not $95,000. If production rent were $40,000, the payment would be $45,000 under that same example.
For comparison only, a separate hypothetical revenue-share formula might pay 5% of defined gross electricity receipts. If the same 12,500 MWh yielded $500,000 in eligible receipts, the payment would be $25,000. That is not $4 per MWh and is not automatically a share of all project income. Specify which sales and periods count, how credits, negative prices, refunds and permitted deductions are treated, and whether the percentage applies to gross or a precisely defined net amount. The example assumes no adjustments; these figures do not establish a market rate.
Define the meter and the statement
Identify the meter, its location, ownership and units, the production period and whether payment uses generation at the array or net energy delivered after onsite use and losses. If a project spans multiple parcels or shares a meter, define the allocation to this land and what happens after expansion or equipment changes. State the conversion and rounding rules, calibration and testing standards, replacement-meter process and a documented method for estimating output when readings are missing or inaccurate.
Request periodic statements showing opening and closing readings, meter adjustments, eligible MWh, the rate or revenue calculation, minimum-payment reconciliation and amount due. For a revenue share, ask for the underlying sales and settlement records needed to verify the defined receipts and deductions, subject to reasonable confidentiality. Negotiate timely access to records, a right to inspect or have an independent auditor inspect them, a dispute window, correction and payment deadlines, and who pays audit costs if a material error is found.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landAddress downtime and a minimum
Cloud cover, equipment failure, maintenance, curtailment or grid outages can reduce measured output. Ask the developer for low, expected and high annual projections and their assumptions, including degradation, losses and downtime. A forecast is not a guarantee. Decide whether the lease pays only for metered output or includes a defined adjustment for particular outages or curtailment; specify how any estimated energy is calculated and supported, and avoid counting the same energy twice.
A negotiable minimum can limit a low-output year’s rent risk. Define its amount, start date, payment schedule and whether it applies during construction, outages, curtailment, partial years or a shutdown. Clarify whether it is a floor against production rent, an additional payment or an advance credited against later production payments. A minimum is only as useful as the obligation and payment security behind it; review the tenant’s obligations and any guaranty or other security with counsel.
Compare complete offers over the same term
Put both offers on the same timeline, acreage and payment schedule, including option and construction periods, operating years and extensions. Compare fixed rent with production payments in low, expected and high cases, including the minimum and any agreed adjustments. Review taxes, access and restoration costs, assignment, payment security and termination rights separately. Inflation adjustments and ownership of renewable energy certificates are distinct lease terms; do not assume a production formula resolves either.
Have a lawyer and financial adviser familiar with solar leases review the formula and risks before signing. Sunland welcomes solar land sale, lease and existing project inquiries nationwide. Share the location, approximate acreage and proposed payment structure; keep detailed financial records private until needed for a secure review.
Questions landowners ask
Is production-based rent the same as a share of electricity revenue?
Not necessarily. A rate per MWh uses measured energy and an agreed rate; a revenue share applies a percentage to receipts defined in the lease.
Does a minimum payment get added to production rent?
Only if the lease says so. A minimum can instead be a floor or an advance credited against later payments. Define the calculation and timing explicitly.
What happens if the solar facility stops producing?
The lease determines the payment. Negotiate whether a minimum, an estimated-output adjustment or another provision applies during specified outages or curtailment.
Sources & further reading
Sources checked 2026-11-15. Local rules and program details can change. Check the requirements for the actual project.