Gather the records before comparing proposals
Ask the owner or operator for the closure certification, final cover design and as-built drawings, current post-closure care plan, inspection and settlement records, and maps of waste limits, access roads and environmental systems. Find out who holds title, who is responsible for care and which agency oversees the site.
EPA explains that the post-closure plan describes monitoring, maintenance and planned property uses. The applicable requirements and care period depend on the site and agency; older landfills and different waste types may have different rules. Ask the responsible agency to confirm the status and any restrictions recorded against the property.

Compare the layout with the cover and settlement history
Give the developer the cover drawings, grades, drainage and settlement history. Ask a qualified landfill engineer how foundations, ballasted equipment, trenching, vehicle loads and future settlement would affect the cover and drainage. A nonpenetrating design may be considered, but it still needs site-specific engineering and agency review.
Request a plan showing panels, foundations, electrical routes, construction staging and areas reserved for inspection and repair. Ask how the cover would be protected during construction and restored if damaged.
Keep landfill systems accessible
Map gas wells and piping, vents, leachate systems, groundwater monitoring points and drainage features. Ask the operator and designer to identify clearance and access needs for equipment, sampling, repairs and emergency work throughout the solar term.
Ask who will coordinate and pay for modifications or repairs if the solar installation interferes with care. A lease or sale should allocate access and responsibilities explicitly; have counsel and the landfill operator review the actual documents.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landAsk the agency and utility about the proposal
Ask the agency overseeing the landfill what information, approvals or changes to the post-closure plan are needed for the specific layout. Separately ask the utility about the applicable interconnection process. Nearby power lines or a completed closure do not establish available capacity or approval.
If you control a property or project opportunity, Sunland welcomes inquiries nationwide. Share the location, your relationship to the site, the closure status if known and whether you are considering a sale, lease or existing agreement. An inquiry is an initial review, not a commitment.
Questions landowners ask
Does closure mean monitoring has ended?
Not necessarily. Ask the operator and overseeing agency for the current post-closure obligations and duration for the specific site.
Can solar foundations penetrate the landfill cover?
The design and applicable approvals require review by the landfill engineer and overseeing agency. Do not assume that any foundation type is acceptable.
Who should provide landfill records?
Start with the owner or operator and the agency overseeing the site. They can identify the current plans and responsible contacts.