Landowner guide

What happens to conservation planning when solar uses part of a highly erodible field?

A solar proposal may use only part of a working field while the rest stays in crops. Roads, fences, grading and new field edges can change how the remaining acres are farmed and how erosion controls work. Check the field records and the proposed footprint together before promising access or possession.

The short answer

Ask the operator and local USDA Service Center for the current field map, highly erodible land determination and applicable conservation plan or system. Overlay the solar work and access areas on those records, then discuss the remaining cropped acreage and proposed management with the Farm Service Agency (FSA) and Natural Resources Conservation Service (NRCS). Document the transition and responsibilities in the sale or lease.

Find the field record and the people affected

Start with the owner, tenant and anyone who operates the field or participates in USDA programs. Ask for farm, tract and field numbers, the current FSA map, crop and management history, the existing HEL determination and map, and any conservation plan or approved system. Obtain the operator’s permission where needed to share or discuss their records. A tax parcel, solar lease boundary and FSA field are not necessarily the same area.

NRCS determines highly erodible land on a field basis. Its determination includes Form NRCS-CPA-026 and a map identifying HEL and non-HEL fields. Ask FSA for the most current determination if one exists; a soil map alone is not a substitute. NRCS says a change in field boundaries with FSA may lead to a new determination. Do not assume that cutting a field in two automatically changes its classification.

Illustration of a land parcel and surrounding landscape

Test the proposed footprint against the remaining farm

On one dated map, show the existing field boundary and conservation features alongside the proposed leased or sold area, panels, fence, gates, road, trench, staging, grading and temporary construction access. Mark waterways, buffers, terraces, drainage routes and other features in the plan, as well as the acres and routes the operator would still cultivate. Include areas outside the final fence that construction equipment may disturb.

Walk through how machinery will turn and reach the remaining crop, where runoff will go and whether residue management, rotations, grassed waterways or other existing measures can still function. A narrow remnant or interrupted terrace may require a different approach. Ask FSA how to report any boundary or land-use change and ask NRCS to evaluate proposed management of the remaining cropped HEL before access, earthwork or changes to conservation measures. Record their advice and any updated plan or determination; allow time for the process.

Separate benefit eligibility from project permissions

For most USDA programs, participating agricultural producers with HEL must manage HEL fields under an approved conservation plan or system. NRCS explains that participants planting or producing agricultural commodities on HEL must follow an approved plan or maintain an approved system; participants self-certify on Form AD-1026. Ask FSA and NRCS how the proposed change affects the particular participant and acreage. The owner and operator may be different people and may have different program interests.

HELC conservation compliance concerns eligibility for USDA benefits; it is not itself a general solar construction permit or a blanket approval of the project. Separately identify any state or local siting, erosion-control, stormwater or other permissions applicable to the work. NRCS’s utility-scale solar guide offers voluntary conservation considerations throughout a project’s life; it does not replace applicable regulations or the field-specific conservation plan.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Check existing conservation commitments

An HEL conservation plan and a financial assistance contract are distinct records. Ask the operator and owner whether an Environmental Quality Incentives Program (EQIP) or other conservation contract, easement or cost-share commitment covers the proposed work or the remaining field. Obtain the contract, amendments, practice locations, schedules and maintenance obligations, with appropriate consent.

Before altering a covered practice or transferring control, the participant should review the actual agreement and proposed change with NRCS. Ask whether a modification, transfer or other action is available, what documentation is needed, and whether payments or repayment could be affected. Do not assume the solar buyer or tenant automatically takes over the participant’s obligations. Coordinate this issue with the operator’s existing lease and the solar transaction.

Put the transition into the sale or lease

Have counsel reconcile the solar agreement with the farm tenancy, farm access and conservation commitments. For a lease, distinguish limited survey entry from exclusive possession and construction; for a sale, address closing, possession and any retained rights. Set a reviewed map and process for changes, access routes and timing around crops and conservation work. Specify who contacts the agencies, who pays for agreed protective or revised measures, who maintains them, and what happens if the proposed footprint or timing cannot be made workable.

At handover, compare the final layout with the farm and conservation records and give the operator, owner and project parties the information each needs. Revisit the analysis if roads, fence lines, drainage or the cropped area change later.

Discuss the opportunity with Sunland

Sunland considers solar land opportunities nationwide, including potential sales and leases. Share the location, approximate acreage, working-field layout and known conservation constraints, with permission before sharing another participant’s records.

Ask what land, access and timing the proposal needs and how it would accommodate the remaining farm. Sunland may contract for an opportunity and assign it to a specialist. A discussion alone does not grant access or establish project approval, a utility connection or a completed transaction.

Questions landowners ask

Does a solar boundary automatically remove HEL status?

No. HEL is determined on a field basis, and NRCS may make a new determination when a producer changes field boundaries with FSA. Ask the agencies about the actual field and proposed change.

Can the remaining acres stay in crops?

Possibly. Review the layout, access and erosion controls with the operator and NRCS, including any applicable conservation plan or system and program requirements.

Is an HEL conservation plan the same as an EQIP contract?

No. An HEL plan or system addresses conservation compliance for participating producers. EQIP is a separate financial assistance program; review any actual contract and proposed changes with NRCS.

Sources & further reading

Sources checked 2026-11-17. Local rules and program details can change. Check the requirements for the actual project.