Landowner guide

Can I promise a solar collector route across a TVA flowage easement?

Before promising a solar collector route, compare the proposed cable and construction footprint with the recorded TVA flowage easement and your project agreement. A route through the easement may require TVA approval, and the easement’s terms and other property rights still matter. Ask the developer and counsel to verify the route and necessary rights before you commit.

The short answer

Obtain the recorded easement and title documents, the option or lease and its exhibits, and a surveyed route overlay showing the easement limits and all proposed work. Ask TVA whether the particular facilities and activities require section 26a approval and what to submit. A TVA permit conveys no property interest; the developer also needs the appropriate land rights for the actual route.

Put the route on the title picture

Ask for a current title commitment or report, the recorded TVA flowage easement and referenced documents, survey and legal descriptions. Have a surveyor locate the easement boundaries and any elevation limits using the actual instruments. Compare these with the option or lease, route exhibits, amendments and any existing utility or access easements. An approximate map or a line on a marketing plan does not establish the legal boundary.

Request an overlay of the proposed collector line, poles or equipment, trench and workspace, access, staging, grading and restoration areas. Show parcel boundaries, ownership, TVA interests and other crossings. Identify where the route leaves your land and who controls each segment. A buried line and the equipment or temporary work needed to install it may affect different areas.

Illustration of a land parcel and surrounding landscape

Ask TVA about the proposed crossing

The flowage easement provisions address privately owned shoreland where TVA holds flood rights. Under 18 CFR 1304.300, a structure built on land subject to a TVA flowage easement is deemed an obstruction under section 26a. Section 1304.301 provides for utility lines in the easement area upon application to and approval by TVA. It sets conditions for power lines, poles, electrical panels and wiring, including avoiding public hazards and interference with TVA operations and complying with state and local electrical codes. Its electrical-service provision also addresses disconnect elevation and flood-event access.

Give TVA the actual route, facility design and work footprint and ask which requirements and approvals apply, including to temporary work. The general section 26a rules can also apply to certain obstructions along or in the Tennessee River or its tributaries; TVA-owned land raises different land-right questions. Do not assume that a location in the watershed alone establishes that this flowage-easement provision applies, or that a proposed crossing will be approved.

Separate permission from property rights

TVA’s section 26a regulations state that a permit conveys no property interest. For a facility on private land, section 1304.2 generally requires the applicant to own the fee or have an adequate leasehold or easement interest where the facility will be located. For a facility on TVA land, the rule has separate adjoining-land requirements. Ask TVA and counsel about the actual ownership and any additional rights needed; the permit does not settle title or replace a grant from the party controlling the land.

The regulation also preserves the rights of the United States or TVA under a flowage easement. Have counsel review the recorded terms and priority of interests, not just the regulatory permit. Ask the developer which party will secure any required property interests and approvals, pay for the work, and handle a route that crosses a neighbor’s land or another existing easement.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Make the commitment match the evidence

Before signing, ask counsel to compare any promise to provide a route with the exhibits and the rights you actually control. Address who prepares and updates the survey, applies to TVA and obtains other consents, pays costs, and bears delay or denial. Consider how a changed alignment, approval conditions or an unavailable crossing will be handled, including any consent, alternative route, termination or restoration terms appropriate to the agreement.

An owner or authorized representative can ask Sunland to screen a solar sale or lease, or submit an existing project or agreement for review. Share the location, approximate acreage and known route or easement issue; provide title and agreement documents privately when requested.

Questions landowners ask

Does TVA approval give the developer an easement?

No. TVA’s regulations say a section 26a permit conveys no property interest. Verify the land rights needed for each segment separately.

Does every solar parcel in the Tennessee Valley have a TVA flowage easement?

No. Check the recorded instruments and survey for the specific property, then ask TVA about the proposed facilities and activities.

Can the route change after an application?

A changed alignment can affect land rights and approvals. Ask TVA and counsel how to handle the change before work begins, and check the agreement’s route-change terms.

Sources & further reading

Sources checked 2026-11-16. Local rules and program details can change. Check the requirements for the actual project.