South Dakota landowner guide

Is my South Dakota solar agreement still binding after five years without panels?

An empty field and a new solar offer can make an older agreement seem finished. South Dakota’s development rule requires a closer look: the relevant construction event may have occurred on another property in the same solar project or construction stage.

Could my land work?

Gather the signed instruments and dates, then request evidence of when and where the first photovoltaic panel mounting system was installed for the associated project or stage. Ask South Dakota counsel to evaluate the applicable law and agreement, and work with the title company on any remaining recorded rights before making a conflicting commitment.

Find the rights and the date that matters

Start with the complete solar lease or easement, exhibits, amendments, notices, assignments and any recorded memorandum. Compare the land descriptions and project name across the documents. An option, access agreement or separate cable easement may grant different rights and may have its own deadlines. A short recorded memorandum may not contain all the terms needed to decide what remains in force.

South Dakota’s definition of a solar easement covers certain rights designed to ensure sunlight for a photovoltaic system or an agreement to refrain from developing one, regardless of whether the right is described as an easement, restriction, option to obtain an easement, covenant or condition. It does not follow that every ordinary option to buy land is a statutory solar easement. Ask counsel to classify each actual instrument.

Illustration of a land parcel and surrounding landscape

Apply the five-year rule to the correct instrument

Under the current text of section 43-13-17, a covered solar easement is void if the associated potential to produce solar energy has not been developed within five years after the easement’s effective date. Section 43-13-19 addresses covered leases of solar resource rights and says a lease is void if the required development has not occurred within five years after the lease began. These provisions use different starting language; a signature date, option date, recording date and lease commencement date are not necessarily interchangeable.

Build a timeline with the documents that establish each date, including any exercise notices or amendments. Ask South Dakota counsel which statutory version applies to an older instrument and how its facts and terms affect the analysis. The current statute alone does not resolve every historical agreement or establish whether a particular right is void.

Look beyond your own field for the construction event

Section 43-13-20.2 defines solar development for these provisions as installation of the mounting system for the first photovoltaic panel on any property that is part of one solar energy project or any single construction stage of a solar energy project. The event can therefore occur away from your parcel. The statute identifies the mounting system event; it does not require an installed or energized panel on your land, or commercial operation.

For example, your field may still be farmed while the first mounting system was installed on a different tract within the associated project or construction stage during the applicable period. That could satisfy the statutory development definition. Conversely, equipment visible at an unrelated nearby project does not by itself establish the required connection. Permits, surveys, payments and an interconnection queue position are useful context, but alone do not establish the specified installation event.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Request a construction record you can check

Ask the current agreement holder for its written position on the project, construction stage and date of the first mounting-system installation. Request dated construction reports, contractor or inspection records and plans showing the location and legal description. Ask for documents connecting that location to the project or stage associated with your agreement, including any changes to project boundaries or names.

Put the claimed installation date beside the legally relevant start date and five-year period. Note missing records and conflicting dates rather than filling gaps with assumptions. Give the full record to counsel: whether the construction and project relationship satisfy the statute is a fact-specific question, and a developer’s statement or an aerial photograph alone may leave important questions unanswered.

Resolve the agreement and title before a new commitment

Identify the current holder and any assignment or lender interests from the agreements and title records. If the parties agree the rights have ended, ask counsel and the title company what documentation and recording are appropriate for this property. The statutory voidness language does not itself tell you what a title company will require to address an existing recorded claim.

If the holder disputes termination, seek legal advice on resolving the dispute before signing a competing lease or promising a buyer unencumbered land. Do not block access or remove equipment on the assumption that the agreement has ended. The statute also contains a twelve-year development extension for qualifying wind developers; that provision is not a solar extension.

Keep payments, restoration and other rights in view

Review accrued payments, notices, site damage, equipment and restoration duties separately with counsel. Collect payment history, photographs and correspondence. A decision about the statutory development event does not automatically settle every payment or restoration dispute, and a proposed settlement may affect more than one claim.

Read separate road, cable, utility and access instruments individually rather than assuming they end with the solar lease. If you plan to sell, tell the buyer and title company about the agreement and share the status evidence. Ask how closing documents will address unresolved rights, payments and any required consents.

Discuss the property and existing agreement

Sunland welcomes nationwide solar land sale, lease and existing agreement inquiries from owners and authorized representatives. Describe the South Dakota location, approximate acreage, existing agreement and what you hope to do. You can discuss the property while its status is being reviewed; an inquiry does not cancel existing rights.

Sunland may contract for a property or agreement and then assign its interest to a specialist, subject to the actual terms and required consents. Provide the agreement and supporting records privately when appropriate, and have your own counsel review any proposed transaction.

Questions landowners ask

Does an empty field prove my solar lease is void after five years?

No. The qualifying first photovoltaic panel mounting system may have been installed on another property in the associated project or single construction stage. The applicable instrument, start date, development evidence and law require review.

Must a solar panel be producing electricity within five years?

The current statutory definition identifies installation of the mounting system for the first photovoltaic panel. It does not require an energized panel or commercial operation as that event.

Can I sign a new solar lease once five years have passed?

First have South Dakota counsel assess the existing rights and evidence, and ask the title company how any recorded claim must be addressed. Resolve a dispute or required release before making a conflicting commitment.

Sources & further reading

Current South Dakota statute checked November 18, 2026. No individual agreement, construction record or title history was reviewed. Counsel should check the applicable statutory version and facts for an existing instrument. Local rules and program details can change. Check the requirements for the actual project.

Want to ask about your land?

Send the location and what you know about the property. You don’t need a project plan, and you are not committing to a lease or sale.