South Carolina · Data centers

Could a missed community benefit payment affect a Jones Road data center sale?

Sources checked

Check payment status and title before closing

The version of the Jones Road development agreement in Spartanburg County’s November 16 final agenda packet gives the County a lien against the project real estate if 300 Jones Road Associates LLC defaults on required community benefit payments. The packet schedules the first payment within 30 days after the company receives all required development approvals, subject to the agreement’s conditions. Before setting a closing date, have your attorney compare the signed agreement and payment records with an updated title search. If the County has recorded a lien, make the County’s written payoff and release terms part of the closing.

If you are buying the 430 Jones Road data center property or taking over its development agreement, ask Spartanburg County which community benefit payments have come due and whether it has sent a default notice or recorded a lien.

Match the parcel and find the date that starts the payments

Spartanburg County Council gave final reading on November 16, 2026 to the ordinance authorizing the 430 Jones Road development agreement. Exhibit A in the final agenda packet identifies tax parcel 3-08-00-085.00 and references the survey re-recorded in Plat Book 184, Page 427. Compare the legal description in the signed agreement and your proposed deed. If the deal covers only part of the site, ask which instrument establishes how the agreement applies to that piece.

Exhibit C in the packet schedules six payments of $1.5 million. The first falls within 30 days after the company receives all required development approvals, and five more fall on the first through fifth anniversaries of the initial payment. Ask the County and seller for the required approval list, the date the last approval was received and receipts for any installments due. Use the executed agreement and any amendments to confirm the schedule.

Sources WYFF, November 16 Spartanburg County Council vote · Spartanburg County final agenda packet, Jones Road agreement Exhibit A · Jones Road agreement Exhibit C, community benefit payment schedule · Jones Road agreement Articles XVI and XVII, recordation and survival

Check the County’s payment records and the recorded title

Article XII in the packet gives the company ten days to cure a monetary default after written notice. It gives the County a lien for the unpaid commitment if the company defaults on the community benefit contributions. Article XVII says an established lien remains against the company’s interest in the Exhibit A property after a sale or assignment and that the County may record a notice of lien. Ask the County for written payment and default status and ask your closing attorney to search for the agreement, amendments, notices and releases.

What the records showWhat to resolve before closing
The first payment date depends on outstanding approvalsGet the County’s approval list and put responsibility for future installments in the purchase agreement.
The County has sent a written default noticeGet the notice date and the County’s cure amount. Decide who will pay and what written confirmation the buyer needs before closing.
The title search shows a recorded notice of lienGet written payoff and release terms from the County. Have your closing attorney confirm when the release will be recorded and what the title policy will cover.

Sources Jones Road agreement Exhibit C, community benefit payment schedule · Jones Road agreement Article XII, written notice and cure · Jones Road agreement Articles XII and XIV, lien and assignment · Jones Road agreement Article XVII, effect of sale on established lien · Spartanburg County Register of Deeds, records and copies

Document who pays before and after the transfer

If your purchase includes an assignment of the development agreement, ask the County to confirm any consent or notice requirements for your transaction. Article XIV calls for County consent, with affiliate provisions in the agreement. It also requires the assignee to deliver a written assumption and the company to give the County written notice within ten days of assignment. The company remains responsible for obligations accrued before the assignment. Under Article XVII, if the conditions precedent to the company’s obligations have been satisfied and the company proceeds with the project, those obligations remain enforceable against it after a sale or assignment. South Carolina Code section 6-31-120 applies the agreement’s burdens and benefits to successors in interest.

Have your closing attorney list accrued, disputed and future installments separately and attach the County documents your closing depends on. For example, if the seller receives a default notice between signing and closing, you can make closing contingent on written confirmation of cure and, if a lien has been recorded, a release acceptable to the title insurer. If a payment will come due after closing, specify who pays it and how the other party gets proof.

Sources Jones Road agreement Article XII, written notice and cure · Jones Road agreement Articles XII and XIV, lien and assignment · Jones Road agreement Articles XVI and XVII, recordation and survival · Jones Road agreement Article XVII, effect of sale on established lien · South Carolina Local Government Development Agreement Act, section 6-31-120

Common questions

Does the November 16 council vote start the first community benefit payment deadline?

Exhibit C in the final agenda packet ties the first payment to receipt of all required development approvals. Ask the County to confirm which approvals are required and when the company received the last one.

Where do I look for a recorded agreement, lien or release?

Use the Spartanburg County Register of Deeds. Ask your closing attorney to search the parcel’s title and obtain the relevant instruments. Request payment and default status from the County separately.

Does a transfer resolve a lien on the project property?

The agenda-packet agreement says an established lien remains against the company’s interest in the Exhibit A property after transfer. If a lien appears in the title search, confirm the County’s payoff and release terms before you close.

Sources

The final agenda packet contains unsigned agreement text. Request the executed agreement, any amendments and current payment or lien records for the transaction.