Identify the pond and the authorization first
WQG100000 concerns eligible industrial and water treatment facilities disposing of wastewater by evaporation from ponds or surface impoundments adjacent to water in the state. TCEQ renewed the permit effective September 15, 2025; existing permittees had to submit a new Notice of Intent (NOI) within 90 days to maintain coverage. Obtain the current authorization and acknowledgment, not just an old permit number. Some facilities instead need an individual permit, whose terms require separate review.
A stormwater basin or detention pond is not automatically a wastewater evaporation pond. The general permit does not authorize stormwater otherwise covered by the listed stormwater permits, and it excludes oil and gas facility evaporation ponds regulated by the Railroad Commission of Texas. Identify the pond’s purpose, waste streams, responsible agency and actual permit before applying this guide.

Put the transition and termination provisions together
Part II.C.4 says the existing owner and operator submit a Notice of Termination (NOT), and the new owner and operator submit an NOI, for a change in the regulated entity’s owner or operator. It says the notices must be submitted at least 10 days before the change to avoid a lapse in authorization. A private deed, lease or assignment does not transfer the agency authorization. A change in other NOI information may instead require a Notice of Change; ownership or operator changes require the NOT and new NOI under the permit.
Part II.D also states that, unless termination follows authorization under an individual or alternative general permit, the NOT must include certification that all evaporation ponds have been properly closed under Part III.B.3. It sets a separate deadline of within 10 days after closure is completed or an individual or alternative general permit is obtained. These provisions must be read together for the proposed facts. Do not assume every land sale mandates pond demolition, or that a new NOI alone permits the existing pond to continue without addressing the certification condition.
Give TCEQ the proposed sale or lease boundary, pond and facility boundaries, current and proposed owner and operator, intended wastewater operations, and transaction date. Ask whether the transaction changes the regulated entity’s owner or operator, which notices and timing apply, and how the termination certification requirement is satisfied if the pond is to continue operating. Obtain the agency’s site-specific direction before setting the handover schedule.
If use of a pond ends, examine closure obligations
Part III.B.3 treats discontinued use of any pond regulated by the general permit as a closure activity. It requires an onsite closure plan and compliance with applicable waste and risk-reduction rules. The plan includes an inventory and closure schedule. Depending on the applicable waste rules, advance written notice may be required before closure work; the permit also calls for a final closure report and certification by a Texas licensed professional engineer, signed by the owner and operator.
Ask the permittee and qualified environmental professionals for the plan, schedule, applicable notices, investigation and final report, and certifications. A pond that looks dry is not proof that closure is complete or that the area is suitable for foundations, roads or cable. A completed closure also does not by itself establish that the proposed battery use is authorized or technically feasible.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landMap the handover and preserve operating access
Gather the current NOI and acknowledgment, notices of change and termination, permit correspondence, pond design and liner records, site drawings, waste stream and inventory information, inspection and monitoring records, release or corrective action reports, and any closure plans, schedules and certifications. Map ponds, liners, buffers, pipes, monitoring points and access alongside the proposed battery equipment, construction areas, roads, drainage and utility route. Ask a surveyor and environmental advisers to resolve uncertain boundaries.
If an existing operator is to remain, identify the area and rights it needs for direct control, inspections, maintenance, monitoring, emergency response and eventual closure. The permit requires the permittee to maintain direct responsibility and control over the wastewater storage and disposal system. A carveout or retained access provision can be discussed, but whether it works depends on the actual facility, permit and transaction. Ask TCEQ to review the proposed arrangement.
Allocate obligations before agreeing on possession
With counsel, specify who remains responsible for operations and compliance, who pays for investigations and closure, who can enter the property, and how long access and funding must continue. Address notice and approval conditions, the consequences of delay, indemnities, insurance, environmental findings and the rights needed if a layout changes. Contract language allocates obligations between parties; it does not replace TCEQ authorization or relieve a permittee of applicable duties.
Sunland welcomes land sale, lease and existing agreement inquiries from owners and authorized representatives across the United States. Share the location, acreage, proposed boundary, known pond status and relevant agreements. Sunland may contract for a parcel and later assign the agreement to a specialist developer, subject to its actual terms. Agency review, environmental diligence and project suitability remain separate questions.
Questions landowners ask
Can the pond permit simply transfer with the land?
No. WQG100000 says authorization is not transferable and specifies notices for a change in owner or operator. Ask TCEQ how those provisions and the termination certification apply to the proposed transaction.
Must every sale include physical closure of the pond?
Do not assume that from the sale alone. Determine whether the transaction changes the regulated entity’s owner or operator, whether the pond will continue in use, and how TCEQ applies the notice and certification provisions to the actual arrangement.
Can battery equipment be built on a drained pond?
A drained appearance does not establish completed closure or site suitability. Review the closure record and proposed work with qualified professionals and the relevant agencies before committing to the layout.
Can the old operator stay on part of the tract?
A retained operating area and access may be worth discussing. Map the arrangement and ask TCEQ how the permit and notice requirements apply; the permittee must retain direct responsibility and control of the wastewater system.
Does this permit cover every pond in Texas?
No. Verify the pond’s purpose and authorization. WQG100000 has specific industrial and water treatment coverage and excludes certain stormwater and oil and gas ponds.
Sources & further reading
TCEQ coverage guidance and the 2025 issued permit, including Parts II.C.4–5, II.D and III.B.3, checked November 17, 2026. Ask TCEQ to resolve their application to the specific proposed transition. Local rules and program details can change. Check the requirements for the actual project.