Start with the property and the actual agreement
Identify the parcel by legal description and map the proposed equipment, access, utility corridor, drainage and construction area. Request the zone ordinance and amendments, current boundary map, project and financing plans, and any agreement specifically covering the tract or its development. Ask the city or county TIRZ administrator for the executed agreement, exhibits, all amendments, notices, approvals and any successor or assignment documents. A summary or a proposed agreement may omit terms that matter.
Texas Tax Code Chapter 311 allows municipalities or counties and zone boards to enter certain development agreements and provide for use of tax increment revenue. The Comptroller describes tax increment financing as a way to fund zone improvements. Being inside a TIRZ does not, by itself, establish that this owner is owed reimbursement or has agreed to build a project. Identify the parties, covered land, beneficiaries and source of each asserted right or duty in the actual documents.

Test the battery plan against use commitments
Obtain a current title commitment and exceptions, deeds, recorded covenants, easements, plats and any memorandum or recorded development restrictions. Have counsel and a surveyor compare their legal descriptions with the site plan and proposed lease or sale area. Check required uses, building locations, landscaping, access and shared infrastructure, as well as restrictions on changes to an approved plan. An agreement may bind a signatory personally, while a recorded covenant or other property interest may affect a later owner; the documents and applicable law determine the result.
Ask the administrator and local planning staff whether the specific BESS layout requires a plan amendment, zoning or other land-use approvals, or consent under a private agreement. The TIRZ agreement is only one review: the project team must also investigate interconnection, fire and emergency access, permits and other site constraints. Do not assume a favorable zoning answer changes a private covenant, or that an agreement approval replaces a permit.
Separate payments from land and ongoing obligations
Request a written accounting of approved project costs, amounts paid, claimed but unpaid amounts, caps, payment sources and remaining conditions. Compare it with the agreement, evidence of completed work, invoices and notices of default. Check construction and completion milestones, reporting duties, cure periods, repayment or clawback provisions and who remains responsible for unfinished improvements. Future reimbursement may depend on eligible costs, performance, available revenue and the agreement; a projected amount is not a guaranteed payment.
A sale conveys whatever real property interest the deed describes; an assignment of a reimbursement receivable transfers the specified payment right, subject to its terms. Neither automatically transfers the other, and a transfer of payment rights does not necessarily release the original developer from performance. A Missouri City Development Authority agenda packet illustrates the distinction: a proposed assignment to a bank concerned eligible reimbursement proceeds while stating that the developer would continue its agreement obligations. That local example is not a rule for other agreements, and the packet alone should not be treated as proof of final execution.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landPlan the transfer and any partial release
Check assignment, lease, conveyance, change-of-control and lender provisions separately. Identify who must consent, whether approval must precede signing or closing, what notice and documents are required, and whether the transferee must assume obligations. Ask counsel whether the seller remains liable after a transfer and whether an express release is available. A buyer, tenant, lender or project company may have a different role under the agreement; name the proposed party accurately when seeking consent.
If only part of the tract is offered, ask whether a partial-parcel release is permitted and who can grant it. Provide a survey and legal description of the released and retained areas, proposed access and utility easements, and a plan for any shared obligations. Negotiate how payments, remaining performance, security and maintenance are allocated, and obtain any required recorded release or amendment. A subdivision or separate lease description alone does not establish that the parcel has been released.
Keep the transaction conditional while facts are confirmed
Ask the TIRZ administrator for the zone’s current status and any outstanding agreement obligations, then have counsel review the actual termination and survival language. Zone termination does not itself prove that every recorded covenant or contractual obligation has been released. Request copies of releases or satisfaction documents and check the property records.
Before signing, align investigation time, consent and permit contingencies, payment allocation, costs and termination rights with the findings. Sunland welcomes land sale, lease and existing project or agreement inquiries from owners and authorized representatives nationwide, including Texas battery storage opportunities. Share the location and acreage if known and provide agreements privately if requested. Sunland may contract for an opportunity and then assign it to a specialist; a transaction, approval or incentive is not guaranteed.
Questions landowners ask
Does TIRZ membership guarantee battery storage incentives?
No. Zone location alone does not establish a payment right. Review the relevant agreement, eligible costs, conditions and funding with the administering authority and counsel.
Does assigning reimbursement release the developer from its obligations?
Not necessarily. Payment rights and performance duties are distinct. The governing documents and any approved assumption or release determine what changes.
Can I lease only part of the tract for batteries?
Possibly. Check the covered property, restrictions, transfer provisions and whether a partial release, amendment, survey or approvals are needed for the proposed footprint.
Sources & further reading
Sources checked 2026-11-17. Local rules and program details can change. Check the requirements for the actual project.