Map the project against enrolled land
Collect the recorded Current Use application, enrollment map, deed, parcel and SPAN information, and any forest management plan. Ask the developer for a scaled plan showing panels, fencing, access roads, equipment, trenches, grading, clearing and temporary work areas. Compare it with enrolled and excluded land, and ask PVR and, for forestland, the county forester which areas must be removed or managed differently. A project boundary, tax parcel and enrolled boundary may not match.
Do not assume the fence line alone defines the changed acreage. Ask PVR to review the actual work and proposed withdrawal map, including access and infrastructure. A partial program withdrawal is not itself a subdivision or a substitute for a required permit.

Distinguish withdrawal from development
An owner may withdraw all or part of enrolled land. Under Vermont law, land use change tax is not due merely because land becomes ineligible if no development has occurred. The Department of Taxes says an owner who withdraws undeveloped land owes no tax at withdrawal, but tax is due if it is developed later. Withdrawn or developed land is thereafter appraised and listed at full fair market value under the applicable rules, so ask the local assessor about future annual property taxes.
Development under 32 V.S.A. § 3752 includes construction of a building, road or other structure and mining, excavation or landfill activity, subject to exceptions. It can also include certain subdivisions and forest management violations. Notify the PVR director immediately if enrolled land is developed. Do not treat filing a withdrawal as a way to eliminate tax on later development.
Check solar and farm exceptions carefully
The statute excludes the location of a solar generation facility in the aggregate on 0.1 acre or less from development, provided the underlying land qualifies as agricultural land or as open land qualifying as managed forestland under the Commissioner of Forests, Parks and Recreation’s standards. The acreage limit and underlying-land conditions matter; do not assume a larger commercial installation qualifies or that separate related work is covered.
The statute also excludes certain structures for farming, logging, forestry or conservation purposes. The Department’s solar bulletin explains that a qualifying farm improvement may remain eligible: among other conditions it must be actively used by a farmer as part of a farming operation. The bulletin presumes this relationship where at least 50% of generation is used by enrolled farm buildings, while allowing further evidence in other cases. This is a fact-specific eligibility determination, not a blanket exemption for solar on a farm. Discuss the full facility and its use with PVR.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landSubmit a partial withdrawal and protect the remainder
The owner can file Form LV-314 by mail or through myVTax. The form distinguishes acreage withdrawn and developed from acreage withdrawn but not developed. For a partial withdrawal, the department requires three copies of a map meeting Current Use Mapping Standards before processing; its online instructions say to mail those maps separately. Confirm the current instructions, descriptions, acreage and signatures with PVR before filing.
Ask PVR whether the remaining land still meets acreage, use and management requirements and whether a revised map or plan is needed. Keep farming certifications current and discuss proposed clearing, access and any management-plan changes with the county forester. A sale or other transfer raises separate enrollment questions: the department says a new application is required within 30 days for transferred land to remain enrolled and for any portion retained by the original owner to continue enrollment.
Budget for tax and the recorded lien
When taxable development occurs, § 3757 generally imposes land use change tax at 10% of the full fair market value of the changed land. For part of a parcel, the changed land is valued as a separate parcel and the assessment is divided by the common level of appraisal. The determination is made as of the date the land is no longer eligible. This is separate from annual property tax. Review the valuation notice and appeal deadline promptly; the statute generally allows 30 days to appeal the determination.
Enrollment creates a recorded notice of contingent lien. Withdrawal without development does not automatically clear it: the obligation runs with the land, and future development can trigger tax. The department says an owner can voluntarily pay the tax to release the lien before development. Ask PVR and a Vermont title professional about the precise acreage, payment, release and recording steps; do not assume a release for the project footprint clears the remainder.
Put the allocation in the lease
Ask the developer for the final footprint, schedule and estimated Current Use and property tax consequences. Have Vermont counsel and a tax adviser review who pays the land use change tax, valuation or appeal costs, recording fees and increased annual taxes; address changes in design, access, restoration and impacts on the retained farm or forest. Coordinate these terms with any mortgage, existing lease or conservation restriction and obtain separate project approvals as required.
Sunland welcomes Vermont solar land sale, lease and existing project inquiries. Share the approximate location, acreage and whether Current Use covers the proposed footprint; keep sensitive title and tax records for secure review.
Questions landowners ask
Does withdrawing land before solar construction avoid land use change tax?
Not necessarily. Withdrawal without development does not itself trigger the tax, but the contingent lien and future obligation can remain. Later taxable development can make the tax due.
Can the rest of the property remain in Current Use?
Potentially, if the remaining land continues to satisfy the program’s acreage, use and management requirements. Confirm the map and eligibility with PVR and the county forester where applicable.
Is a small solar facility always exempt?
No. The statutory exclusion applies to a facility in the aggregate on 0.1 acre or less only when the underlying land satisfies the specified agricultural or managed-forest open-land conditions. Ask PVR about the whole project and any other work.
Sources & further reading
Sources checked 2026-11-16. Local rules and program details can change. Check the requirements for the actual project.
- Vermont Department of Taxes: withdrawal
- Vermont Department of Taxes: Form LV-314
- Vermont Department of Taxes: filing Form LV-314 in myVTax
- Vermont Department of Taxes: Current Use enrollee information
- Vermont Department of Taxes: solar facilities on Current Use land, TB-69
- Vermont statutes: 32 V.S.A. § 3752
- Vermont statutes: 32 V.S.A. § 3757