Confirm who owns the solar system
Get the CPG number, certificate, approved layout and any amendments. Compare the CPG holder with the current owner of the property and the party shown as owning the equipment in the purchase, lease or financing records. The Commission's net-metering transfer form asks for the existing certificate number, system location and host property owner. Use those identifiers to match the array in the deal to the array in the Commission record.
If a solar company owns the equipment and leases space on your farm, check the lease and equipment exhibits before describing the array as part of a land sale. When the buyer is acquiring the land subject to a continuing solar lease, ask the Commission and the utility what records to update and have counsel confirm what the buyer takes under the lease. This guide covers certificates under Vermont's net-metering rule. Check the project's own authorization if the array was approved under a different program.

Put the right transfer step on the closing checklist
When the buyer acquires the host property and the net-metering system together, Rule 5.110(A) treats the CPG as automatically transferred. The new owner must give written notice to the electric utility to continue operating the system. The Commission's transfer portal says the separate transfer form is unnecessary in this case. Ask the utility where to send the notice and how to confirm that it matched the certificate and meter to the new owner.
If the system changes owners independently of the host property, Rule 5.110(B) requires the current holder to be in compliance with the certificate and the new holder to comply with the certificate and Rule 5.100. The new system owner must file the official transfer form within 30 days of acquiring the system. The Commission's ePUC portal sends filing notice to the Department of Public Service and the electric utility, and also to the Agency of Natural Resources for a ground-mounted system. Collect the current holder's signed certification before closing and have the buyer retain the ePUC filing confirmation.
Check whether the approved system matches what is on the property
Compare the latest approved plans with the array today, including any added rows, moved inverters or other changes. The separate-transfer form asks the new holder to certify that the system matches the approved system and has had no material changes. If the records and installation differ, identify the changes and ask the Commission whether an amendment or other action is needed before the transfer. Rule 5.109 sets out the amendment process.
If a deal includes equipment or an unbuilt project with a CPG, ask for the commissioning record or the filed extension. Under Rule 5.110(C), a CPG is revoked after one year of nonuse following issuance unless extended, and commissioning is what counts as use. The holder can obtain a one-year extension by giving the Commission and the electric utility written notice before the anniversary, with further extensions subject to a timely request and good cause. Confirm current certificate status before assigning value to an unbuilt system.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landCheck the utility and contract records separately
Make a closing list for the certificate, utility accounts and any private agreements. Ask the utility whose account receives the credits, what meter or group records need updating, and how the utility will handle credits around the closing date. If a farm or business participates in group net metering, compare the group's meter and allocation records with the sale documents and ask the utility how and when a change can take effect. Have counsel review any host lease, access easement or lender consent that affects the changes you are proposing.
Sunland welcomes land sale, lease and existing solar agreement inquiries nationwide. Share the property location and whether your proposed deal includes the land, the array or an existing agreement. Arrange to provide certificates and agreement copies privately if needed.
Questions landowners ask
Do I file with the Commission if I buy the land and solar array together?
The Commission's net-metering transfer portal says the separate transfer form is unnecessary when ownership of the system changes with the property. As the buyer, provide written notice to the utility to continue operating the system and keep a copy for your closing records.
Who files if the operator buys only the array?
The new system owner files the Commission's official transfer form within 30 days after acquiring the system. Collect the current holder's signed certification and identify the system's location, utility and existing CPG number before closing.
Is there a special transfer procedure for older net-metered arrays?
Rule 5.125(H) includes the transfer provisions of Rule 5.110 among the rules that apply to qualifying pre-existing net-metering systems. Ask the utility about the system's billing treatment using its commissioning date and CPG number.
Sources & further reading
Sources checked 2026-11-19. Local rules and program details can change. Check the requirements for the actual project.
- Vermont Public Utility Commission Rule 5.100, sections 5.109, 5.110, 5.125, 5.129 and 5.130
- Vermont Public Utility Commission ePUC net-metering transfer instructions and form
- Vermont Statutes section 8010, self-generation and net metering
- Vermont Rule 5.100 text, Cornell Legal Information Institute copy