Virginia landowner guide

What should a landowner check before signing a battery equipment lender’s fixture waiver?

A battery storage tenant’s equipment lender may ask the landowner to sign a fixture waiver or access consent. The document can affect competing rights in equipment and access to the land after a default. Compare it with the lease, the equipment list and the property’s existing obligations before signing.

Could my land work?

Ask for the proposed waiver, the lease and a schedule and site plan identifying the financed equipment and removal route. Have Virginia counsel review ownership, fixture priority, access, notice, repair and security for removal costs alongside existing mortgages and other agreements. A lender’s interest in equipment is not automatically ownership of the land, but the terms signed can matter.

Identify the goods and the land

Request a schedule and plan showing the battery units, inverters, transformers, cables, foundations, fencing and other improvements. Ask who owns or leases each item, what the lender claims as collateral, which items it may remove and what must remain. Include shared equipment and connections, not just the battery containers. Some items may be goods that become fixtures; classification depends on the facts and applicable law, not just a label in the waiver.

Compare the schedule and plan with the lease, amendments, site restoration obligations, title and recorded mortgages or easements. Ask counsel to identify the borrower, the property owner, the secured party and other parties with interests. Virginia Code § 8.9A-334 permits security interests in fixtures but says an Article 9 security interest does not exist in ordinary building materials incorporated into an improvement on land. Do not assume every foundation, cable or other component falls into the same category.

Illustration of a land parcel and surrounding landscape

Read the priority and consent language

A request to consent, disclaim an interest, subordinate a claim or recognize a right to remove equipment can change the owner’s position. Under § 8.9A-334, fixture priority depends on the facts and several rules. For example, a security interest in fixtures, whether or not perfected, has priority over the conflicting interest of an owner or encumbrancer who signed a record consenting to the security interest or disclaiming an interest in the goods as fixtures. The statute also addresses priority where the debtor has a right to remove goods against that owner or encumbrancer.

Have counsel examine exactly which goods and interests the proposed language covers and how it interacts with the lease and other recorded interests. The landowner’s consent alone does not establish the lender’s priority over every other owner or encumbrancer. Ask whether a mortgage lender’s consent or other documentation is needed under existing agreements.

Plan for access and removal after default

Under § 8.9A-604(c), subject to the other provisions of that part, a secured party with a security interest in fixtures that has priority over all owners and encumbrancers of the real property may remove the collateral after default. Whether those conditions are met requires a fact-specific review. The waiver may also contain contractual access or removal terms; have counsel compare them with statutory rights and the lease.

Identify the proposed route, gate access, notice and hours, safety procedures, insurance, utility disconnection, contractors, deadlines and responsibility for damage. Ask how removal affects shared roads, underground cables and retained land uses, and how an interrupted removal or abandoned equipment will be handled. Coordinate any necessary utility and regulatory steps with the project team.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Address repair and the cost of an incomplete site

Section 8.9A-604(d) requires a secured party that removes collateral to promptly reimburse an owner or encumbrancer of the real property other than the debtor for the cost of repairing physical injury caused by removal. It does not require reimbursement for a decrease in real-property value caused by the goods’ absence or the need to replace them. A person entitled to reimbursement may refuse permission to remove until the secured party gives adequate assurance that it will perform that reimbursement obligation.

Discuss with counsel how the documents address physical repair, remaining foundations or cables, replacement or lost site value, and any broader restoration obligation. Ask what assurance, insurance or other security is proposed and how it works with the tenant’s obligations; the statute’s repair provision is not the same as a complete decommissioning plan. Sunland welcomes land and existing project inquiries nationwide. Share the location and your relationship to the property, and provide the lease and financing documents privately if requested.

Questions landowners ask

Does a fixture waiver give the lender the land?

Not necessarily. It may address priority in goods, access and removal. Have counsel review the actual document and its relationship to the lease and property records.

Can the lender remove fixtures after default?

Virginia Code § 8.9A-604(c) allows removal subject to the other provisions of the part when the secured party has priority over all owners and encumbrancers of the real property. Contractual terms and the facts also need review.

Must the lender restore the site to its former value?

Section 8.9A-604(d) requires prompt reimbursement of eligible non-debtor owners or encumbrancers for repair of physical injury caused by removal, but excludes diminished value caused by absence of the goods or the need to replace them. Review any additional contractual obligations.

Can an owner request assurance before removal?

A person entitled to reimbursement under § 8.9A-604(d) may refuse permission to remove until the secured party gives adequate assurance of its reimbursement obligation. Ask counsel how that applies to the particular situation and document.

Sources & further reading

Sources checked 2026-11-16. Local rules and program details can change. Check the requirements for the actual project.