Start with the permit and the system
Obtain the complete individual permit, modifications, fact sheet, discharge monitoring reports, inspection and enforcement correspondence, fee records and plans for the treatment equipment and outfalls. Identify the legal entity named on the permit, the property owner, the operator and any contractor. These may be different parties. Map the treatment system, pipes and access alongside the proposed battery layout.
Ask an environmental adviser what is still discharged or managed, what monitoring and reporting remain due, and whether the permit is active even though industrial production has stopped. A battery project may have different wastewater and stormwater needs. Determine with DEQ whether the existing discharge will continue, change or cease, and whether transfer, modification or eventual termination is appropriate. Do not assume that inactivity or a land sale ends permit obligations.

Set a transfer date before closing
Under 9VAC25-31-380, the ordinary route requires modification, revocation and reissuance, or a minor modification identifying the new permittee and incorporating other necessary requirements. Alternatively, automatic transfer is available if all regulatory conditions are met. The current permittee must notify DEQ at least 30 days before the proposed transfer date, and the notice must include a written agreement between existing and new permittees specifying the date responsibility, coverage and liability transfer between them.
Automatic transfer also requires that DEQ not notify both parties of its intent to modify or revoke and reissue the permit, and that the new owner or operator demonstrate compliance with 9VAC25-650-70 if applicable. If that notice of intent is not received and the conditions are met, the transfer is effective on the agreement’s specified date. A purchase contract or deed alone is not that notice and agreement. Discuss the route and submission with the regional office; retain proof of delivery and DEQ correspondence.
Use the individual permit form and check its scope
DEQ publishes an individual VPDES permit change-of-ownership agreement form addressed to its regional office. It asks for the permit and facility, anticipated transfer date, current owner and proposed new entity, authorized signatures and annual fee information. It asks the new owner to accept the permit conditions and responsibilities. The form says it will not be processed until all fees are paid. Ask DEQ whether the current form and any accompanying agreement or documents satisfy the chosen transfer route, including the specific responsibility, coverage and liability date.
The form also asks about financial assurance for certain privately owned sewerage systems treating sewage from permanent private residences. Chapter 650 is not a blanket requirement for every industrial wastewater facility: it applies to privately owned systems subject to the VPDES regulation that treat sewage from private residences and discharge more than 1,000 and less than 40,000 gallons per day to state waters, and the form distinguishes industrial facilities that do not serve as permanent residences. If the site also has a qualifying residential sewage system, ask DEQ whether 9VAC25-650-70 applies. If it does, that rule requires certified-mail notice at least 30 days before the sale or transfer and new-owner compliance and DEQ approval of the financial mechanism before permit transfer.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landMake the handoff workable
Have counsel coordinate the closing date, permit transfer date and actual control of the treatment system. If closing moves, consult DEQ and revise the signed agreement and notice as appropriate; do not assume the original date follows the closing automatically. Agree who operates, samples, reports, pays fees, maintains access and responds to problems through the transition. Address records, outstanding issues and costs in the sale documents, while recognizing that private allocations do not themselves change regulatory obligations.
If the buyer does not intend to operate the system, ask DEQ what must happen before the discharge and permit can be terminated and who is responsible in the meantime. Construction stormwater and other authorizations are separate questions. Sunland welcomes land and existing project inquiries nationwide. Share the property location, approximate acreage, your relationship to it and the permit issue; provide permit records privately if requested.
Questions landowners ask
Does the individual VPDES permit transfer with the deed?
Not automatically because of the deed. A transfer must follow an available route under 9VAC25-31-380, including the notice, agreement and other conditions for automatic transfer, or an appropriate permit modification or reissuance.
Can the transfer date simply be the closing date?
It can be coordinated with closing, but the written agreement must state a specific date and the automatic transfer conditions must be met. If the closing changes, consult DEQ promptly about the agreement and notice.
Does every industrial facility need Chapter 650 financial assurance?
No. Chapter 650 concerns certain privately owned systems treating sewage from private residences. Ask DEQ whether a separate residential sewage system at the property falls within its scope.
Sources & further reading
Sources checked 2026-11-16. Local rules and program details can change. Check the requirements for the actual project.
- Virginia Administrative Code: 9VAC25-31-380, transfer of VPDES permits
- Virginia Administrative Code: 9VAC25-650-20, purpose
- Virginia Administrative Code: 9VAC25-650-30, applicability
- Virginia Administrative Code: 9VAC25-650-70, transfer of ownership or permit
- Virginia DEQ: Individual VPDES permit change of ownership agreement
- Virginia DEQ: VPDES permit writers’ manual